Project Manual_IFB 27-07_Montgomery County Fire & EMS Headquarters Montgomery County Fire & EMS Headquarters 305 Roanoke Street Christiansburg, VA 24073 October 22, 2026 Project Manual Contract Documents Owner: Montgomery County 755 Roanoke Street Christiansburg, VA 24073 Architect: Local Studio Architecture and Design, PLLC 336 N Washington Ave Pulaski, VA 24301 (540) 250-4139 Local Studio Project Number: 2317B Montgomery County VA Bid Request No. 27-07 Montgomery County Cover Page Fire & EMS Headquarters Page 2 of 286 Consulting Engineers Civil Engineering: Foresight Design Services 1260 Radford Street Christiansburg, VA 24073 (540) 381-6011 Structural Engineering: Truesdell Engineering, Inc. 613 Country Club Drive SE Blacksburg, VA 24060 (540) 552-7090 Plumbing and Mechanical Engineering: MDR Engineering, LLC P.O. Box 20812 Roanoke, VA 24018 (540) 915-1576 Electrical Engineering: Gibson Engineering 2100 Lubna Drive Christiansburg, VA 24073 (540) 998-6069 Montgomery County Table of Contents Fire & EMS Headquarters Page 3 of 286 Table of Contents Part I General Requirements Invitation for Bids Instructions to Bidders: AIA A701-2018 Terms and Conditions of Bid Pre-Bid Question Form Part II Bid Submittal Documents Bid Form Bid Bond: AIA A310-2010 Debarment and Suspension Certification Part III Conditions of the Contract General Conditions of the Contract for Construction: AIA A201-2017 Part IV Contract Forms Notice of Award Standard Form of Agreement Between Owner and Contractor: AIA A101-2017 Exhibit A – Insurance and Bond Requirements Performance Bond: AIA A312 Payment Bond: AIA A312 Worker’s Compensation Certificate of Coverage DGS-30-076 Notice to Proceed Application and Certificate for Payment: AIA G702 / G703 General Contractor Estimate for Change Order DGS-30-200 Contract Change Order: AIA G701 Certificate of Substantial Completion: AIA G704 Certificate of Completion by Architect / Engineer DGS-30-112 Certificate of Completion by Contractor DGS-30-136 Contractor’s Affidavit of Payment of Debts and Claims: AIA G706 Contractor’s Affidavit of Release of Liens: AIA G706A Consent of Surety to Final Payment: AIA G707 Montgomery County Table of Contents Fire & EMS Headquarters Page 4 of 286 Part V General Requirements 011000 – Summary 012100 – Allowances 012200 – Unit Prices 012300 – Alternates 012500 – Substitution Procedures 012600 – Contract Modification Procedures 012900 – Payment Procedures 013100 – Project Management and Coordination 013200 – Construction Progress Documentation 013300 – Submittal Procedures 014000 – Quality Requirements 014200 – References 015000 – Temporary Facilities and Controls 016000 – Product Requirements 017300 – Execution 017419 – Construction Waste Management and Disposal 017700 – Closeout Procedures 017823 – Operation and Maintenance Data 017839 – Project Record Documents 017900 – Demonstration and Training Part VI Reference Documents Statement of Special Inspections, September 30, 2026 Backwater Valve Certification, October 6, 2026 Lead & Asbestos Inspection Report, April 23, 2025 Station Alerting System Plan by US Digital Designs, May 21, 2026 Station Alerting System Rough-in Specifications by US Digital Designs, No Date Montgomery County Part I – General Requirements Fire & EMS Headquarters Page 5 of 286 Part I – General Requirements Montgomery County Invitation for Bids Fire & EMS Headquarters Page 6 of 286 Invitation for Bids For Montgomery County Fire & EMS Headquarters Montgomery County VA Bid Request No. 27-07 Sealed bids for construction of the Montgomery County Fire & EMS Headquarters, will be received in person, via regular mail by U.S. Postal Service, or via special courier service at the Purchasing Office in the Montgomery County Government Center; 755 Roanoke Street, Suite 2C, Christiansburg, VA, 24073, until but no later than 3:00 PM Prevailing Eastern Time, December 10, 2026, and then publicly opened and read immediately thereafter. Bids received after the announced time and date for submittal, whether by mail or otherwise, will be rejected. Bidders are responsible for ensuring their Bid is received before the deadline indicated. Bids submitted by telephone, text message, email, or facsimile shall not be accepted. Bidders may choose to submit electronic copies through the eVA Electronic Submission process by the date and time identified herein. Bidders should still submit the sealed paper copy described above. In order to submit an electronic bid, the bidder must be properly registered with eVA. Registration may be accomplished through this site: https://eva.virginia.gov/register- now.html. It is strongly encouraged that registration be completed well in advance of the submission deadline to avoid any delays in the process. Montgomery County will not be able to assist bidders with their submissions. Bidders must contact eVA with any questions or needs for assistance with submission. Upon successful submission, the bidder should receive confirmation of the submission through eVA. The County will not confirm receipt of the proposal. For a tutorial on how to view and respond to a solicitation, visit: https://www.youtube.com/watch?v=KSxcAkOekW0. Montgomery County is not responsible for delays, miscommunications, or transmission errors that may occur during the electronic submission process. This includes, but is not limited to, issues related to internet connectivity, email servers, or other technical malfunctions. It is the sole responsibility of the Bidder to ensure the proposal is submitted on time. The Work generally consists of the complete interior renovation of the approximately 8,000 square foot building located at 305 Roanoke Street in Christiansburg, Virginia, as well as some exterior improvements. The proposed use of the space is for an administrative facility for the Montgomery County Department of Fire and EMS to include a lobby, offices, conference room, training room, storage rooms, break room, and toilet rooms. The property will also include space for on-call response personnel in the Fire and EMS departments to include sleep rooms, locker room, shower rooms, day room, apparatus bays, pharmacy, and storage rooms. Support spaces include a utility room and an IT / Electrical room. The County’s Mobile Command Unit vehicle will be housed on the property as well. The renovation Work consists of significant modifications to the existing building structural systems; the removal of the existing plumbing, mechanical, Montgomery County Invitation for Bids Fire & EMS Headquarters Page 7 of 286 and electrical systems and replacement with new systems throughout; new interior finishes throughout; new exterior windows and doors. A non-mandatory pre-bid conference will be held at 10:00 AM Prevailing Eastern Time, on November 5, 2026, in the Board Room on the second floor of the Montgomery County Government Center located at 755 Roanoke Street, Christiansburg, VA 24073, followed immediately by a site visit at the Project Location. Bidders may obtain Bidding Documents electronically by visiting: https://montva.com/1/departments-services/purchasing. Bidders must notify Local Studio via email at mcfemshq@localstudiova.com to be recognized as a Planholder. Only Bidders or entities who follow the process outlined above will be considered Planholders. All others who obtain electronic Bid Documents or hard/paper Bid Documents through other means, including Plan Rooms, other Contractors, Owner, or third-party websites (ConstructConnect, Dodge, iSqFt., etc) are not considered Planholders. Only Planholders will be notified of Addenda. Bidders may submit Pre-Bid Questions by submitting the Pre-Bid Question Form via email to mcfemshq@localstudiova.com. Questions/clarifications shall be submitted by 5:00 p.m. Prevailing Eastern Time on November 13, 2026. Responses will be in the form of addenda if required. Refer to the Instructions to Bidders for bidding procedures and requirements. Any questions related to accessing or viewing the Bidding Documents shall be directed to Local Studio via email at mcfemshq@localstudiova.com. Submit Pre-Bid Question Forms via the process outlined above. END OF INVITATION FOR BIDS Montgomery County Terms and Conditions of Bid Fire & EMS Headquarters Page 31 of 286 Terms and Conditions of Bid By submitting a bid in response to this Solicitation, Contractor agrees to the following terms and conditions that shall apply to this procurement. A. Submittal of bid One copy of the completed bid form and certifications may be submitted by regular mail delivery (U.S. or private delivery service) or hand-delivered to the Purchasing Office in the Montgomery County Government Center; 755 Roanoke Street, Suite 2C, Christiansburg, VA, 24073. The County shall not accept bids by email transmittal. If forwarded by mail, the sealed envelope containing the Bid must be enclosed in another envelope addressed to the County at the above address. Sealed Bids may be submitted electronically through eVA (eVA.virginia.gov), but this is NOT a requirement. A hard copy of the bid and other required documents should be submitted by regular mail delivery or be hand delivered to the Purchasing Office in the Montgomery County Government Center. B. Deadline for County receipt Bids must be received by the County no later than: 3:00 PM Prevailing Eastern Time on December 10, 2026. Bids received after the deadline, postmark notwithstanding, shall be rejected. C. Form of bid a. Bid must be made using the form provided with this Solicitation. b. Bid must include signed certification regarding debarment and suspension using the form provided with this Solicitation. c. Sealed paper copies of bids submitted to the Montgomery County Purchasing Office must be in an envelope that is clearly marked: “Bid for Montgomery County Fire & EMS Headquarters” and shall bear on the outside the Bidder’s name, address, and license number. d. Bid must be signed by an official authorized to bind the Contractor. e. Sealed paper copies of bids must contain the following on the outside of the envelope containing the Bid: If a contract is for one hundred fifty thousand dollars ($150,000) or more, or if the total value of all construction, removal, repair, or improvements undertaken by the bidder within any twelve-month period is one million dollars ($1,000,000) or more, the bidder is required under Title 54.1, Chapter 11, Code of Virginia (1950) as amended, to show evidence of being licensed as a “Class A Contractor.” The bidder shall place on the outside of the envelope containing the Bid, and shall place in the Bid over his signature, the following notation: “Licensed Class A Virginia Contractor No. __________________” Montgomery County Terms and Conditions of Bid Fire & EMS Headquarters Page 32 of 286 D. Bid Bond or Guarantee Each bid shall be accompanied by surety in the form of a bid bond or letter of credit in the amount of five percent of the amount of the base bid, which shall be made payable to the Treasurer of Montgomery County. The surety provider must be legally authorized by the Virginia State Corporation Commission to do business in the Commonwealth of Virginia. Such bid surety shall be submitted with the understanding that it shall guarantee that the bidder will not withdraw such bid during the period of 30 days following the opening of bids; that if such bid is accepted, the bidder will accept and perform under the terms of the Invitation for Bids and purchase order or contract. The bid surety will be returned upon award of contract. E. Rejection if bid in improper form Contractor’s failure to submit a bid on the bid form provided with this Solicitation and with all information required by this Solicitation shall be a cause for rejection of the bid. Modification of or additions to any portion of the bid form may be cause for rejection of the bid; however, the County reserves the right to decide, on a case-by-case basis, in its sole discretion, whether to reject such a bid as nonresponsive. As a precondition to its acceptance, the County may, in its sole discretion, request that Contractor withdraw or modify non-responsive portions of a bid that do not affect quality, quantity, price, or delivery. The County may waive any informalities or minor defects or reject any and all bids. Any Bid may be modified or withdrawn prior to the scheduled time for the opening of bids or authorized postponement thereof. Any Bid received after the time and date specified shall not be considered. No Bidder may withdraw a Bid within 30 days after the actual date of the opening thereof except due to an error in accordance with provision “(i)” contained in 11-54(a), Code of Virginia (1950) as amended. Should there be reasons why the contract cannot be awarded within the specified period, the time may be extended by mutual agreement between the County and Bidder. F. Questions and modification Questions to clarify this Solicitation shall not be received or answered by telephone or in- person. Questions shall be submitted by email no later than 5:00 p.m. Prevailing Eastern Time on November 13, 2026 to Local Studio. The email must identify in the subject line: “Question Regarding Construction of Montgomery County Fire & EMS Headquarters.” Please complete the Pre-Bid Question Form provided with the Solicitation and submit to the email indicated. Responses to all questions will be issued via Addenda. All Contractors of whom the County is aware have interest in this Solicitation will be notified of the Addenda via email. There shall be no modification of the Solicitation except by written modification provided by the County. Any written modification will be provided by email to all Contractors of whom the County is aware have interest in this Solicitation. Montgomery County Terms and Conditions of Bid Fire & EMS Headquarters Page 33 of 286 G. Optional (Non-Mandatory) Pre-Bid Meeting An optional (non-mandatory) pre-bid meeting will be held at 10:00 AM Prevailing Eastern Time, on November 5, 2026, in the Board Room on the second floor of the Montgomery County Government Center located at 755 Roanoke Street, Christiansburg, VA 24073, followed immediately by a site visit at the Project Location; 305 Roanoke Street, Christiansburg, VA, 24073. The purpose of this meeting is to allow potential bidders an opportunity to visit the site and present questions relative to any facet of this solicitation. Any changes to the Bid Documents resulting from this meeting will be issued in a written addendum to the solicitation. While attendance at this meeting will not be a prerequisite to submitting a bid, bidders who intend to submit a bid are encouraged to attend. H. Inspection of job site and review of contract documents By submittal of a bid in response to this Solicitation, Contractor certifies that Contractor has inspected the job site and is aware of the conditions under which the work must be accomplished. Claims, as a result of failure to inspect the job site, will not be considered by the County. Contractor must satisfy themselves of the accuracy of the quantity of the Work by examination of the site and a review of the Contract Documents including Addenda. After bids have been submitted, the Contractor shall not assert that there was a misunderstanding concerning the quantities of work or of the nature of the work to be done. It is the responsibility of each Contractor before submitting a bid to (a) examine the Contract Documents thoroughly, (b) visit and inspect the site to become familiar with local conditions and perform additional investigations necessary to satisfy themselves as to surface and subsurface conditions, availability of utilities, and access roads as necessary that may affect the cost, progress, performance, or furnishing of the Work, (c) consider federal, state, and local laws and regulations that may affect cost, progress, performance, or furnishing of the Work, (d) study and carefully correlate Contractor’s observations with the Contract Documents, and (e) notify the County of all conflicts, errors, or discrepancies in the Contract Documents. The failure of any Contractor to do any of the foregoing shall in no way relieve any Contractor from any obligation in respect to its Bid. I. Period allowed for County acceptance of bid Any bid submitted in accordance with this solicitation shall be valid for 60 days after the bid submittal deadline. At the end of the 60-day period, the bid may be withdrawn at the written request of the Contractor. If the bid is not withdrawn at that time, it remains in effect until an award is made or the solicitation is cancelled. J. Interview Prior to making an award pursuant to this solicitation, the County reserves the right to require Contractor to interview with a County review committee to determine whether Contractor is fully qualified to provide the goods and services as set forth herein. The interview is intended to show that Contractor is fully qualified, that Contractor’s services will be provided in a completely satisfactory manner, and that Contractor is competent to meet or exceed the performance specifications. Failure by a Contractor to comply promptly with a request for interview may result in its bid being rejected. Montgomery County Terms and Conditions of Bid Fire & EMS Headquarters Page 34 of 286 K. Award The contract will be awarded to the lowest responsive and responsible bidder that demonstrates the qualifications as required by this solicitation. The award will be based on the Total Base Bid plus the Additive Bid Alternate, if selected. If the Additive Alternate is not selected, the award will be based on the Total Base Bid. The County reserves the right to conduct any tests it may deem advisable and to make all evaluations. The County reserves the right to reject any and all bids in whole or in part, to waive any informality, and to negotiate the bid price as permitted by Virginia Code § 2.2-4318 if the lowest responsive and responsible bid exceeds available funds. Failure of Contractor to execute a contract, provide certificate(s) of insurance, and, if required, file an acceptable performance security within 10 business days of the date of the approval for awarding of the contract as herein provided will be just and sufficient cause for denial of the award. The Contractor to whom the Contract is awarded will be required to execute the Contract and obtain acceptable performance and payment bonds and certificates of insurance and return four copies of these documents within ten (10) business days from the date when Notice of Award is delivered to the Contractor. The Notice of Award shall be accompanied by the necessary Contract forms. In case of failure of Contractor to execute the Contract, the County may consider the Contractor in default, in which case the Bid Bond accompanying the proposal shall become the property of the County. The County within twenty (20) days of receipt of an acceptable certificate of insurance, performance and payment bonds, and the Contract signed by the party to whom the Contract was awarded shall sign the Contract and return to such party an executed duplicate of the Contract. Should the County not execute the Contract within this twenty (20) day period, the Contractor may, by written notice, withdraw the signed Contract. Such notice of withdrawal shall be effective upon receipt of the notice by the County. This withdrawal is the only recourse available to the Contractor when the County fails to execute the contract within this specified time period. The Contractor cannot be reimbursed for any additional costs incurred if he does not, by written notice, withdraw the signed Contract. The Notice to Proceed shall be issued within ten (10) business days of the execution of the Contract by the County. Should there be reasons why the Notice to Proceed cannot be issued within such period; the time may be extended by mutual agreement between the County and Contractor. If the Notice to Proceed has not been issued within the period mutually agreed upon, the Contractor may terminate the Contract without further liability on the part of either party. L. Announcement of Decision to Award Following the announcement of the decision to award a contract as a result of this solicitation, the County will publicly post such notice on the County website at https://montva.com/1/departments-services/purchasing. Montgomery County Terms and Conditions of Bid Fire & EMS Headquarters Page 35 of 286 M. Performance Bond and Payment Bond A performance security instrument (bond or letter of credit) in the amount of 100 percent of the total contract price for materials and installation will be required of the Contractor prior to providing goods/services. The form of instrument to be provided as surety must be approved by the County. Failure to execute a contract and file an acceptable performance security and certificate of insurance within 10 business days of the date of the approval for awarding of the contract as herein provided, will be just and sufficient cause for the denial of the award. The performance bond will be released upon County’s written acceptance after final inspection and determination that the project was completed in compliance with contract specifications. N. Applicable laws and courts This solicitation and any resulting contract shall be governed in all respects by the law of the Commonwealth of Virginia, and any litigation with respect thereto shall be brought in the court of appropriate jurisdiction in Montgomery County, Virginia. The Contractor shall comply with all applicable federal, state and local laws, rules and regulations. All applicable laws, ordinances, and the rules and regulations of all authorities having jurisdiction over construction projects shall apply to the contract throughout. O. Ethics in public contracting By submitting their bid, Contractor certifies that their bid is made without collusion or fraud and that they have not offered or received any kickbacks or inducements from any other bidder, supplier, manufacturer, or subcontractor in connection with their bid, and that they have not conferred on any public employee having official responsibility for this procurement transaction any payment, loan, subscription, advance, deposit of money, services or anything of more than nominal value, present or promised, unless consideration of substantially equal or greater value was exchanged. P. Debarment status By submitting their bid, Contractor certifies that they are not currently debarred by the Commonwealth of Virginia or County of Montgomery, Virginia from submitting a response for the type of goods and/or services covered by this solicitation. Contractor further certifies that they are not debarred from filling any order or accepting any resulting order, or that they are an agent of any person or entity that is currently debarred by the Commonwealth of Virginia or County of Montgomery, Virginia. If a vendor is created or used for the purpose of circumventing a debarment decision against another vendor, the non-debarred vendor will be debarred for the same time period as the debarred vendor. Montgomery County Terms and Conditions of Bid Fire & EMS Headquarters Page 36 of 286 Q. Investigation of qualifications of contractor Contractor agrees to cooperate with such reasonable investigation as the County deems proper and necessary to determine the ability of Contractor to satisfy the terms of any contract that may be awarded pursuant to this Solicitation. Investigation may include inspection of Contractor’s physical facilities prior to award to satisfy questions regarding Contractor’s capabilities. Further, the County reserves the right to reject any bid if the evidence submitted by, or investigations of, such contractor fails to satisfy the County that such contractor is properly qualified to fulfill the obligations of the contract. R. Testing and inspection The County reserves the right to conduct any test/inspection it may deem advisable to assure goods and services conform to the specifications. S. Equal employment opportunity The Contractor agrees to abide by the requirements under Executive Order No. 11246, as amended, including specifically the provisions of equal opportunity. Executive Order No. 11246 requires affirmative action and prohibits contractors from discriminating on the basis of race, color, religion, sex, sexual orientation, gender identity, or national origin. Montgomery County Pre-Bid Question Form Fire & EMS Headquarters Page 37 of 286 Pre-Bid Question Form (Use a Separate Form for Each Question Submitted) Date: ________________________ Project Title: Montgomery County Fire & EMS Headquarters The following question concerns drawing sheet number(s), project manual section(s), or other project document(s): _____________________________________________________ The question is: ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ All responses to questions will be issued via Addendum. Question Submitted By: _______________________________________________________ Name Organization Bidders Shall Submit Form To: Braxton Cox Local Studio____________ Name Organization Email Address: mcfemshq@localstudiova.com Montgomery County Part II – Bid Submittal Documents Fire & EMS Headquarters Page 38 of 286 Part II – Bid Submittal Documents Montgomery County Bid Form Fire & EMS Headquarters Page 39 of 286 Bidder’s Name Bidder’s Address Bidder’s Address Bid Form Montgomery County Bid Request No.: 27-07 Date: _________________________ To: Montgomery County Purchasing Office 755 Roanoke Street, Suite 2C Christiansburg, VA; 24073 From: _________________________________ _________________________________ _________________________________ For: Montgomery County Fire & EMS Headquarters Having carefully examined the site, and all of the Bidding and Contract Documents, and in compliance with the “Invitation to Bid,” “Instructions to Bidders,” and “Supplementary Instructions to Bidders,” the undersigned proposes to provide all labor, materials, supplies, equipment, services, and perform all Work necessary for the construction of this Project in accordance with the Bid Documents, dated October 6, 2026 (Drawings) and October 22, 2026 (Project Manual), prepared by Local Studio Architecture and Design PLLC. Complete this Bid Form in blue or black ink or by computer. Discrepancies in the multiplications of units of work and the unit prices will be resolved in favor of the correct multiplication of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. PART A: BASE BID PRICE The Base Bid Price includes all Work required by and in strict accordance with the Bid Documents for this Project, for the Lump Sum of: $_____________________________________ (Figures only) Montgomery County Bid Form Fire & EMS Headquarters Page 40 of 286 PART B: Allowances (Reference Sections 012100 – Allowances) Note: Allowances are to be included in the Base Bid Price above. Allowance No. 1: Unsatisfactory soil excavation, disposal, and replacement (1,000 cu. yd.) $______________________________________ (Figures Only) Allowance No. 2: Mass rock removal and replacement (500 cu. yd.) $______________________________________ (Figures Only) Allowance No. 3: Trench rock removal and replacement (10 cu. yd.) $______________________________________ (Figures Only) Allowance No. 4: Partial repointing of existing brick veneer (1,500 sq. ft.) $______________________________________ (Figures Only) PART C: Unit Prices (Reference Sections 012100 – Allowances and 012200 – Unit Prices) Note: Unit prices are to be based on the allowances above. Unit Price No. 1: Unsatisfactory soil excavation, disposal, and replacement $______________________________________ (Figures Only) / cu. yd. Unit Price No. 2: Mass rock removal and replacement $______________________________________ (Figures Only) / cu. yd. Unit Price No. 3: Trench rock removal and replacement $______________________________________ (Figures Only) / cu. yd. Unit Price No. 4: Partial repointing of existing brick veneer $______________________________________ (Figures Only) / sq. ft. Montgomery County Bid Form Fire & EMS Headquarters Page 41 of 286 PART D: Alternates (Reference Sections 012100 – Allowances and 012300 – Alternates) Alternate No. 1: New Roof Structure Option A (Standing-Seam Metal Roof Panels System): $______________________________________ (Figures Only) Option B (Exposed-Fastener Metal Roof Panels System): $______________________________________ (Figures Only) Option C (Asphalt Shingle Roofing System): $______________________________________ (Figures Only) Alternate No. 2: Gas Fired Unit Heaters: $______________________________________ (Figures Only) RECEIPT OF ADDENDA We acknowledge the receipt of the following Addenda: Addendum No. _________, dated _________________________ Addendum No. _________, dated _________________________ Addendum No. _________, dated _________________________ Addendum No. _________, dated _________________________ TIME OF COMPLETION Based upon a Notice to Proceed within forty-five (45) calendar days from the opening of bid, Work included in this Contract shall be Substantially Complete no later than ten (10) calendar months from the Notice to Proceed and finally complete no later than thirty (30) calendar days thereafter. LIQUIDATED DAMAGES Liquidated Damages (refer to General Conditions for additional information): $500.00 per calendar day for failure to achieve the approved Substantial Completion date and $500.00 per calendar day for failure to achieve Final Completion within thirty (30) calendar days after the Substantial Completion date. Montgomery County Bid Form Fire & EMS Headquarters Page 42 of 286 REGISTRATION The undersigned is a licensed Class A Contractor in accordance with applicable state statutes and regulations, as amended, Certificated No. _______________________, dated ____/____/________. A Class A Contractor License is required for this project. A bid by a corporation shall further give the State of incorporation ___________________________, State Corporation Commission ID number _____________________________, and have the corporate seal affixed in the space provided herein. CERTIFICATION I certify that the firm name given below is the true and complete name of the Bidder and that the Bidder is legally qualified and licensed, to perform all Work included in the scope of the Contract. Legal Name of Bidder (Company) ________________________________________________________ Bidder’s (Company) Address ____________________________________________________________ Corporate Seal Signature _______________________________________________________________________ (Signature of person(s) legally authorized to bind Bidder (Company) to this Contract) By: _______________________________________________________________________ (Typed or printed Name(s) of Person(s) Signing) Title: _______________________________________________________________________ (Typed or printed Title(s) of Person(s) Signing) Telephone Number: (______)________________ E-mail(s):_______________________________ (Include Area Code) (of person(s) indicated above) (This form may be reproduced in exact detail.) END OF BID FORM AIA ® Document A310™ – 2010 Bid Bond AIA Document A310 – 2010. Copyright © 1963, 1970 and 2010. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 16:08:27 ET on 09/28/2026 under Order No.500072155_3 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (3B9ADA70) 1 ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification. Any singular reference to Contractor, Surety, Owner or other party shall be considered plural where applicable. ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document. CONTRACTOR: (Name, legal status and address) SURETY: (Name, legal status and principal place of business) « »« » « » « »« » « » OWNER: (Name, legal status and address) « Montgomery County, Virginia »««755 Roanoke Street «Suite 2E » «Christiansburg, Virginia 24073 » BOND AMOUNT: $ « » PROJECT: (Name, location or address, and Project number, if any) «Montgomery County Fire & EMS Headquarters » «Christiansburg, Virginia » « » The Contractor and Surety are bound to the Owner in the amount set forth above, for the payment of which the Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, as provided herein. The conditions of this Bond are such that if the Owner accepts the bid of the Contractor within the time specified in the bid documents, or within such time period as may be agreed to by the Owner and Contractor, and the Contractor either (1) enters into a contract with the Owner in accordance with the terms of such bid, and gives such bond or bonds as may be specified in the bidding or Contract Documents, with a surety admitted in the jurisdiction of the Project and otherwise acceptable to the Owner, for the faithful performance of such Contract and for the prompt payment of labor and material furnished in the prosecution thereof; or (2) pays to the Owner the difference, not to exceed the amount of this Bond, between the amount specified in said bid and such larger amount for which the Owner may in good faith contract with another party to perform the work covered by said bid, then this obligation shall be null and void, otherwise to remain in full force and effect. The Surety hereby waives any notice of an agreement between the Owner and Contractor to extend the time in which the Owner may accept the bid. Waiver of notice by the Surety shall not apply to any extension exceeding sixty (60) days in the aggregate beyond the time for acceptance of bids specified in the bid documents, and the Owner and Contractor shall obtain the Surety’s consent for an extension beyond sixty (60) days. If this Bond is issued in connection with a subcontractor’s bid to a Contractor, the term Contractor in this Bond shall be deemed to be Subcontractor and the term Owner shall be deemed to be Contractor. When this Bond has been furnished to comply with a statutory or other legal requirement in the location of the Project, any provision in this Bond conflicting with said statutory or legal requirement shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be deemed incorporated herein. When so furnished, the intent is that this Bond shall be construed as a statutory bond and not as a common law bond. Signed and sealed this « » day of « » , « » AIA Document A310 – 2010. Copyright © 1963, 1970 and 2010. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 16:08:27 ET on 09/28/2026 under Order No.500072155_3 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (3B9ADA70) 2 « » (Contractor as Principal) (Seal) « » « » (Witness) (Title) « » (Surety) (Seal) « » « » (Witness) (Title) Montgomery County Debarment and Suspension Certification Fire & EMS Headquarters Page 45 of 286 Signature of Contractor’s Authorized Oicial Name and Title of Contractor’s Authorized Oicial Date Debarment and Suspension Certification Certification Regarding Debarment, Suspension, and Other Responsibility Matters This certification is required by the regulations implementing Executive Order 12549, Debarment and Suspension, and 2 C.F.R. § 180.335, Participants’ responsibilities. The regulations were amended and published on August 31, 2005, in 70 Federal Register 51865- 51880. Copies of the regulations may be obtained by contacting the agency offering the proposed covered transaction. A) The prospective primary participant certifies to the best of its knowledge and belief, that it and its principals: (1) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency. (2) Have not within a three-year period preceding this bid been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violations of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification, or destruction of records, making false statements, or receiving stolen property; (3) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offenses enumerated in paragraph A.2. of this certification; and (4) Have not within a three-year period preceding this bid had one or more public transactions (Federal, State or local) terminated for cause or default. B) Where the prospective primary participant is unable to certify to any of the statements in this certification, such prospective participant shall attach an explanation to this bid. __________________________________________________ __________________________________________________ __________________________________________________ Montgomery County Part III – Conditions of the Contract Fire & EMS Headquarters Page 46 of 286 Part III – Conditions of the Contract AIA ® Document A201® – 2017 General Conditions of the Contract for Construction AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 1 ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification. For guidance in modifying this document to include supplementary conditions, see AIA Document A503™, Guide for Supplementary Conditions. ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document. for the following PROJECT: (Name and location or address) « Montgomery County Fire & EMS Headquarters » « Christiansburg, Virginia » THE OWNER: (Name, legal status and address) « Montgomery County, Virginia »« » « 755 Roanoke Street Suite 2E Christiansburg, Virginia 24073 » THE ARCHITECT: (Name, legal status and address) « Local Studio Architecture and Design PLLC »« » « 336 North Washington Avenue Pulaski, Virginia 24301 » TABLE OF ARTICLES 1 GENERAL PROVISIONS 2 OWNER 3 CONTRACTOR 4 ARCHITECT 5 SUBCONTRACTORS 6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS 7 CHANGES IN THE WORK 8 TIME 9 PAYMENTS AND COMPLETION 10 PROTECTION OF PERSONS AND PROPERTY 11 INSURANCE AND BONDS 12 UNCOVERING AND CORRECTION OF WORK 13 MISCELLANEOUS PROVISIONS AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 2 14 TERMINATION OR SUSPENSION OF THE CONTRACT 15 CLAIMS AND DISPUTES AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 3 INDEX (Topics and numbers in bold are Section headings.) Acceptance of Nonconforming Work 9.6.6, 9.9.3, 12.3 Acceptance of Work 9.6.6, 9.8.2, 9.9.3, 9.10.1, 9.10.3, 12.3 Access to Work 3.16, 6.2.1, 12.1 Accident Prevention 10 Acts and Omissions 3.2, 3.3.2, 3.12.8, 3.18, 4.2.3, 8.3.1, 9.5.1, 10.2.5, 10.2.8, 13.3.2, 14.1, 15.1.2, 15.2 Addenda 1.1.1 Additional Costs, Claims for 3.7.4, 3.7.5, 10.3.2, 15.1.5 Additional Inspections and Testing 9.4.2, 9.8.3, 12.2.1, 13.4 Additional Time, Claims for 3.2.4, 3.7.4, 3.7.5, 3.10.2, 8.3.2, 15.1.6 Administration of the Contract 3.1.3, 4.2, 9.4, 9.5 Advertisement or Invitation to Bid 1.1.1 Aesthetic Effect 4.2.13 Allowances 3.8 Applications for Payment 4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5.1, 9.5.4, 9.6.3, 9.7, 9.10 Approvals 2.1.1, 2.3.1, 2.5, 3.1.3, 3.10.2, 3.12.8, 3.12.9, 3.12.10.1, 4.2.7, 9.3.2, 13.4.1 Arbitration 8.3.1, 15.3.2, 15.4 ARCHITECT 4 Architect, Definition of 4.1.1 Architect, Extent of Authority 2.5, 3.12.7, 4.1.2, 4.2, 5.2, 6.3, 7.1.2, 7.3.4, 7.4, 9.2, 9.3.1, 9.4, 9.5, 9.6.3, 9.8, 9.10.1, 9.10.3, 12.1, 12.2.1, 13.4.1, 13.4.2, 14.2.2, 14.2.4, 15.1.4, 15.2.1 Architect, Limitations of Authority and Responsibility 2.1.1, 3.12.4, 3.12.8, 3.12.10, 4.1.2, 4.2.1, 4.2.2, 4.2.3, 4.2.6, 4.2.7, 4.2.10, 4.2.12, 4.2.13, 5.2.1, 7.4, 9.4.2, 9.5.4, 9.6.4, 15.1.4, 15.2 Architect’s Additional Services and Expenses 2.5, 12.2.1, 13.4.2, 13.4.3, 14.2.4 Architect’s Administration of the Contract 3.1.3, 3.7.4, 15.2, 9.4.1, 9.5 Architect’s Approvals 2.5, 3.1.3, 3.5, 3.10.2, 4.2.7 Architect’s Authority to Reject Work 3.5, 4.2.6, 12.1.2, 12.2.1 Architect’s Copyright 1.1.7, 1.5 Architect’s Decisions 3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 4.2.14, 6.3, 7.3.4, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4.1, 9.5, 9.8.4, 9.9.1, 13.4.2, 15.2 Architect’s Inspections 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 13.4 Architect’s Instructions 3.2.4, 3.3.1, 4.2.6, 4.2.7, 13.4.2 Architect’s Interpretations 4.2.11, 4.2.12 Architect’s Project Representative 4.2.10 Architect’s Relationship with Contractor 1.1.2, 1.5, 2.3.3, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.7.5, 3.9.2, 3.9.3, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.2, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3, 12, 13.3.2, 13.4, 15.2 Architect’s Relationship with Subcontractors 1.1.2, 4.2.3, 4.2.4, 4.2.6, 9.6.3, 9.6.4, 11.3 Architect’s Representations 9.4.2, 9.5.1, 9.10.1 Architect’s Site Visits 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.4 Asbestos 10.3.1 Attorneys’ Fees 3.18.1, 9.6.8, 9.10.2, 10.3.3 Award of Separate Contracts 6.1.1, 6.1.2 Award of Subcontracts and Other Contracts for Portions of the Work 5.2 Basic Definitions 1.1 Bidding Requirements 1.1.1 Binding Dispute Resolution 8.3.1, 9.7, 11.5, 13.1, 15.1.2, 15.1.3, 15.2.1, 15.2.5, 15.2.6.1, 15.3.1, 15.3.2, 15.3.3, 15.4.1 Bonds, Lien 7.3.4.4, 9.6.8, 9.10.2, 9.10.3 Bonds, Performance, and Payment 7.3.4.4, 9.6.7, 9.10.3, 11.1.2, 11.1.3, 11.5 Building Information Models Use and Reliance 1.8 Building Permit 3.7.1 Capitalization 1.3 Certificate of Substantial Completion 9.8.3, 9.8.4, 9.8.5 AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 4 Certificates for Payment 4.2.1, 4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 14.1.1.3, 14.2.4, 15.1.4 Certificates of Inspection, Testing or Approval 13.4.4 Certificates of Insurance 9.10.2 Change Orders 1.1.1, 3.4.2, 3.7.4, 3.8.2.3, 3.11, 3.12.8, 4.2.8, 5.2.3, 7.1.2, 7.1.3, 7.2, 7.3.2, 7.3.7, 7.3.9, 7.3.10, 8.3.1, 9.3.1.1, 9.10.3, 10.3.2, 11.2, 11.5, 12.1.2 Change Orders, Definition of 7.2.1 CHANGES IN THE WORK 2.2.2, 3.11, 4.2.8, 7, 7.2.1, 7.3.1, 7.4, 8.3.1, 9.3.1.1, 11.5 Claims, Definition of 15.1.1 Claims, Notice of 1.6.2, 15.1.3 CLAIMS AND DISPUTES 3.2.4, 6.1.1, 6.3, 7.3.9, 9.3.3, 9.10.4, 10.3.3, 15, 15.4 Claims and Timely Assertion of Claims 15.4.1 Claims for Additional Cost 3.2.4, 3.3.1, 3.7.4, 7.3.9, 9.5.2, 10.2.5, 10.3.2, 15.1.5 Claims for Additional Time 3.2.4, 3.3.1, 3.7.4, 6.1.1, 8.3.2, 9.5.2, 10.3.2, 15.1.6 Concealed or Unknown Conditions, Claims for 3.7.4 Claims for Damages 3.2.4, 3.18, 8.3.3, 9.5.1, 9.6.7, 10.2.5, 10.3.3, 11.3, 11.3.2, 14.2.4, 15.1.7 Claims Subject to Arbitration 15.4.1 Cleaning Up 3.15, 6.3 Commencement of the Work, Conditions Relating to 2.2.1, 3.2.2, 3.4.1, 3.7.1, 3.10.1, 3.12.6, 5.2.1, 5.2.3, 6.2.2, 8.1.2, 8.2.2, 8.3.1, 11.1, 11.2, 15.1.5 Commencement of the Work, Definition of 8.1.2 Communications 3.9.1, 4.2.4 Completion, Conditions Relating to 3.4.1, 3.11, 3.15, 4.2.2, 4.2.9, 8.2, 9.4.2, 9.8, 9.9.1, 9.10, 12.2, 14.1.2, 15.1.2 COMPLETION, PAYMENTS AND 9 Completion, Substantial 3.10.1, 4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 15.1.2 Compliance with Laws 2.3.2, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 9.6.4, 10.2.2, 13.1, 13.3, 13.4.1, 13.4.2, 13.5, 14.1.1, 14.2.1.3, 15.2.8, 15.4.2, 15.4.3 Concealed or Unknown Conditions 3.7.4, 4.2.8, 8.3.1, 10.3 Conditions of the Contract 1.1.1, 6.1.1, 6.1.4 Consent, Written 3.4.2, 3.14.2, 4.1.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3, 13.2, 15.4.4.2 Consolidation or Joinder 15.4.4 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS 1.1.4, 6 Construction Change Directive, Definition of 7.3.1 Construction Change Directives 1.1.1, 3.4.2, 3.11, 3.12.8, 4.2.8, 7.1.1, 7.1.2, 7.1.3, 7.3, 9.3.1.1 Construction Schedules, Contractor’s 3.10, 3.11, 3.12.1, 3.12.2, 6.1.3, 15.1.6.2 Contingent Assignment of Subcontracts 5.4, 14.2.2.2 Continuing Contract Performance 15.1.4 Contract, Definition of 1.1.2 CONTRACT, TERMINATION OR SUSPENSION OF THE 5.4.1.1, 5.4.2, 11.5, 14 Contract Administration 3.1.3, 4, 9.4, 9.5 Contract Award and Execution, Conditions Relating to 3.7.1, 3.10, 5.2, 6.1 Contract Documents, Copies Furnished and Use of 1.5.2, 2.3.6, 5.3 Contract Documents, Definition of 1.1.1 Contract Sum 2.2.2, 2.2.4, 3.7.4, 3.7.5, 3.8, 3.10.2, 5.2.3, 7.3, 7.4, 9.1, 9.2, 9.4.2, 9.5.1.4, 9.6.7, 9.7, 10.3.2, 11.5, 12.1.2, 12.3, 14.2.4, 14.3.2, 15.1.4.2, 15.1.5, 15.2.5 Contract Sum, Definition of 9.1 Contract Time 1.1.4, 2.2.1, 2.2.2, 3.7.4, 3.7.5, 3.10.2, 5.2.3, 6.1.5, 7.2.1.3, 7.3.1, 7.3.5, 7.3.6, 7, 7, 7.3.10, 7.4, 8.1.1, 8.2.1, 8.2.3, 8.3.1, 9.5.1, 9.7, 10.3.2, 12.1.1, 12.1.2, 14.3.2, 15.1.4.2, 15.1.6.1, 15.2.5 Contract Time, Definition of 8.1.1 CONTRACTOR 3 Contractor, Definition of 3.1, 6.1.2 Contractor’s Construction and Submittal Schedules 3.10, 3.12.1, 3.12.2, 4.2.3, 6.1.3, 15.1.6.2 AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 5 Contractor’s Employees 2.2.4, 3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3, 11.3, 14.1, 14.2.1.1 Contractor’s Liability Insurance 11.1 Contractor’s Relationship with Separate Contractors and Owner’s Forces 3.12.5, 3.14.2, 4.2.4, 6, 11.3, 12.2.4 Contractor’s Relationship with Subcontractors 1.2.2, 2.2.4, 3.3.2, 3.18.1, 3.18.2, 4.2.4, 5, 9.6.2, 9.6.7, 9.10.2, 11.2, 11.3, 11.4 Contractor’s Relationship with the Architect 1.1.2, 1.5, 2.3.3, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5.1, 3.7.4, 3.10, 3.11, 3.12, 3.16, 3.18, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3, 12, 13.4, 15.1.3, 15.2.1 Contractor’s Representations 3.2.1, 3.2.2, 3.5, 3.12.6, 6.2.2, 8.2.1, 9.3.3, 9.8.2 Contractor’s Responsibility for Those Performing the Work 3.3.2, 3.18, 5.3, 6.1.3, 6.2, 9.5.1, 10.2.8 Contractor’s Review of Contract Documents 3.2 Contractor’s Right to Stop the Work 2.2.2, 9.7 Contractor’s Right to Terminate the Contract 14.1 Contractor’s Submittals 3.10, 3.11, 3.12, 4.2.7, 5.2.1, 5.2.3, 9.2, 9.3, 9.8.2, 9.8.3, 9.9.1, 9.10.2, 9.10.3 Contractor’s Superintendent 3.9, 10.2.6 Contractor’s Supervision and Construction Procedures 1.2.2, 3.3, 3.4, 3.12.10, 4.2.2, 4.2.7, 6.1.3, 6.2.4, 7.1.3, 7.3.4, 7.3.6, 8.2, 10, 12, 14, 15.1.4 Coordination and Correlation 1.2, 3.2.1, 3.3.1, 3.10, 3.12.6, 6.1.3, 6.2.1 Copies Furnished of Drawings and Specifications 1.5, 2.3.6, 3.11 Copyrights 1.5, 3.17 Correction of Work 2.5, 3.7.3, 9.4.2, 9.8.2, 9.8.3, 9.9.1, 12.1.2, 12.2, 12.3, 15.1.3.1, 15.1.3.2, 15.2.1 Correlation and Intent of the Contract Documents 1.2 Cost, Definition of 7.3.4 Costs 2.5, 3.2.4, 3.7.3, 3.8.2, 3.15.2, 5.4.2, 6.1.1, 6.2.3, 7.3.3.3, 7.3.4, 7.3.8, 7.3.9, 9.10.2, 10.3.2, 10.3.6, 11.2, 12.1.2, 12.2.1, 12.2.4, 13.4, 14 Cutting and Patching 3.14, 6.2.5 Damage to Construction of Owner or Separate Contractors 3.14.2, 6.2.4, 10.2.1.2, 10.2.5, 10.4, 12.2.4 Damage to the Work 3.14.2, 9.9.1, 10.2.1.2, 10.2.5, 10.4, 12.2.4 Damages, Claims for 3.2.4, 3.18, 6.1.1, 8.3.3, 9.5.1, 9.6.7, 10.3.3, 11.3.2, 11.3, 14.2.4, 15.1.7 Damages for Delay 6.2.3, 8.3.3, 9.5.1.6, 9.7, 10.3.2, 14.3.2 Date of Commencement of the Work, Definition of 8.1.2 Date of Substantial Completion, Definition of 8.1.3 Day, Definition of 8.1.4 Decisions of the Architect 3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 6.3, 7.3.4, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4, 9.5.1, 9.8.4, 9.9.1, 13.4.2, 14.2.2, 14.2.4, 15.1, 15.2 Decisions to Withhold Certification 9.4.1, 9.5, 9.7, 14.1.1.3 Defective or Nonconforming Work, Acceptance, Rejection and Correction of 2.5, 3.5, 4.2.6, 6.2.3, 9.5.1, 9.5.3, 9.6.6, 9.8.2, 9.9.3, 9.10.4, 12.2.1 Definitions 1.1, 2.1.1, 3.1.1, 3.5, 3.12.1, 3.12.2, 3.12.3, 4.1.1, 5.1, 6.1.2, 7.2.1, 7.3.1, 8.1, 9.1, 9.8.1, 15.1.1 Delays and Extensions of Time 3.2, 3.7.4, 5.2.3, 7.2.1, 7.3.1, 7.4, 8.3, 9.5.1, 9.7, 10.3.2, 10.4, 14.3.2, 15.1.6, 15.2.5 Digital Data Use and Transmission 1.7 Disputes 6.3, 7.3.9, 15.1, 15.2 Documents and Samples at the Site 3.11 Drawings, Definition of 1.1.5 Drawings and Specifications, Use and Ownership of 3.11 Effective Date of Insurance 8.2.2 Emergencies 10.4, 14.1.1.2, 15.1.5 Employees, Contractor’s 3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3.3, 11.3, 14.1, 14.2.1.1 Equipment, Labor, or Materials 1.1.3, 1.1.6, 3.4, 3.5, 3.8.2, 3.8.3, 3.12, 3.13, 3.15.1, 4.2.6, 4.2.7, 5.2.1, 6.2.1, 7.3.4, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1, 10.2.4, 14.2.1.1, 14.2.1.2 Execution and Progress of the Work 1.1.3, 1.2.1, 1.2.2, 2.3.4, 2.3.6, 3.1, 3.3.1, 3.4.1, 3.7.1, 3.10.1, 3.12, 3.14, 4.2, 6.2.2, 7.1.3, 7.3.6, 8.2, 9.5.1, 9.9.1, 10.2, 10.3, 12.1, 12.2, 14.2, 14.3.1, 15.1.4 AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 6 Extensions of Time 3.2.4, 3.7.4, 5.2.3, 7.2.1, 7.3, 7.4, 9.5.1, 9.7, 10.3.2, 10.4, 14.3, 15.1.6, 15.2.5 Failure of Payment 9.5.1.3, 9.7, 9.10.2, 13.5, 14.1.1.3, 14.2.1.2 Faulty Work (See Defective or Nonconforming Work) Final Completion and Final Payment 4.2.1, 4.2.9, 9.8.2, 9.10, 12.3, 14.2.4, 14.4.3 Financial Arrangements, Owner’s 2.2.1, 13.2.2, 14.1.1.4 GENERAL PROVISIONS 1 Governing Law 13.1 Guarantees (See Warranty) Hazardous Materials and Substances 10.2.4, 10.3 Identification of Subcontractors and Suppliers 5.2.1 Indemnification 3.17, 3.18, 9.6.8, 9.10.2, 10.3.3, 11.3 Information and Services Required of the Owner 2.1.2, 2.2, 2.3, 3.2.2, 3.12.10.1, 6.1.3, 6.1.4, 6.2.5, 9.6.1, 9.9.2, 9.10.3, 10.3.3, 11.2, 13.4.1, 13.4.2, 14.1.1.4, 14.1.4, 15.1.4 Initial Decision 15.2 Initial Decision Maker, Definition of 1.1.8 Initial Decision Maker, Decisions 14.2.4, 15.1.4.2, 15.2.1, 15.2.2, 15.2.3, 15.2.4, 15.2.5 Initial Decision Maker, Extent of Authority 14.2.4, 15.1.4.2, 15.2.1, 15.2.2, 15.2.3, 15.2.4, 15.2.5 Injury or Damage to Person or Property 10.2.8, 10.4 Inspections 3.1.3, 3.3.3, 3.7.1, 4.2.2, 4.2.6, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 12.2.1, 13.4 Instructions to Bidders 1.1.1 Instructions to the Contractor 3.2.4, 3.3.1, 3.8.1, 5.2.1, 7, 8.2.2, 12, 13.4.2 Instruments of Service, Definition of 1.1.7 Insurance 6.1.1, 7.3.4, 8.2.2, 9.3.2, 9.8.4, 9.9.1, 9.10.2, 10.2.5, 11 Insurance, Notice of Cancellation or Expiration 11.1.4, 11.2.3 Insurance, Contractor’s Liability 11.1 Insurance, Effective Date of 8.2.2, 14.4.2 Insurance, Owner’s Liability 11.2 Insurance, Property 10.2.5, 11.2, 11.4, 11.5 Insurance, Stored Materials 9.3.2 INSURANCE AND BONDS 11 Insurance Companies, Consent to Partial Occupancy 9.9.1 Insured loss, Adjustment and Settlement of 11.5 Intent of the Contract Documents 1.2.1, 4.2.7, 4.2.12, 4.2.13 Interest 13.5 Interpretation 1.1.8, 1.2.3, 1.4, 4.1.1, 5.1, 6.1.2, 15.1.1 Interpretations, Written 4.2.11, 4.2.12 Judgment on Final Award 15.4.2 Labor and Materials, Equipment 1.1.3, 1.1.6, 3.4, 3.5, 3.8.2, 3.8.3, 3.12, 3.13, 3.15.1, 5.2.1, 6.2.1, 7.3.4, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1, 10.2.4, 14.2.1.1, 14.2.1.2 Labor Disputes 8.3.1 Laws and Regulations 1.5, 2.3.2, 3.2.3, 3.2.4, 3.6, 3.7, 3.12.10, 3.13, 9.6.4, 9.9.1, 10.2.2, 13.1, 13.3.1, 13.4.2, 13.5, 14, 15.2.8, 15.4 Liens 2.1.2, 9.3.1, 9.3.3, 9.6.8, 9.10.2, 9.10.4, 15.2.8 Limitations, Statutes of 12.2.5, 15.1.2, 15.4.1.1 Limitations of Liability 3.2.2, 3.5, 3.12.10, 3.12.10.1, 3.17, 3.18.1, 4.2.6, 4.2.7, 6.2.2, 9.4.2, 9.6.4, 9.6.7, 9.6.8, 10.2.5, 10.3.3, 11.3, 12.2.5, 13.3.1 Limitations of Time 2.1.2, 2.2, 2.5, 3.2.2, 3.10, 3.11, 3.12.5, 3.15.1, 4.2.7, 5.2, 5.3, 5.4.1, 6.2.4, 7.3, 7.4, 8.2, 9.2, 9.3.1, 9.3.3, 9.4.1, 9.5, 9.6, 9.7, 9.8, 9.9, 9.10, 12.2, 13.4, 14, 15, 15.1.2, 15.1.3, 15.1.5 Materials, Hazardous 10.2.4, 10.3 Materials, Labor, Equipment and 1.1.3, 1.1.6, 3.4.1, 3.5, 3.8.2, 3.8.3, 3.12, 3.13, 3.15.1, 5.2.1, 6.2.1, 7.3.4, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1.2, 10.2.4, 14.2.1.1, 14.2.1.2 Means, Methods, Techniques, Sequences and Procedures of Construction 3.3.1, 3.12.10, 4.2.2, 4.2.7, 9.4.2 Mechanic’s Lien 2.1.2, 9.3.1, 9.3.3, 9.6.8, 9.10.2, 9.10.4, 15.2.8 Mediation 8.3.1, 15.1.3.2, 15.2.1, 15.2.5, 15.2.6, 15.3, 15.4.1, 15.4.1.1 AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 7 Minor Changes in the Work 1.1.1, 3.4.2, 3.12.8, 4.2.8, 7.1, 7.4 MISCELLANEOUS PROVISIONS 13 Modifications, Definition of 1.1.1 Modifications to the Contract 1.1.1, 1.1.2, 2.5, 3.11, 4.1.2, 4.2.1, 5.2.3, 7, 8.3.1, 9.7, 10.3.2 Mutual Responsibility 6.2 Nonconforming Work, Acceptance of 9.6.6, 9.9.3, 12.3 Nonconforming Work, Rejection and Correction of 2.4, 2.5, 3.5, 4.2.6, 6.2.4, 9.5.1, 9.8.2, 9.9.3, 9.10.4, 12.2 Notice 1.6, 1.6.1, 1.6.2, 2.1.2, 2.2.2., 2.2.3, 2.2.4, 2.5, 3.2.4, 3.3.1, 3.7.4, 3.7.5, 3.9.2, 3.12.9, 3.12.10, 5.2.1, 7.4, 8.2.2 9.6.8, 9.7, 9.10.1, 10.2.8, 10.3.2, 11.5, 12.2.2.1, 13.4.1, 13.4.2, 14.1, 14.2.2, 14.4.2, 15.1.3, 15.1.5, 15.1.6, 15.4.1 Notice of Cancellation or Expiration of Insurance 11.1.4, 11.2.3 Notice of Claims 1.6.2, 2.1.2, 3.7.4, 9.6.8, 10.2.8, 15.1.3, 15.1.5, 15.1.6, 15.2.8, 15.3.2, 15.4.1 Notice of Testing and Inspections 13.4.1, 13.4.2 Observations, Contractor’s 3.2, 3.7.4 Occupancy 2.3.1, 9.6.6, 9.8 Orders, Written 1.1.1, 2.4, 3.9.2, 7, 8.2.2, 11.5, 12.1, 12.2.2.1, 13.4.2, 14.3.1 OWNER 2 Owner, Definition of 2.1.1 Owner, Evidence of Financial Arrangements 2.2, 13.2.2, 14.1.1.4 Owner, Information and Services Required of the 2.1.2, 2.2, 2.3, 3.2.2, 3.12.10, 6.1.3, 6.1.4, 6.2.5, 9.3.2, 9.6.1, 9.6.4, 9.9.2, 9.10.3, 10.3.3, 11.2, 13.4.1, 13.4.2, 14.1.1.4, 14.1.4, 15.1.4 Owner’s Authority 1.5, 2.1.1, 2.3.32.4, 2.5, 3.4.2, 3.8.1, 3.12.10, 3.14.2, 4.1.2, 4.2.4, 4.2.9, 5.2.1, 5.2.4, 5.4.1, 6.1, 6.3, 7.2.1, 7.3.1, 8.2.2, 8.3.1, 9.3.2, 9.5.1, 9.6.4, 9.9.1, 9.10.2, 10.3.2, 11.4, 11.5, 12.2.2, 12.3, 13.2.2, 14.3, 14.4, 15.2.7 Owner’s Insurance 11.2 Owner’s Relationship with Subcontractors 1.1.2, 5.2, 5.3, 5.4, 9.6.4, 9.10.2, 14.2.2 Owner’s Right to Carry Out the Work 2.5, 14.2.2 Owner’s Right to Clean Up 6.3 Owner’s Right to Perform Construction and to Award Separate Contracts 6.1 Owner’s Right to Stop the Work 2.4 Owner’s Right to Suspend the Work 14.3 Owner’s Right to Terminate the Contract 14.2, 14.4 Ownership and Use of Drawings, Specifications and Other Instruments of Service 1.1.1, 1.1.6, 1.1.7, 1.5, 2.3.6, 3.2.2, 3.11, 3.17, 4.2.12, 5.3 Partial Occupancy or Use 9.6.6, 9.9 Patching, Cutting and 3.14, 6.2.5 Patents 3.17 Payment, Applications for 4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5, 9.6.3, 9.7, 9.8.5, 9.10.1, 14.2.3, 14.2.4, 14.4.3 Payment, Certificates for 4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 14.1.1.3, 14.2.4 Payment, Failure of 9.5.1.3, 9.7, 9.10.2, 13.5, 14.1.1.3, 14.2.1.2 Payment, Final 4.2.1, 4.2.9, 9.10, 12.3, 14.2.4, 14.4.3 Payment Bond, Performance Bond and 7.3.4.4, 9.6.7, 9.10.3, 11.1.2 Payments, Progress 9.3, 9.6, 9.8.5, 9.10.3, 14.2.3, 15.1.4 PAYMENTS AND COMPLETION 9 Payments to Subcontractors 5.4.2, 9.5.1.3, 9.6.2, 9.6.3, 9.6.4, 9.6.7, 14.2.1.2 PCB 10.3.1 Performance Bond and Payment Bond 7.3.4.4, 9.6.7, 9.10.3, 11.1.2 Permits, Fees, Notices and Compliance with Laws 2.3.1, 3.7, 3.13, 7.3.4.4, 10.2.2 PERSONS AND PROPERTY, PROTECTION OF 10 Polychlorinated Biphenyl 10.3.1 Product Data, Definition of 3.12.2 Product Data and Samples, Shop Drawings 3.11, 3.12, 4.2.7 AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 8 Progress and Completion 4.2.2, 8.2, 9.8, 9.9.1, 14.1.4, 15.1.4 Progress Payments 9.3, 9.6, 9.8.5, 9.10.3, 14.2.3, 15.1.4 Project, Definition of 1.1.4 Project Representatives 4.2.10 Property Insurance 10.2.5, 11.2 Proposal Requirements 1.1.1 PROTECTION OF PERSONS AND PROPERTY 10 Regulations and Laws 1.5, 2.3.2, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 9.6.4, 9.9.1, 10.2.2, 13.1, 13.3, 13.4.1, 13.4.2, 13.5, 14, 15.2.8, 15.4 Rejection of Work 4.2.6, 12.2.1 Releases and Waivers of Liens 9.3.1, 9.10.2 Representations 3.2.1, 3.5, 3.12.6, 8.2.1, 9.3.3, 9.4.2, 9.5.1, 9.10.1 Representatives 2.1.1, 3.1.1, 3.9, 4.1.1, 4.2.10, 13.2.1 Responsibility for Those Performing the Work 3.3.2, 3.18, 4.2.2, 4.2.3, 5.3, 6.1.3, 6.2, 6.3, 9.5.1, 10 Retainage 9.3.1, 9.6.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3 Review of Contract Documents and Field Conditions by Contractor 3.2, 3.12.7, 6.1.3 Review of Contractor’s Submittals by Owner and Architect 3.10.1, 3.10.2, 3.11, 3.12, 4.2, 5.2, 6.1.3, 9.2, 9.8.2 Review of Shop Drawings, Product Data and Samples by Contractor 3.12 Rights and Remedies 1.1.2, 2.4, 2.5, 3.5, 3.7.4, 3.15.2, 4.2.6, 5.3, 5.4, 6.1, 6.3, 7.3.1, 8.3, 9.5.1, 9.7, 10.2.5, 10.3, 12.2.1, 12.2.2, 12.2.4, 13.3, 14, 15.4 Royalties, Patents and Copyrights 3.17 Rules and Notices for Arbitration 15.4.1 Safety of Persons and Property 10.2, 10.4 Safety Precautions and Programs 3.3.1, 4.2.2, 4.2.7, 5.3, 10.1, 10.2, 10.4 Samples, Definition of 3.12.3 Samples, Shop Drawings, Product Data and 3.11, 3.12, 4.2.7 Samples at the Site, Documents and 3.11 Schedule of Values 9.2, 9.3.1 Schedules, Construction 3.10, 3.12.1, 3.12.2, 6.1.3, 15.1.6.2 Separate Contracts and Contractors 1.1.4, 3.12.5, 3.14.2, 4.2.4, 4.2.7, 6, 8.3.1, 12.1.2 Separate Contractors, Definition of 6.1.1 Shop Drawings, Definition of 3.12.1 Shop Drawings, Product Data and Samples 3.11, 3.12, 4.2.7 Site, Use of 3.13, 6.1.1, 6.2.1 Site Inspections 3.2.2, 3.3.3, 3.7.1, 3.7.4, 4.2, 9.9.2, 9.4.2, 9.10.1, 13.4 Site Visits, Architect’s 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.4 Special Inspections and Testing 4.2.6, 12.2.1, 13.4 Specifications, Definition of 1.1.6 Specifications 1.1.1, 1.1.6, 1.2.2, 1.5, 3.12.10, 3.17, 4.2.14 Statute of Limitations 15.1.2, 15.4.1.1 Stopping the Work 2.2.2, 2.4, 9.7, 10.3, 14.1 Stored Materials 6.2.1, 9.3.2, 10.2.1.2, 10.2.4 Subcontractor, Definition of 5.1.1 SUBCONTRACTORS 5 Subcontractors, Work by 1.2.2, 3.3.2, 3.12.1, 3.18, 4.2.3, 5.2.3, 5.3, 5.4, 9.3.1.2, 9.6.7 Subcontractual Relations 5.3, 5.4, 9.3.1.2, 9.6, 9.10, 10.2.1, 14.1, 14.2.1 Submittals 3.10, 3.11, 3.12, 4.2.7, 5.2.1, 5.2.3, 7.3.4, 9.2, 9.3, 9.8, 9.9.1, 9.10.2, 9.10.3 Submittal Schedule 3.10.2, 3.12.5, 4.2.7 Subrogation, Waivers of 6.1.1, 11.3 Substances, Hazardous 10.3 Substantial Completion 4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 15.1.2 Substantial Completion, Definition of 9.8.1 Substitution of Subcontractors 5.2.3, 5.2.4 Substitution of Architect 2.3.3 AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 9 Substitutions of Materials 3.4.2, 3.5, 7.3.8 Sub-subcontractor, Definition of 5.1.2 Subsurface Conditions 3.7.4 Successors and Assigns 13.2 Superintendent 3.9, 10.2.6 Supervision and Construction Procedures 1.2.2, 3.3, 3.4, 3.12.10, 4.2.2, 4.2.7, 6.1.3, 6.2.4, 7.1.3, 7.3.4, 8.2, 8.3.1, 9.4.2, 10, 12, 14, 15.1.4 Suppliers 1.5, 3.12.1, 4.2.4, 4.2.6, 5.2.1, 9.3, 9.4.2, 9.5.4, 9.6, 9.10.5, 14.2.1 Surety 5.4.1.2, 9.6.8, 9.8.5, 9.10.2, 9.10.3, 11.1.2, 14.2.2, 15.2.7 Surety, Consent of 9.8.5, 9.10.2, 9.10.3 Surveys 1.1.7, 2.3.4 Suspension by the Owner for Convenience 14.3 Suspension of the Work 3.7.5, 5.4.2, 14.3 Suspension or Termination of the Contract 5.4.1.1, 14 Taxes 3.6, 3.8.2.1, 7.3.4.4 Termination by the Contractor 14.1, 15.1.7 Termination by the Owner for Cause 5.4.1.1, 14.2, 15.1.7 Termination by the Owner for Convenience 14.4 Termination of the Architect 2.3.3 Termination of the Contractor Employment 14.2.2 TERMINATION OR SUSPENSION OF THE CONTRACT 14 Tests and Inspections 3.1.3, 3.3.3, 3.7.1, 4.2.2, 4.2.6, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 10.3.2, 12.2.1, 13.4 TIME 8 Time, Delays and Extensions of 3.2.4, 3.7.4, 5.2.3, 7.2.1, 7.3.1, 7.4, 8.3, 9.5.1, 9.7, 10.3.2, 10.4, 14.3.2, 15.1.6, 15.2.5 Time Limits 2.1.2, 2.2, 2.5, 3.2.2, 3.10, 3.11, 3.12.5, 3.15.1, 4.2, 5.2, 5.3, 5.4, 6.2.4, 7.3, 7.4, 8.2, 9.2, 9.3.1, 9.3.3, 9.4.1, 9.5, 9.6, 9.7, 9.8, 9.9, 9.10, 12.2, 13.4, 14, 15.1.2, 15.1.3, 15.4 Time Limits on Claims 3.7.4, 10.2.8, 15.1.2, 15.1.3 Title to Work 9.3.2, 9.3.3 UNCOVERING AND CORRECTION OF WORK 12 Uncovering of Work 12.1 Unforeseen Conditions, Concealed or Unknown 3.7.4, 8.3.1, 10.3 Unit Prices 7.3.3.2, 9.1.2 Use of Documents 1.1.1, 1.5, 2.3.6, 3.12.6, 5.3 Use of Site 3.13, 6.1.1, 6.2.1 Values, Schedule of 9.2, 9.3.1 Waiver of Claims by the Architect 13.3.2 Waiver of Claims by the Contractor 9.10.5, 13.3.2, 15.1.7 Waiver of Claims by the Owner 9.9.3, 9.10.3, 9.10.4, 12.2.2.1, 13.3.2, 14.2.4, 15.1.7 Waiver of Consequential Damages 14.2.4, 15.1.7 Waiver of Liens 9.3, 9.10.2, 9.10.4 Waivers of Subrogation 6.1.1, 11.3 Warranty 3.5, 4.2.9, 9.3.3, 9.8.4, 9.9.1, 9.10.2, 9.10.4, 12.2.2, 15.1.2 Weather Delays 8.3, 15.1.6.2 Work, Definition of 1.1.3 Written Consent 1.5.2, 3.4.2, 3.7.4, 3.12.8, 3.14.2, 4.1.2, 9.3.2, 9.10.3, 13.2, 13.3.2, 15.4.4.2 Written Interpretations 4.2.11, 4.2.12 Written Orders 1.1.1, 2.4, 3.9, 7, 8.2.2, 12.1, 12.2, 13.4.2, 14.3.1 AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 10 ARTICLE 1 GENERAL PROVISIONS § 1.1 Basic Definitions § 1.1.1 The Contract Documents The Contract Documents are enumerated in the Agreement between the Owner and Contractor (hereinafter the Agreement) and consist of the Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of the Contract, other documents listed in the Agreement, and Modifications issued after execution of the Contract. A Modification is (1) a written amendment to the Contract signed by both parties, (2) a Change Order, (3) a Construction Change Directive, or (4) a written order for a minor change in the Work issued by the Architect. Unless specifically enumerated in the Agreement, the Contract Documents do not include the advertisement or invitation to bid, Instructions to Bidders, sample forms, other information furnished by the Owner in anticipation of receiving bids or proposals, the Contractor’s bid or proposal, or portions of Addenda relating to bidding or proposal requirements. § 1.1.2 The Contract The Contract Documents form the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. The Contract may be amended or modified only by a Modification. The Contract Documents shall not be construed to create a contractual relationship of any kind (1) between the Contractor and the Architect or the Architect’s consultants, (2) between the Owner and a Subcontractor or a Sub-subcontractor, (3) between the Owner and the Architect or the Architect’s consultants, or (4) between any persons or entities other than the Owner and the Contractor. The Architect shall, however, be entitled to performance and enforcement of obligations under the Contract intended to facilitate performance of the Architect’s duties. § 1.1.3 The Work The term “Work” means the construction and services required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment, and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations. The Work may constitute the whole or a part of the Project. § 1.1.4 The Project The Project is the total construction of which the Work performed under the Contract Documents may be the whole or a part and which may include construction by the Owner and by Separate Contractors. § 1.1.5 The Drawings The Drawings are the graphic and pictorial portions of the Contract Documents showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, schedules, and diagrams. § 1.1.6 The Specifications The Specifications are that portion of the Project Manual and Contract Documents consisting of the written requirements for materials, equipment, systems, standards and workmanship for the Work, and performance of related services. § 1.1.7 Instruments of Service Instruments of Service are representations, in any medium of expression now known or later developed, of the tangible and intangible creative work performed by the Architect and the Architect’s consultants under their respective professional services agreements. Instruments of Service may include, without limitation, studies, surveys, models, sketches, drawings, specifications, and other similar materials. § 1.1.8 Initial Decision Maker The Initial Decision Maker is the person identified in the Agreement to render initial decisions on Claims in accordance with Section 15.2. The Initial Decision Maker shall not show partiality to the Owner or Contractor and shall not be liable for results of interpretations or decisions rendered in good faith. § 1.2 Correlation and Intent of the Contract Documents § 1.2.1 The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work by the Contractor. The Contract Documents are complementary, and what is required by one shall be as binding as if required by all. Performance by the Contractor shall be consistent with the Contract Documents and reasonably inferable from them as being necessary to produce the indicated results. Notwithstanding AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 11 such performance, in case of a conflict, disagreement, or ambiguity, provide the better quality of Work. In case of a conflict, disagreement, or ambiguity, provide the greater quantity of Work. § 1.2.1.1 The invalidity of any provision of the Contract Documents shall not invalidate the Contract or its remaining provisions. If it is determined that any provision of the Contract Documents violates any law, or is otherwise invalid or unenforceable, then that provision shall be revised to the extent necessary to make that provision legal and enforceable. In such case the Contract Documents shall be construed, to the fullest extent permitted by law, to give effect to the parties’ intentions and purposes in executing the Contract. § 1.2.1.2 Plumbing, Mechanical, Fire Protection and Electrical drawings are diagrammatic, showing general locations and arrangements of piping, wiring, equipment, security and technology, and specialties; not necessarily showing all required offsets, conditions and appurtenances required for maximum practical accessibility for operation, maintenance and clearances. Coordinate this Work in order to achieve the required and intended Work and notify the Architect immediately of conditions which do not comply or will not allow for this condition. § 1.2.2 Organization of the Specifications into divisions, sections and articles, and arrangement of Drawings shall not control the Contractor in dividing the Work among Subcontractors or in establishing the extent of Work to be performed by any trade. § 1.2.3 Unless otherwise stated in the Contract Documents, words that have well-known technical or construction industry meanings are used in the Contract Documents in accordance with such recognized meanings. § 1.3 Capitalization Terms capitalized in these General Conditions include those that are (1) specifically defined, (2) the titles of numbered articles, or (3) the titles of other documents published by the American Institute of Architects. § 1.4 Interpretation In the interest of brevity the Contract Documents frequently omit modifying words such as “all” and “any” and articles such as “the” and “an,” but the fact that a modifier or an article is absent from one statement and appears in another is not intended to affect the interpretation of either statement. § 1.5 Ownership and Use of Drawings, Specifications, and Other Instruments of Service § 1.5.1 Unless otherwise required by the Owner and Architect Agreement, the Architect and the Architect’s consultants shall be deemed the authors and owners of their respective Instruments of Service, including the Drawings and Specifications, and retain all common law, statutory, and other reserved rights in their Instruments of Service, including copyrights. The Contractor, Subcontractors, Sub-subcontractors, and suppliers shall not own or claim a copyright in the Instruments of Service. Submittal or distribution to meet official regulatory requirements or for other purposes in connection with the Project is not to be construed as publication in derogation of the Architect’s or Architect’s consultants’ reserved rights. § 1.5.2 The Contractor, Subcontractors, Sub-subcontractors, and suppliers are authorized to use and reproduce the Instruments of Service provided to them, subject to any protocols established pursuant to Sections 1.7, 1.8, and 1.9 solely and exclusively for execution of the Work. All copies made under this authorization shall bear the copyright notice, if any, shown on the Instruments of Service. The Contractor, Subcontractors, Sub-subcontractors, and suppliers may not use the Instruments of Service on other projects or for additions to the Project outside the scope of the Work without the specific written consent of the Owner, Architect, and the Architect’s consultants. § 1.6 Notice § 1.6.1 Except as otherwise provided in Section 1.6.2, where the Contract Documents require one party to notify or give notice to the other party, such notice shall be provided in writing to the designated representative of the party to whom the notice is addressed and shall be deemed to have been duly served if delivered in person, by mail, by courier, or by electronic transmission if a method for electronic transmission is set forth in the Agreement. § 1.6.2 Notice of Claims as provided in Section 15.1.3 shall be provided in writing and shall be deemed to have been duly served only if delivered to the designated representative of the party to whom the notice is addressed by certified or registered mail, or by courier providing proof of delivery, including signature of receiver of such notices. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 12 § 1.7 Digital Data Use and Transmission The parties shall agree upon protocols governing the transmission and use of Instruments of Service or any other information or documentation in digital form. The parties shall use AIA Document E203™-2013, Building Information Modeling and Digital Data Exhibit, to establish the protocols for the development, use, transmission, and exchange of digital data, should such Exhibit be included in the Agreement. § 1.8 Building Information Models Use and Reliance Any use of, or reliance on, all or a portion of a building information model without agreement to protocols governing the use of, and reliance on, the information contained in the model and without having those protocols set forth in AIA Document E203™-2013, Building Information Modeling and Digital Data Exhibit, and the requisite AIA Document G202™-2013, Project Building Information Modeling Protocol Form, shall be at the using or relying party’s sole risk and without liability to the other party and its contractors or consultants, the authors of, or contributors to, the building information model, and each of their agents and employees. § 1.9 If such Exhibits are not included in the Agreement, the Architect may, with the concurrence of the Owner, furnish to the Contractor versions of the Instruments of Service in electronic form. The Contract Documents executed or identified in accordance with Section 1.1.1 shall prevail in case of an inconsistency with subsequent versions made through manipulatable electronic operations involving computers. The Contractor shall not transfer or reuse Instruments of Service in electronic or machine readable form without prior written consent of the Architect. ARTICLE 2 OWNER § 2.1 General § 2.1.1 The Owner is the person or entity identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The Owner shall designate in writing a representative who shall have express authority to bind the Owner with respect to all matters requiring the Owner’s approval or authorization. The Architect does not have such authority. The term “Owner” means the Owner or the Owner’s authorized representative. § 2.1.2 The Owner shall furnish to the Contractor, within fifteen days after receipt of a written request, information necessary and relevant for the Contractor to evaluate, give notice of, or enforce mechanic’s lien rights. Such information shall include a correct statement of the record legal title to the property on which the Project is located, usually referred to as the site, and the Owner’s interest therein. § 2.2 Evidence of the Owner’s Financial Arrangements § 2.2.1 Prior to commencement of the Work and upon written request by the Contractor, the Owner shall furnish to the Contractor reasonable evidence that the Owner has made financial arrangements to fulfill the Owner’s obligations under the Contract. The Contractor shall have no obligation to commence the Work until the Owner provides such evidence. If commencement of the Work is delayed under this Section 2.2.1, the Contract Time shall be extended appropriately. § 2.2.2 Following commencement of the Work and upon written request by the Contractor, the Owner shall furnish to the Contractor reasonable evidence that the Owner has made financial arrangements to fulfill the Owner’s obligations under the Contract only if (1) the Owner fails to make payments to the Contractor as the Contract Documents require; (2) the Contractor identifies in writing a reasonable concern regarding the Owner’s ability to make payment when due; or (3) a change in the Work materially changes the Contract Sum. If the Owner fails to provide such evidence, as required, within fourteen days of the Contractor’s request, the Contractor may immediately stop the Work and, in that event, shall notify the Owner that the Work has stopped. However, if the request is made because a change in the Work materially changes the Contract Sum under (3) above, the Contractor may immediately stop only that portion of the Work affected by the change until reasonable evidence is provided. If the Work is stopped under this Section 2.2.2, the Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Contractor’s reasonable costs of shutdown, delay and start-up, plus interest as provided in the Contract Documents. § 2.2.3 After the Owner furnishes evidence of financial arrangements under this Section 2.2, the Owner shall not materially vary such financial arrangements without prior notice to the Contractor. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 13 § 2.2.4 Where the Owner has designated information furnished under this Section 2.2 as “confidential,” the Contractor shall keep the information confidential and shall not disclose it to any other person. However, the Contractor may disclose “confidential” information, after seven (7) days’ notice to the Owner, where disclosure is required by law, including a subpoena or other form of compulsory legal process issued by a court or governmental entity, or by court or arbitrator(s) order. The Contractor may also disclose “confidential” information to its employees, consultants, sureties, Subcontractors and their employees, Sub-subcontractors, and others who need to know the content of such information solely and exclusively for the Project and who agree to maintain the confidentiality of such information. § 2.3 Information and Services Required of the Owner § 2.3.1 Except for permits and fees that are the responsibility of the Contractor under the Contract Documents, including those required under Section 3.7.1, the Owner shall secure and pay for necessary approvals, easements, assessments and charges required for construction, use or occupancy of permanent structures or for permanent changes in existing facilities. § 2.3.2 The Owner shall retain an architect lawfully licensed to practice architecture, or an entity lawfully practicing architecture, in the jurisdiction where the Project is located. That person or entity is identified as the Architect in the Agreement and is referred to throughout the Contract Documents as if singular in number. § 2.3.3 If the employment of the Architect terminates, the Owner shall employ a successor to whom the Contractor has no reasonable objection and whose status under the Contract Documents shall be that of the Architect. § 2.3.4 The Owner shall furnish surveys describing physical characteristics, legal limitations and utility locations for the site of the Project, and a legal description of the site. The Contractor shall be entitled to rely on the accuracy of information furnished by the Owner but shall exercise proper precautions relating to the safe performance of the Work. § 2.3.5 The Owner shall furnish information or services required of the Owner by the Contract Documents with reasonable promptness. The Owner shall also furnish any other information or services under the Owner’s control and relevant to the Contractor’s performance of the Work with reasonable promptness after receiving the Contractor’s written request for such information or services. § 2.3.6 Unless otherwise provided in the Contract Documents, the Owner, free of charge, (XX) (PIC/PM to determine number of sets) copies of Drawings, Specifications, and Addenda issued, which may be picked up from the Architect’s office. OR Unless otherwise provided in the Contract Documents, the Owner shall furnish to the Contractor one electronic copy of the Drawings, Specifications, and Addenda issued, for the purposes of making reproductions pursuant to Section 1.5.2. § 2.3.6.1 At the Architect’s sole discretion, selected electronic (CAD) Drawing files may be made available for use by the Contractor after the execution of the Contract for Construction, with the exception of civil grading and layout plans, if authorized by the civil consultant. Such electronic files are not part of the Contract Documents. If available, the Architect shall release them to the Contractor subject to the terms and conditions established by the Architect, to which the Contractor must agree without exception prior to release of the electronic files. § 2.4 Owner’s Right to Stop the Work If the Contractor fails to correct Work that is not in accordance with the requirements of the Contract Documents as required by Section 12.2 or repeatedly fails to carry out Work in accordance with the Contract Documents, the Owner may issue a written order to the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, the right of the Owner to stop the Work shall not give rise to a duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity, except to the extent required by Section 6.1.3. § 2.5 Owner’s Right to Carry Out the Work If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a ten-day period after receipt of notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, without prejudice to other remedies the Owner may have, correct such default or neglect. Amounts charged to the Contractor may, pursuant to Section 9.5.1, nullify a AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 14 Certificate for Payment in whole or in part, to the extent reasonably necessary to reimburse the Owner for the reasonable cost of correcting such deficiencies, including Owner’s expenses and compensation for the Architect’s additional services made necessary by such default, neglect, or failure. If current and future payments are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner. If the Contractor disagrees with the actions of the Owner or the Architect, or the amounts claimed as costs to the Owner, the Contractor may file a Claim pursuant to Article 15. ARTICLE 3 CONTRACTOR § 3.1 General § 3.1.1 The Contractor is the person or entity identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The Contractor shall be lawfully licensed, if required in the jurisdiction where the Project is located. The Contractor shall designate in writing a representative who shall have express authority to bind the Contractor with respect to all matters under this Contract. The term “Contractor” means the Contractor or the Contractor’s authorized representative. § 3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents. § 3.1.3 The Contractor shall not be relieved of its obligations to perform the Work in accordance with the Contract Documents either by activities or duties of the Architect in the Architect’s administration of the Contract, or by tests, inspections or approvals required or performed by persons or entities other than the Contractor. § 3.1.4 During the performance of this Contract, the Contractor will include the provisions of the foregoing Sections 3.1.4.1 and 3.1.4.2 in every Subcontract or purchase order of over ten thousand dollars ($10,000.00), so that the provisions will be binding upon each Subcontractor or vendor; and furthermore, the Contractor agrees as follows: .1 The Contractor will not discriminate against any employee or applicant for employment because of race, religion, color, sex, or national origin, except where religion, sex, or national origin is a bona fide occupational qualification reasonably necessary to the normal operation of the Contractor. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this non-discrimination clause. .2 The Contractor, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, will state that such Contractor is an equal opportunity employer. .3 Notices, advertisements, and solicitations placed in accordance with federal law, rule, or regulation shall be deemed sufficient for the purpose of meeting requirements of this section. .4 The Contractor does not, and shall not during the performance of this Contract, knowingly employ an unauthorized alien as defined in the Federal Immigration Reform and Control Act of 1986. .5 Contractor hereby represents it is organized as a stock or non-stock corporation, limited liability company, business trust, or limited partnership and is authorized to transact business in the jurisdiction where the Project is located as a domestic or foreign business entity if so required by Title 13.1 or Title 50 or as otherwise required by law. § 3.2 Review of Contract Documents and Field Conditions by Contractor § 3.2.1 Execution of the Contract by the Contractor is a representation that the Contractor has visited the site, become generally familiar with local conditions under which the Work is to be performed, and correlated personal observations with requirements of the Contract Documents. § 3.2.2 Because the Contract Documents are complementary, the Contractor shall, before starting each portion of the Work, carefully study and compare the various Contract Documents relative to that portion of the Work, as well as the information furnished by the Owner pursuant to Section 2.3, shall take field measurements of any existing conditions related to that portion of the Work, and shall observe any conditions at the site affecting it. These obligations are for the purpose of facilitating coordination and construction by the Contractor and are not for the purpose of discovering errors, omissions, or inconsistencies in the Contract Documents; however, the Contractor shall promptly report to the Architect any errors, inconsistencies or omissions discovered by or made known to the Contractor as a request for information in such form as the Architect may require. It is recognized that the Contractor’s review is made in the Contractor’s capacity as a contractor and not as a licensed design professional, unless otherwise specifically provided in the Contract Documents. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 15 § 3.2.3 The Contractor is not required to ascertain that the Contract Documents are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Contractor shall promptly report to the Architect any nonconformity discovered by or made known to the Contractor as a request for information in such form as the Architect may require. If the Contractor performs Work knowing it to be contrary to applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, the Contractor shall assume appropriate responsibility for such Work and shall bear the costs attributable to correction. § 3.2.4 If the Contractor believes that additional cost or time is involved because of clarifications or instructions the Architect issues in response to the Contractor’s notices or requests for information pursuant to Sections 3.2.2 or 3.2.3, the Contractor shall submit Claims as provided in Article 15. If the Contractor fails to perform the obligations of Sections 3.2.2 or 3.2.3, the Contractor shall pay such costs and damages to the Owner, subject to Section 15.1.7, as would have been avoided if the Contractor had performed such obligations. If the Contractor performs those obligations, the Contractor shall not be liable to the Owner or Architect for damages resulting from errors, inconsistencies or omissions in the Contract Documents, for differences between field measurements or conditions and the Contract Documents, or for nonconformities of the Contract Documents to applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities. § 3.2.5 The Owner shall deduct from the Contract Sum amounts paid to the Architect for the Architect to evaluate and respond to the Contractor’s request for information, where such information was available to the Contractor from a careful study and comparison of the Contract Documents, field conditions, other Owner-provided information, Contractor-prepared coordination drawings, or prior correspondence or documentation. § 3.3 Supervision and Construction Procedures § 3.3.1 The Contractor shall supervise and direct the Work, using the Contractor’s best skill and attention. The Contractor shall be solely responsible for, and have control over, construction means, methods, techniques, sequences, and procedures, and for coordinating all portions of the Work under the Contract. If the Contract Documents give specific instructions concerning construction means, methods, techniques, sequences, or procedures, the Contractor shall evaluate the jobsite safety thereof and shall be solely responsible for the jobsite safety of such means, methods, techniques, sequences, or procedures. If the Contractor determines that such means, methods, techniques, sequences or procedures may not be appropriate, the Contractor shall give timely notice to the Owner and Architect, and shall propose alternative means, methods, techniques, sequences, or procedures. The Architect shall evaluate the proposed alternative solely for conformance with the design intent for the completed construction. Unless the Architect objects to the Contractor’s proposed alternative in writing, the Contractor shall perform the Work using its alternative means, methods, techniques, sequences, or procedures. § 3.3.2 The Contractor shall be responsible to the Owner for acts and omissions of the Contractor’s employees, Subcontractors and their agents and employees, and other persons or entities performing portions of the Work for, or on behalf of, the Contractor or any of its Subcontractors. § 3.3.3 The Contractor shall be responsible for inspection of portions of Work already performed to determine that such portions are in proper condition to receive subsequent Work. § 3.4 Labor and Materials § 3.4.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work. § 3.4.2 Except in the case of minor changes in the Work found to be acceptable by the Architect in accordance with Section 3.12.8 or ordered by the Architect in accordance with Section 7.4, the Contractor may make substitutions only with the consent of the Owner, after review by the Architect and in accordance with a Change Order or Construction Change Directive. § 3.4.2.1 After the Contract has been executed, the Owner and the Architect will consider a formal request for substitution in lieu of those required by the Contract Documents only under and in addition to, the conditions set forth in the Contract Documents. By making requests for substitutions, the Contractor: AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 16 .1 represents that the Contractor has personally investigated the proposed substitute product and determined that it is equal or superior in all respects to requirements of the Contract Documents; .2 represents that the Contractor will provide the same warranty for the substitution that the Contractor is required to provide under the Contract Documents; .3 certifies that the cost data presented is complete and includes all related costs under this Contract including the Architect’s redesign costs, and waives all claims for additional costs and time related to the substitution which subsequently become apparent; and .4 will coordinate and perform the installation of the accepted substitute, making such changes to the Work as may be required for the Work to be complete in all respects. § 3.4.3 The Contractor shall enforce strict discipline and good order among the Contractor’s employees and other persons carrying out the Work. The Contractor shall not permit employment of unfit persons or persons not properly skilled in tasks assigned to them. § 3.4.4 The Owner shall deduct from the Contract Sum amounts paid to the Architect for the Architect to review the Contractor’s proposed substitutions, to make agreed-upon changes in the Instruments of Service, including the Contract Documents, and to provide additional construction phase services made necessary by the Owner’s acceptance of such substitutions. § 3.5 Warranty § 3.5.1 The Contractor warrants to the Owner and Architect that materials and equipment furnished under the Contract will be of good quality and new unless the Contract Documents require or permit otherwise. The Contractor further warrants that the Work will conform to the requirements of the Contract Documents and will be free from defects, except for those inherent in the quality of the Work the Contract Documents require or permit. Work, materials, or equipment not conforming to these requirements may be considered defective. The Contractor’s warranty excludes remedy for damage or defect caused by abuse, alterations to the Work not executed by the Contractor, improper or insufficient maintenance, improper operation, or normal wear and tear and normal usage. If required by the Architect, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment. § 3.5.2 All material, equipment, or other special warranties required by the Contract Documents shall be issued in the name of the Owner, or shall be transferable to the Owner, and shall commence in accordance with Section 9.8.4. § 3.6 Taxes The Contractor shall pay sales, consumer, use and similar taxes for the Work provided by the Contractor that are legally enacted when bids are received or negotiations concluded, whether or not yet effective or merely scheduled to go into effect. § 3.7 Permits, Fees, Notices and Compliance with Laws § 3.7.1 Unless otherwise provided in the Contract Documents, the Contractor shall secure and pay for the building permit as well as for other permits, fees, licenses, and inspections by government agencies necessary for proper execution and completion of the Work that are customarily secured after execution of the Contract and legally required at the time bids are received or negotiations concluded. § 3.7.1.1 Unless otherwise provided in the Contract Documents, the Contractor is responsible for obtaining utilities for the Project and providing the Work relating to Project utilities as indicated. Responsibility for payment of fees associated with providing utilities to the Project shall be as follows: .1 Any fees assessed by entities for providing permanent utilities to the Project shall be paid directly to the utility entities by the Owner. These include “tap fees” and “electrical connection and service fee.” Contractor shall coordinate the permanent utilities and the entity’s related work to comply with the construction schedule. .2 Any fees assessed by entities for providing temporary utilities to the Project for use by the Contractor during construction of the Project shall be paid by the Contractor. The Contractor’s payment of fees for temporary utilities shall be included in the Base Bid and Contract Sum and will not be reimbursed by the Owner. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 17 § 3.7.2 The Contractor shall comply with and give notices required by applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities applicable to performance of the Work. § 3.7.3 If the Contractor performs Work knowing it to be contrary to applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, the Contractor shall assume appropriate responsibility for such Work and shall bear the costs attributable to correction. § 3.7.4 Concealed or Unknown Conditions If the Contractor encounters conditions at the site that are (1) subsurface or otherwise concealed physical conditions that differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature that differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, the Contractor shall promptly provide notice to the Owner and the Architect before conditions are disturbed and in no event later than 14 days after first observance of the conditions. The Architect will promptly review such conditions and, if the Architect determines that they differ materially and cause an increase or decrease in the Contractor’s cost of, or time required for, performance of any part of the Work, will determine that an equitable adjustment should be made in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall promptly notify the Owner and Contractor, stating the reasons. If either party disputes the Architect’s determination or that party may submit a Claim as provided in Article 15. § 3.7.5 If, in the course of the Work, the Contractor encounters human remains or recognizes the existence of burial markers, archaeological sites or wetlands not indicated in the Contract Documents, the Contractor shall immediately suspend any operations that would affect them and shall notify the Owner and Architect. Upon receipt of such notice, the Owner shall promptly take any action necessary to obtain governmental authorization required to resume the operations. The Contractor shall continue to suspend such operations until otherwise instructed by the Owner but shall continue with all other operations that do not affect those remains or features. Requests for adjustments in the Contract Sum and Contract Time arising from the existence of such remains or features may be made as provided in Article 15. § 3.8 Allowances § 3.8.1 The Contractor shall include in the Contract Sum all allowances stated in the Contract Documents. Items covered by allowances shall be supplied for such amounts and by such persons or entities as the Owner may direct, but the Contractor shall not be required to employ persons or entities to whom the Contractor has reasonable objection. § 3.8.2 Unless otherwise provided in the Contract Documents, .1 allowances shall cover the cost to the Contractor of materials and equipment delivered at the site and all required taxes, less applicable trade discounts; .2 Contractor’s costs for unloading and handling at the site, labor, installation costs, overhead, profit, and other expenses contemplated for stated allowance amounts shall be included in the Contract Sum but not in the allowances; and .3 whenever costs are more than or less than allowances, the Contract Sum shall be adjusted accordingly by Change Order. The amount of the Change Order shall reflect (1) the difference between actual costs and the allowances under Section 3.8.2.1 and (2) changes in Contractor’s costs under Section 3.8.2.2. § 3.8.3 Materials and equipment under an allowance shall be selected by the Owner with reasonable promptness. The Contractor shall identify the date for Owner’s selection on the critical path of the Contractor’s Construction Schedule and provide the Owner a minimum of two weeks notice before this date. § 3.9 Superintendent and Project Manager § 3.9.1 The Contractor shall employ a competent superintendent and project manager and necessary assistants who shall be in attendance at the Project site during performance of the Work. The superintendent and project manager shall represent the Contractor, and communications given to the superintendent or project manager shall be as binding as if given to the Contractor. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 18 § 3.9.2 The Contractor, as soon as practicable after award of the Contract, shall notify the Owner and Architect of the name and qualifications of a proposed superintendent and project manager. Within 14 days of receipt of the information, the Owner may notify the Contractor, stating whether the Owner (1) has reasonable objection to the proposed superintendent or project manager or (2) requires additional time for review. Failure of the Owner to provide notice within the 14-day period shall constitute notice of no reasonable objection. § 3.9.3 The Contractor shall not employ a proposed superintendent or project manager to whom the Owner has made reasonable and timely objection. The Contractor shall not change the superintendent or project manager without the Owner’s consent, which shall not unreasonably be withheld or delayed. § 3.9.4 The Superintendent employed by the Contractor shall have a minimum of five (5) years commercial experience as the primary Superintendent on projects of similar size and complexity as the Work. The superintendent shall speak fluent English and clearly understand the English language. The Contractor shall submit to the Owner a resume and other supporting documentation showing that the proposed Superintendent is competent and has the minimum work experience required to execute the Work. The Owner reserves the right to request additional supporting documentation regarding the proposed Superintendent's qualifications and to require the Contractor to propose an alternate Superintendent who better meets the requirements contained in this Article, as may reasonably be determined by the Owner. The Contractor shall notify the Architect and Owner in writing of any proposed replacement of the Superintendent. The Contractor shall not replace a competent Superintendent without prior written approval from the Owner. The requirements contained in this Article shall apply to any proposed replacement Superintendent, regardless if the proposed tenure is to be temporary or permanent. § 3.9.5 The Contractor shall employ a Project Manager to be assigned to the Work. The Project Manager employed by the Contractor shall have a minimum of five (5) years commercial experience as Project Manager on projects of similar size and complexity as the Work. The project manager shall speak fluent English and clearly understand the English language. The Contractor shall submit to the Owner a resume and other supporting documentation showing that the proposed Project Manager is competent and has the minimum work experience required to execute the Work. The Owner reserves the right to request additional supporting documentation regarding the proposed Project Manager's qualifications and to require the Contractor to propose an alternate Project Manager who better meets the requirements contained in this Article, as may reasonably be determined by the Owner. The Contractor shall notify the Architect and Owner in writing of any proposed replacement of the Project Manager. The Contractor shall not replace a competent Project Manager without prior written approval from the Owner. The requirements contained in this Article shall apply to any proposed replacement Project Manager, regardless if the proposed tenure is to be temporary or permanent. The Project Manager shall not act as the Superintendent or replacement for the Superintendent without written approval from the Owner. § 3.10 Contractor’s Construction and Submittal Schedules § 3.10.1 The Contractor, promptly after being awarded the Contract, shall submit for the Owner’s and Architect’s information a Contractor’s construction schedule for the Work. Unless otherwise required by the Contract Documents; the schedule shall contain details appropriate for the Project, including (1) the date of commencement of the Work, interim schedule milestone dates, and the date of Substantial Completion; (2) an apportionment of the Work by construction activity; and (3) the time required for completion of each portion of the Work. The schedule shall provide for the orderly progression of the Work to the Substantial Completion date and final completion date indicated in the Contract Documents. The schedule shall be revised at appropriate intervals as required by the conditions of the Work and Project. § 3.10.2 The Contractor, promptly after being awarded the Contract and thereafter as necessary to maintain a current submittal schedule, shall submit a submittal schedule in accordance with Section 3.12. Unless otherwise required by the Contract Documents, the submittal schedule shall (1) be coordinated with the Contractor’s construction schedule, and (2) allow the Architect reasonable time to review submittals. If the Contractor fails to submit a submittal schedule, or fails to provide submittals in accordance with the accepted submittal schedule, the Contractor shall not be entitled to any increase in Contract Sum or extension of Contract Time based on the time required for review of submittals. § 3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to the Owner and Architect. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 19 § 3.11 Documents and Samples at the Site The Contractor shall make available, at the Project site, the Contract Documents, including Change Orders, Construction Change Directives, and other modifications, in good order and marked currently to indicate field changes and selections made during construction, and the approved Shop Drawings, Product Data, Samples, and similar required submittals. These shall be in electronic form or paper copy, available to the Architect and Owner, and delivered to the Architect for submittal to the Owner upon completion of the Work as a record of the Work as constructed. § 3.12 Shop Drawings, Product Data and Samples § 3.12.1 Shop Drawings are drawings, diagrams, schedules, and other data specially prepared for the Work by the Contractor or a Subcontractor, Sub-subcontractor, manufacturer, supplier, or distributor to illustrate some portion of the Work. § 3.12.2 Product Data are illustrations, standard schedules, performance charts, instructions, brochures, diagrams, and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. § 3.12.3 Samples are physical examples that illustrate materials, equipment, or workmanship, and establish standards by which the Work will be judged. § 3.12.4 Shop Drawings, Product Data, Samples, and similar submittals are not Contract Documents. Their purpose is to demonstrate how the Contractor proposes to conform to the information given and the design concept expressed in the Contract Documents for those portions of the Work for which the Contract Documents require submittals. Review by the Architect is subject to the limitations of Section 4.2.7. Informational submittals upon which the Architect is not expected to take responsive action may be so identified in the Contract Documents. Submittals that are not required by the Contract Documents may be returned by the Architect without action. § 3.12.5 The Contractor shall review for compliance with the Contract Documents, approve, and submit to the Architect, Shop Drawings, Product Data, Samples, and similar submittals required by the Contract Documents, in accordance with the submittal schedule accepted by the Architect or, in the absence of an accepted submittal schedule, with reasonable promptness and in such sequence as to cause no delay in the Work or in the activities of the Owner or of Separate Contractors. § 3.12.6 By submitting Shop Drawings, Product Data, Samples, and similar submittals, the Contractor represents to the Owner and Architect that the Contractor has (1) reviewed and approved them, (2) determined and verified materials, field measurements and field construction criteria related thereto, or will do so, and (3) checked and coordinated the information contained within such submittals with the requirements of the Work and of the Contract Documents. § 3.12.7 The Contractor shall perform no portion of the Work for which the Contract Documents require submittal and review of Shop Drawings, Product Data, Samples, or similar submittals, until the respective submittal has been accepted by the Architect. § 3.12.8 The Work shall be in accordance with accepted submittals except that the Contractor shall not be relieved of responsibility for deviations from the requirements of the Contract Documents by the Architect’s acceptance of Shop Drawings, Product Data, Samples, or similar submittals, unless the Contractor has specifically notified the Architect of such deviation at the time of submittal and (1) the Architect has given written acceptance to the specific deviation in accordance with 3.12.9 as a minor change in the Work, or (2) a Change Order or Construction Change Directive has been issued authorizing the deviation. The Contractor shall not be relieved of responsibility for errors or omissions in Shop Drawings, Product Data, Samples, or similar submittals, by the Architect’s acceptance thereof. § 3.12.9 The Contractor shall direct specific attention, in writing on a cover letter attached to the original or on the case of a resubmittal, on resubmitted Shop Drawings, Product Data, Samples, or similar submittals, to all revisions or deviations other than those requested by the Architect on previous submittals. In the absence of such notice, the Architect’s acceptance of a resubmission shall not apply to such revisions or deviations. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 20 § 3.12.10 The Contractor shall not be required (delegated design) to provide professional services that constitute the practice of architecture or engineering unless such services are specifically required by the Contract Documents for a portion of the Work or unless the Contractor needs to provide such services in order to carry out the Contractor’s responsibilities for construction means, methods, techniques, sequences, and procedures. The Contractor shall not be required to provide professional services in violation of applicable law. § 3.12.10.1 If such delegated professional design services or certifications by a design professional related to systems, materials, or equipment are specifically required of the Contractor by the Contract Documents, the Owner and the Architect will provide all performance and design criteria that such services must satisfy. The Contractor shall be entitled to rely upon the adequacy and accuracy of the performance and design criteria provided in the Contract Documents. The Contractor shall cause such services or certifications to be provided by an appropriately licensed design professional, licensed in the state where the Project is located, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, Shop Drawings, and other submittals prepared by such professional. Shop Drawings, and other submittals related to the Work, designed or certified by such professional, if prepared by others, shall bear such professional’s written approval when submitted to the Architect. The Owner and the Architect shall be entitled to rely upon the adequacy and accuracy of the services, certifications, and approvals performed or provided by such design professionals, provided the Owner and Architect have provided to the Contractor the performance and design criteria that such services must satisfy. Pursuant to this Section 3.12.10, the Architect will review and take appropriate action on submittals only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. § 3.12.10.2 If the Contract Documents require the Contractor’s design professional to certify that the Work has been performed in accordance with the design criteria, the Contractor shall furnish such certifications to the Architect at the time and in the form specified by the Architect. § 3.12.11 The Architect’s review of Contractor’s submittals will be limited to examination of an initial submittal and one resubmittal. The Architect’s review of additional resubmittals will be made only with the consent of the Owner after notification by the Architect. The Owner shall deduct from the Contract Sum amounts paid to the Architect for evaluation of such additional resubmittals. § 3.13 Use of Site The Contractor shall confine operations at the site to areas permitted by applicable laws, statutes, ordinances, codes, rules and regulations, lawful orders of public authorities, and the Contract Documents and shall not unreasonably encumber the site with materials or equipment. § 3.14 Cutting and Patching § 3.14.1 The Contractor shall be responsible for cutting, fitting, or patching required to complete the Work or to make its parts fit together properly. All areas requiring cutting, fitting, or patching shall be restored to the condition existing prior to the cutting, fitting, or patching, unless otherwise required by the Contract Documents. § 3.14.2 The Contractor shall not damage or endanger a portion of the Work or fully or partially completed construction of the Owner or Separate Contractors by cutting, patching, or otherwise altering such construction, or by excavation. The Contractor shall not cut or otherwise alter construction by the Owner or a Separate Contractor except with written consent of the Owner and of the Separate Contractor. Consent shall not be unreasonably withheld. The Contractor shall not unreasonably withhold, from the Owner or a Separate Contractor, its consent to cutting or otherwise altering the Work. § 3.15 Cleaning Up § 3.15.1 The Contractor shall keep the premises and surrounding area free from accumulation of waste materials and rubbish caused by operations under the Contract. At completion of the Work, the Contractor shall remove waste materials, rubbish, the Contractor’s tools, construction equipment, machinery, and surplus materials from and about the Project. § 3.15.2 If the Contractor fails to clean up as provided in the Contract Documents, the Owner may do so and the Owner shall be entitled to reimbursement from the Contractor. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 21 § 3.16 Access to Work The Contractor shall provide the Owner and Architect with access to the Work in preparation and progress wherever located. § 3.17 Royalties, Patents and Copyrights The Contractor shall pay all royalties and license fees. The Contractor shall defend suits or claims for infringement of copyrights and patent rights and shall hold the Owner and Architect harmless from loss on account thereof, but shall not be responsible for defense or loss when a particular design, process, or product of a particular manufacturer or manufacturers is required by the Contract Documents, or where the copyright violations are contained in Drawings, Specifications, or other documents prepared by the Owner or Architect. However, if an infringement of a copyright or patent is discovered by, or made known to, the Contractor, the Contractor shall be responsible for the loss unless the information is promptly furnished to the Architect. § 3.18 Indemnification § 3.18.1 To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the Owner, Architect, Architect’s consultants, and agents and employees of any of them from and against claims, damages, losses, and expenses, including but not limited to attorneys’ fees, arising out of or resulting from performance of the Work, provided that such claim, damage, loss, or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself), but only to the extent caused by the negligent acts or omissions of the Contractor, a Subcontractor, anyone directly or indirectly employed by them, or anyone for whose acts they may be liable, regardless of whether or not such claim, damage, loss, or expense is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge, or reduce other rights or obligations of indemnity that would otherwise exist as to a party or person described in this Section 3.18. § 3.18.2 In claims against any person or entity indemnified under this Section 3.18 by an employee of the Contractor, a Subcontractor, anyone directly or indirectly employed by them, or anyone for whose acts they may be liable, the indemnification obligation under Section 3.18.1 shall not be limited by a limitation on amount or type of damages, compensation, or benefits payable by or for the Contractor or a Subcontractor under workers’ compensation acts, disability benefit acts, or other employee benefit acts. ARTICLE 4 ARCHITECT § 4.1 General § 4.1.1 The Architect is the person or entity retained by the Owner pursuant to Section 2.3.2 and identified as such in the Agreement. Such terms as ‘Architect-Engineer,’ ‘Engineer,’ and ‘A-E,’ if used in these Contract Documents, is intended to mean the Architect and its consultants unless otherwise intended by the context or usage of such terms. Such terms do not mean or include any design professional of the Contractor, Subcontractor, or Owner. § 4.1.2 Duties, responsibilities, and limitations of authority of the Architect as set forth in the Contract Documents shall not be restricted, modified, or extended without written consent of the Owner, Contractor, and Architect. Consent shall not be unreasonably withheld. § 4.1.3 Subject to the standard of care for applying professional judgment to information used or relied upon, Architect and its Consultants may use and rely upon design elements, technical standards, test results, and all other information ordinarily or customarily furnished or published by others, including, but not limited to, specialty contractors, manufacturers, fabricators, and suppliers. § 4.2 Administration of the Contract § 4.2.1 The Architect will provide administration of the Contract as described in the Contract Documents and will be an Owner’s representative during construction until the date the Architect issues the final Certificate for Payment. The Architect will have authority to act on behalf of the Owner only to the extent provided in the Contract Documents. § 4.2.2 The Architect will visit the site as agreed with the Owner, to become generally familiar with the progress and quality of the portion of the Work completed, and to determine in general if the Work observed is being performed in a manner indicating that the Work, when fully completed, will be in general compliance with the Contract Documents. However, the Architect will not be required to make exhaustive or continuous on-site inspections to AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 22 check the quality or quantity of the Work. The Architect will not have control over, charge of, or responsibility for the construction means, methods, techniques, sequences or procedures, or for the safety precautions and programs in connection with the Work, since these are solely the Contractor’s rights and responsibilities under the Contract Documents. § 4.2.2.1 The Contractor shall reimburse the Owner for compensation paid to the Architect for additional site visits made necessary by the fault, neglect or request of the Contractor. § 4.2.3 On the basis of the site visits, the Architect will keep the Owner reasonably informed about the progress and quality of the portion of the Work completed, and endeavor to report to the Owner (1) known deviations from the Contract Documents, (2) known deviations from the most recent construction schedule submitted by the Contractor, and (3) known defects and deficiencies in the Work. The Architect will not be responsible for the Contractor’s failure to perform the Work in accordance with the requirements of the Contract Documents. The Architect will not have control over or charge of, and will not be responsible for acts or omissions of, the Contractor, Subcontractors, or their agents or employees, or any other persons or entities performing portions of the Work. § 4.2.4 Communications The Owner and Contractor shall include the Architect in all communications that relate to or affect the Architect’s services or professional responsibilities. The Owner shall promptly notify the Architect of the substance of any direct communications between the Owner and the Contractor otherwise relating to the Project. Communications by and with the Architect’s consultants shall be through the Architect. Communications by and with Subcontractors and suppliers shall be through the Contractor. Communications by and with Separate Contractors shall be through the Owner. The Contract Documents may specify other communication protocols. § 4.2.5 Based on the Architect’s evaluations of the Contractor’s Applications for Payment, the Architect will review and certify the amounts due the Contractor and will issue Certificates for Payment in such amounts. § 4.2.6 The Architect has authority to reject Work that does not conform to the Contract Documents. Whenever the Architect considers it necessary or advisable, the Architect will have authority to require inspection or testing of the Work in accordance with Sections 13.4.2 and 13.4.3, whether or not the Work is fabricated, installed or completed. However, neither this authority of the Architect nor a decision made in good faith either to exercise or not to exercise such authority shall give rise to a duty or responsibility of the Architect to the Contractor, Subcontractors, suppliers, their agents or employees, or other persons or entities performing portions of the Work. § 4.2.7 The Architect will review and take appropriate action upon, the Contractor’s submittals such as Shop Drawings, Product Data, and Samples, but only for the limited purpose of checking for general conformance with information given and the design concept expressed in the Contract Documents. The Architect’s action will be taken with reasonable promptness while allowing sufficient time in the Architect’s professional judgment to permit adequate review. Review of such submittals is not conducted for the purpose of determining the accuracy and completeness of other details such as dimensions and quantities, or for substantiating instructions for installation or performance of equipment or systems, all of which remain the responsibility of the Contractor. The Architect’s review of the Contractor’s submittals shall not relieve the Contractor of the obligations under Sections 3.3, 3.5, and 3.12. The Architect’s review shall not constitute acceptance of safety precautions or of any construction means, methods, techniques, sequences, or procedures. The Architect’s acceptance of a specific item shall not indicate acceptance of an assembly of which the item is a component. § 4.2.8 The Architect will prepare Change Orders and Construction Change Directives, and may order minor changes in the Work as provided in Section 7.4. The Architect will review and make determinations regarding concealed and unknown conditions as provided in Section 3.7.4. § 4.2.9 The Architect will conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion pursuant to Section 9.8; receive and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract and assembled by the Contractor pursuant to Section 9.10; and issue a final Certificate for Payment pursuant to Section 9.10. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 23 § 4.2.10 If the Owner and Architect agree, the Architect will provide one or more Project representatives to assist in carrying out the Architect’s responsibilities at the site. The Owner shall notify the Contractor of any change in the duties, responsibilities and limitations of authority of the Project representatives. § 4.2.11 The Architect will interpret and decide matters concerning performance under, and requirements of, the Contract Documents on written request of either the Owner or Contractor. The Architect’s response to such requests will be made in writing within any time limits agreed upon or otherwise with reasonable promptness. § 4.2.12 Interpretations and decisions of the Architect will be consistent with the intent of, and reasonably inferable from, the Contract Documents and will be in writing or in the form of drawings. When making such interpretations and decisions, the Architect will endeavor to secure faithful performance by both Owner and Contractor, will not show partiality to either, and will not be liable for results of interpretations or decisions rendered in good faith. § 4.2.13 The Architect’s decisions on matters relating to aesthetic effect will be final if consistent with the intent expressed in the Contract Documents. § 4.2.14 The Architect will review and respond to requests for information about the Contract Documents. The Architect’s response to such requests will be made in writing within any time limits agreed upon or otherwise with reasonable promptness. If appropriate, the Architect will prepare and issue supplemental Drawings and Specifications in response to the requests for information. ARTICLE 5 SUBCONTRACTORS § 5.1 Definitions § 5.1.1 A Subcontractor is a person or entity who has a direct contract with the Contractor to perform a portion of the Work at the site. The term “Subcontractor” is referred to throughout the Contract Documents as if singular in number and means a Subcontractor or an authorized representative of the Subcontractor. The term “Subcontractor” does not include a Separate Contractor or the subcontractors of a Separate Contractor. § 5.1.2 A Sub-subcontractor is a person or entity who has a direct or indirect contract with a Subcontractor to perform a portion of the Work at the site. The term “Sub-subcontractor” is referred to throughout the Contract Documents as if singular in number and means a Sub-subcontractor or an authorized representative of the Sub- subcontractor. § 5.2 Award of Subcontracts and Other Contracts for Portions of the Work § 5.2.1 Unless otherwise stated in the Contract Documents, the Contractor, as soon as practicable after award of the Contract, shall submit to the Owner and Architect the persons or entities proposed for each principal portion of the Work (list of proposed subcontractors), including those who are to furnish materials or equipment fabricated to a special design no later than two days prior to the date of the Pre-construction Conference. Include Contractor’s License number and Class for each subcontractor. Within 14 days of receipt of the information, the Owner may notify the Contractor whether the Owner (1) has reasonable objection to any such proposed person or entity or (2) requires additional time for review. Failure of the Owner to provide notice within the 14-day period shall constitute notice of no reasonable objection. § 5.2.2 The Contractor shall not contract with a proposed person or entity to whom the Owner or Architect has made reasonable and timely objection. The Contractor shall not be required to contract with anyone to whom the Contractor has made reasonable objection. § 5.2.3 If the Owner has reasonable objection to a person or entity proposed by the Contractor, the Contractor shall propose another to whom the Owner or Architect has no reasonable objection. If the proposed but rejected Subcontractor was reasonably capable of performing the Work, the Contract Sum and Contract Time shall be increased or decreased by the difference, if any, occasioned by such change, and an appropriate Change Order shall be issued before commencement of the substitute Subcontractor’s Work. However, no increase in the Contract Sum or Contract Time shall be allowed for such change unless the Contractor has acted promptly and responsively in submitting names as required. § 5.2.4 The Contractor shall not substitute a Subcontractor, person, or entity for one previously selected if the Owner makes reasonable objection to such substitution. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 24 § 5.3 Subcontractual Relations By appropriate written agreement, the Contractor shall require each Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by terms of the Contract Documents, and to assume toward the Contractor all the obligations and responsibilities, including the responsibility for safety of the Subcontractor’s Work that the Contractor, by these Contract Documents, assumes toward the Owner and Architect. Each subcontract agreement shall preserve and protect the rights of the Owner and Architect under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights, and shall allow to the Subcontractor, unless specifically provided otherwise in the subcontract agreement, the benefit of all rights, remedies, and redress against the Contractor that the Contractor, by the Contract Documents, has against the Owner. Where appropriate, the Contractor shall require each Subcontractor to enter into similar agreements with Sub-subcontractors. The Contractor shall make available to each proposed Subcontractor, prior to the execution of the subcontract agreement, copies of the complete Contract Documents to which the Subcontractor will be bound, and, upon written request of the Subcontractor, identify to the Subcontractor terms and conditions of the proposed subcontract agreement that may be at variance with the Contract Documents. Subcontractors shall similarly make available copies of the complete Contract Documents to their respective proposed Sub-subcontractors. § 5.4 Contingent Assignment of Subcontracts § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and Contractor; and .2 assignment is subject to the prior rights of the surety, if any, obligated under bond relating to the Contract. When the Owner accepts the assignment of a subcontract agreement, the Owner assumes the Contractor’s rights and obligations under the subcontract. § 5.4.2 Upon such assignment, if the Work has been suspended for more than 30 days, the Subcontractor’s compensation shall be equitably adjusted for increases in cost resulting from the suspension. § 5.4.3 Upon assignment to the Owner under this Section 5.4, the Owner may further assign the subcontract to a successor contractor or other entity. If the Owner assigns the subcontract to a successor contractor or other entity, the Owner shall nevertheless remain legally responsible for all of the successor contractor’s obligations under the subcontract. ARTICLE 6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS § 6.1 Owner’s Right to Perform Construction and to Award Separate Contracts § 6.1.1 The term “Separate Contractor(s)” shall mean other contractors retained by the Owner under separate agreements. The Owner reserves the right to perform construction or operations related to the Project with the Owner’s own forces, and with Separate Contractors retained under Conditions of the Contract substantially similar to those of this Contract, including those provisions of the Conditions of the Contract related to insurance and waiver of subrogation. § 6.1.2 When separate contracts are awarded for different portions of the Project or other construction or operations on the site, the term “Contractor” in the Contract Documents in each case shall mean the Contractor who executes each separate Owner-Contractor Agreement. § 6.1.3 The Owner shall provide for coordination of the activities of the Owner’s own forces and of each Separate Contractor with the Work of the Contractor, who shall cooperate with them. The Contractor shall participate with any Separate Contractors and the Owner in reviewing their construction schedules. The Contractor shall make any revisions to its construction schedule deemed necessary after a joint review and mutual agreement. The construction schedules shall then constitute the schedules to be used by the Contractor, Separate Contractors, and the Owner until subsequently revised. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 25 § 6.1.4 Unless otherwise provided in the Contract Documents, when the Owner performs construction or operations related to the Project with the Owner’s own forces or with Separate Contractors, the Owner or its Separate Contractors shall have the same obligations and rights that the Contractor has under the Conditions of the Contract, including, without excluding others, those stated in Article 3, this Article 6, and Articles 10, 11, and 12. § 6.2 Mutual Responsibility § 6.2.1 The Contractor shall afford the Owner and Separate Contractors reasonable opportunity for introduction and storage of their materials and equipment and performance of their activities, and shall connect and coordinate the Contractor’s construction and operations with theirs as required by the Contract Documents. § 6.2.2 If part of the Contractor’s Work depends for proper execution or results upon construction or operations by the Owner or a Separate Contractor, the Contractor shall, prior to proceeding with that portion of the Work, promptly notify the Owner and Architect of apparent discrepancies or defects in the construction or operations by the Owner or Separate Contractor that would render it unsuitable for proper execution and results of the Contractor’s Work. Failure of the Contractor to notify the Owner and Architect of apparent discrepancies or defects prior to proceeding with the Work shall constitute an acknowledgment that the Owner’s or Separate Contractor’s completed or partially completed construction is fit and proper to receive the Contractor’s Work. The Contractor shall not be responsible for discrepancies or defects in the construction or operations by the Owner or Separate Contractor that are not apparent. § 6.2.3 The Contractor shall reimburse the Owner for costs the Owner incurs that are payable to a Separate Contractor because of the Contractor’s delays, improperly timed activities or defective construction. The Owner shall be responsible to the Contractor for costs the Contractor incurs because of a Separate Contractor’s delays, improperly timed activities, damage to the Work or defective construction. § 6.2.4 The Contractor shall promptly remedy damage that the Contractor wrongfully causes to completed or partially completed construction or to property of the Owner or Separate Contractor as provided in Section 10.2.5. § 6.2.5 The Owner and each Separate Contractor shall have the same responsibilities for cutting and patching as are described for the Contractor in Section 3.14. § 6.3 Owner’s Right to Clean Up If a dispute arises among the Contractor, Separate Contractors, and the Owner as to the responsibility under their respective contracts for maintaining the premises and surrounding area free from waste materials and rubbish, the Owner may clean up and the Architect will allocate the cost among those responsible between the Owner, Separate Contractors, and Contractor. ARTICLE 7 CHANGES IN THE WORK § 7.1 General § 7.1.1 Changes in the Work may be accomplished after execution of the Contract, and without invalidating the Contract, by Change Order, Construction Change Directive or order for a minor change in the Work, subject to the limitations stated in this Article 7 and elsewhere in the Contract Documents. § 7.1.1.1 A Change Order is a written instrument prepared by the Architect and signed by the Owner, Contractor, and Architect stating their agreement upon all of the following: .1 The change in the Work; .2 The amount of the adjustment, if any, in the Contract Sum; and .3 The extent of the adjustment, if any, in the Contract Time. § 7.1.1.2 A Construction Change Directive shall be used in the absence of total agreement on the terms of a Change Order. A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, or other revisions, the Contract Sum and Contract Time being adjusted accordingly. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 26 § 7.1.1.2.1 If the Construction Change Directive provides for an adjustment to the Contract Sum, the adjustment shall be based on one of the following methods: .1 Mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to permit evaluation; .2 Unit prices stated in the Contract Documents or subsequently agreed upon; .3 Cost to be determined in a manner agreed upon by the parties and a mutually acceptable fixed or percentage fee; or .4 As provided in Section 7.2. § 7.1.1.2.2 Upon receipt of a Construction Change Directive, the Contractor shall promptly proceed with the change in the Work involved and advise the Architect of the Contractor’s agreement or disagreement with the method, if any, provided in the Construction Change Directive for determining the proposed adjustment in the Contract Sum or Contract Time. § 7.1.1.2.3 A Construction Change Directive signed by the Contractor indicates the Contractor’s agreement therewith, including adjustment in Contract Sum and Contract Time or the method for determining them. Such agreement shall be effective immediately and shall be recorded as a Change Order. § 7.1.1.2.4 Pending final determination of the total cost of a Construction Change Directive to the Owner, the Contractor may request payment for Work completed under the Construction Change Directive in Applications for Payment. The Architect will make an interim determination for purposes of monthly certification for payment for those costs and certify for payment the amount that the Architect determines, in the Architect’s professional opinion, to be reasonably justified. The Architect’s interim determination of cost shall adjust the Contract Sum on the same basis as a Change Order, subject to the right of either party to disagree and assert a Claim in accordance with Article 15. § 7.1.2 A Change Order shall be based upon agreement among the Owner, Contractor, and Architect. A Construction Change Directive requires agreement by the Owner and Architect and may or may not be agreed to by the Contractor. § 7.1.3 Changes in the Work shall be performed under applicable provisions of the Contract Documents. The Contractor shall proceed promptly with changes in the Work, unless otherwise provided in the Change Order, Construction Change Directive, or order for a minor change in the Work. § 7.1.4 If a change in the Work results in an adjustment to the Contract Sum, the adjustment (increase or decrease) shall be based on the following, unless noted otherwise: .1 Material quantities and unit prices (separated into trades; include sales tax). .2 Labor costs (raw cost). .3 Labor burden, applied to labor only, including but not limited to, worker’s compensation and public liability, social security tax, old age and unemployment insurance, union welfare fund and fringe benefits. Contractor shall be required to substantiate the labor burden percentage applied to any change in contract amount. Labor burden percentage shall not exceed 30% in any case. .4 Construction equipment cost. .5 Overhead and profit combined (on Claims for net increase only), as defined in Section 7.3.11. .6 Cost of Premiums for Bonds (for Contractor only). Evidence of additional premium for bond shall be submitted with Claim. .7 Extended Overhead Costs (if applicable) which shall be established by pro-rating the value of supervision, temporary facility, and General Conditions and all other direct and indirect costs of Contractor included in the Contract Sum over the number of days included in the Contract Time. § 7.2.1 If the Contractor does not respond promptly or disagrees with the method for adjustment in the Contract Sum, the Architect shall determine the adjustment on the basis of reasonable expenditures and savings of those performing the Work attributable to the change, including, in case of an increase in the Contract Sum, an amount for overhead and profit as set forth in the Agreement, or if no such amount is set forth, a reasonable amount. In such case, and also under Section 7.1.1.2.1.3, the Contractor shall keep and present, in such form as the Architect may prescribe, an itemized accounting together with appropriate supporting data which shall include, at the Architect’s AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 27 sole discretion, a cost breakdown itemized in accordance with the current appropriate Data Book and edition of R.S. Means Company, Inc., or other source of construction industry cost data acceptable to the Architect. .1 Overhead shall include, but not be limited to, project management, field office personnel including supervision, superintendence, wages of timekeepers, watchmen and clerks, small tools, incidentals, general office expenses, insurance premiums, and all other expenses not included in “costs.” .2 If the net value of the change results in a credit, the credit given shall be the net cost without overhead or profit (for Contractor, Subcontractor, or Sub-contractor). The cost as used herein shall include all items of labor, materials, equipment premiums, and bonds. § 7.2.2 If the Contractor disagrees with the adjustment in the Contract Time, the Contractor may make a Claim in accordance with applicable provisions of Article 15. § 7.2.3 The amount of credit to be allowed by the Contractor to the Owner for a deletion or change that results in a net decrease in the Contract Sum shall be actual net cost as confirmed by the Architect. When both additions and credits covering related Work or substitutions are involved in a change, the allowance for overhead and profit shall be figured on the basis of net increase, if any, with respect to that change. § 7.2.4When the Owner and Contractor agree with a determination made by the Architect concerning the adjustments in the Contract Sum and Contract Time, or otherwise reach agreement upon the adjustments, such agreement shall be effective immediately and the Architect will prepare a Change Order. Change Orders may be issued for all or any part of a Construction Change Directive. § 7.3. In Sections 7.2 and 7.2.1, the amount for overhead and profit combined, included in the total cost to the Owner, shall be based on the following schedule: .1 for the Contractor, for Work performed by the Contractor's own forces, 15 percent of the cost. .2 for the Contractor, for Work performed by the Contractor’s Subcontractors, 5 percent of the amount due the Subcontractors. .3 for each Subcontractor involved, for Work performed by that Subcontractor's own forces, 15 percent of the cost. .4 for each Subcontractor involved, for Work performed by the Subcontractor’s Sub-subcontractor, 5 percent of the amount due the Sub-subcontractor. .5 cost to which overhead and profit is to be applied shall be determined in accordance with Section 7.2. .6 In order to facilitate checking of quotations for extras or credits, all proposals, except those so minor that their propriety can be seen by inspection, shall be accompanied by a complete itemization of costs in the manner prescribed above. Where major cost items are changes to Subcontracts, they shall be itemized also. In no case will a change involving over $500.00 be approved without such itemization. § 7.4 Minor Changes in the Work In the Architect’s opinion, Architect may order minor changes in the Work that are consistent with the intent of the Contract Documents and do not involve an adjustment in the Contract Sum or an extension of the Contract Time. The Architect’s order for minor changes shall be in writing. If the Contractor believes that the proposed minor change in the Work will affect the Contract Sum or Contract Time, the Contractor shall notify the Architect and shall not proceed to implement the change in the Work. If the Contractor performs the Work set forth in the Architect’s order for a minor change without prior notice to the Architect that such change will affect the Contract Sum or Contract Time, the Contractor waives any adjustment to the Contract Sum or extension of the Contract Time. ARTICLE 8 TIME § 8.1 Definitions § 8.1.1 Unless otherwise provided, Contract Time is the period of time, including authorized adjustments, allotted in the Contract Documents for Substantial Completion of the Work. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 28 § 8.1.2 The date of commencement of the Work is the date established in the Agreement. § 8.1.3 The date of Substantial Completion is the date certified by the Architect in accordance with Section 9.8. § 8.1.4 The term “day” as used in the Contract Documents shall mean calendar day unless otherwise specifically defined. § 8.2 Progress and Completion § 8.2.1 Time limits stated in the Contract Documents are of the essence of the Contract. By executing the Agreement, the Contractor confirms that the Contract Time is a reasonable period for performing the Work. § 8.2.2 The Contractor shall not knowingly, except by agreement or instruction of the Owner in writing, commence the Work prior to the effective date of insurance required to be furnished by the Contractor and Owner. § 8.2.3 The Contractor shall proceed expeditiously with adequate forces and shall achieve Substantial Completion within the Contract Time. § 8.3 Delays and Extensions of Time § 8.3.1 If the Contractor is delayed at any time in the commencement or progress of the Work by (1) an act or neglect of the Owner or Architect, of an employee of either, or of a Separate Contractor; (2) by changes ordered in the Work; (3) by labor disputes, fire, unavoidable casualties, adverse weather conditions documented in accordance with Section 15.1.6.2, or other causes beyond the Contractor’s control; (4) by delay authorized by the Owner pending mediation and binding dispute resolution; or (5) by other causes that the Contractor asserts, and the Architect determines, justify delay, then the Contract Time shall be extended for such reasonable time as the Architect may determine and the Owner approves. § 8.3.2 Claims relating to time shall be made in accordance with applicable provisions of Article 15. § 8.3.3 This Section 8.3 does not preclude recovery of damages for delay by either party under other provisions of the Contract Documents. ARTICLE 9 PAYMENTS AND COMPLETION § 9.1 Contract Sum § 9.1.1 The Contract Sum is stated in the Agreement and, including authorized adjustments, is the total amount payable by the Owner to the Contractor for performance of the Work under the Contract Documents. § 9.1.2 If unit prices are stated in the Contract Documents or subsequently agreed upon, and if quantities originally contemplated are materially changed so that application of such unit prices to the actual quantities causes substantial inequity to the Owner or Contractor, the applicable unit prices shall be equitably adjusted. § 9.2 Schedule of Values Where the Contract is based on a stipulated sum or Guaranteed Maximum Price, the Contractor shall submit a schedule of values to the Architect before the first Application for Payment, allocating the entire Contract Sum to the various portions of the Work. The schedule of values shall be prepared in the form, and supported by the data to substantiate its accuracy, required by the Architect. This schedule, unless objected to by the Architect, shall be used as a basis for reviewing the Contractor’s Applications for Payment. Any changes to the schedule of values shall be submitted to the Architect and supported by such data to substantiate its accuracy as the Architect may require, and unless objected to by the Architect, shall be used as a basis for reviewing the Contractor’s subsequent Applications for Payment. § 9.3 Applications for Payment § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The application shall be notarized, if required, and supported by all data substantiating the Contractor’s right to payment that the Owner or Architect require, such as copies of requisitions, and releases and waivers of liens from Subcontractors and suppliers, and shall reflect retainage if provided for in the Contract Documents. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 29 § 9.3.1.1 As provided in Section 7.1.1.2.4, such applications may include requests for payment on account of changes in the Work that have been properly authorized by Construction Change Directives, or by interim determinations of the Architect, but not yet included in Change Orders. § 9.3.1.2 Applications for Payment shall not include requests for payment for portions of the Work for which the Contractor does not intend to pay a Subcontractor or supplier, unless such Work has been performed by others whom the Contractor intends to pay. § 9.3.1.3 Until final completion, the Owner will pay 95% of the amount due the Contractor on account of progress payments. § 9.3.2 Unless otherwise provided in the Contract Documents, payments shall be made on account of materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work. If approved in advance by the Owner, payment may similarly be made for materials and equipment suitably stored off the site at a location agreed upon in writing. Payment for materials and equipment stored on or off the site shall be conditioned upon compliance by the Contractor with procedures satisfactory to the Owner to establish the Owner’s title to such materials and equipment or otherwise protect the Owner’s interest, and shall include the costs of applicable insurance, storage, and transportation to the site, for such materials and equipment stored off the site. § 9.3.2.1 Contractor shall provide invoices, package slips, or other form of supporting data for materials stored onsite claimed on the progress payment, unless it can be verified through on-site observations. Maintain concise bill of materials and label materials stored on-site for ready identification and verification. § 9.3.3 The Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner no later than the time of payment. The Contractor further warrants that upon submittal of an Application for Payment all Work for which Certificates for Payment have been previously issued and payments received from the Owner shall, to the best of the Contractor’s knowledge, information, and belief, be free and clear of liens, claims, security interests, or encumbrances, in favor of the Contractor, Subcontractors, suppliers, or other persons or entities that provided labor, materials, and equipment relating to the Work. § 9.4 Certificates for Payment § 9.4.1 The Architect will, unless otherwise agreed upon, within seven working days after receipt of the Contractor’s Application for Payment, either (1) issue to the Owner a Certificate for Payment in the full amount of the Application for Payment, with a copy to the Contractor; or (2) issue to the Owner a Certificate for Payment for such amount as the Architect determines is properly due, and notify the Contractor and Owner of the Architect’s reasons for withholding certification in part as provided in Section 9.5.1; or (3) withhold certification of the entire Application for Payment, and notify the Contractor and Owner of the Architect’s reason for withholding certification in whole as provided in Section 9.5.1. § 9.4.2 The issuance of a Certificate for Payment will constitute a representation by the Architect to the Owner, based on the Architect’s evaluation of the Work and the data in the Application for Payment, that, to the best of the Architect’s knowledge, information, and belief, the Work has progressed to the point indicated, the quality of the Work is in general conformance with the Contract Documents, and that the Contractor is entitled to payment in the amount certified. The foregoing representations are subject to an evaluation of the Work for general conformance with the Contract Documents upon Substantial Completion, to results of subsequent tests and inspections, to correction of minor deviations from the Contract Documents prior to completion, and to specific qualifications expressed by the Architect. However, the issuance of a Certificate for Payment is not a representation that the Architect has (1) made exhaustive or continuous on-site inspections to check the quality or quantity of the Work; (2) reviewed construction means, methods, techniques, sequences, or procedures; (3) reviewed copies of requisitions received from Subcontractors and suppliers and other data requested by the Owner to substantiate the Contractor’s right to payment; or (4) made examination to ascertain how or for what purpose the Contractor has used money previously paid on account of the Contract Sum. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 30 § 9.5 Decisions to Withhold Certification § 9.5.1 The Architect may withhold a Certificate for Payment in whole or in part, to the extent reasonably necessary to protect the Owner, if in the Architect’s opinion the representations to the Owner required by Section 9.4.2 cannot be made. If the Architect is unable to certify payment in the amount of the Application, the Architect will notify the Contractor and Owner as provided in Section 9.4.1. If the Contractor and Architect cannot agree on a revised amount, the Architect will promptly issue a Certificate for Payment for the amount for which the Architect is able to make such representations to the Owner. The Architect may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued, to such extent as may be necessary in the Architect’s opinion to protect the Owner from loss for which the Contractor is responsible, including loss resulting from acts and omissions described in Section 3.3.2, because of .1 defective Work not remedied; .2 third party claims filed or reasonable evidence indicating probable filing of such claims, unless security acceptable to the Owner is provided by the Contractor; .3 failure of the Contractor to make payments properly to Subcontractors or suppliers for labor, materials or equipment; .4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum; .5 damage to the Owner or a Separate Contractor; .6 reasonable evidence that the Work will not be completed within the Contract Time, and that the unpaid balance would not be adequate to cover actual or liquidated damages for the anticipated delay; or .7 repeated failure to carry out the Work in accordance with the Contract Documents. § 9.5.2 When either party disputes the Architect’s decision regarding a Certificate for Payment under Section 9.5.1, in whole or in part, that party may submit a Claim in accordance with Article 15. § 9.5.3 When the reasons for withholding certification are removed, certification will be made for amounts previously withheld. § 9.5.4 If the Architect withholds certification for payment under Section 9.5.1.3, the Owner may, at its sole option, issue joint checks to the Contractor and to any Subcontractor or supplier to whom the Contractor failed to make payment for Work properly performed or material or equipment suitably delivered. If the Owner makes payments by joint check, the Owner shall notify the Architect and the Contractor shall reflect such payment on its next Application for Payment. § 9.6 Progress Payments § 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and shall so notify the Architect. § 9.6.1.1 The Owner may withhold payments to the Contractor notwithstanding the Architect’s certification if it is necessary, in the Owner’s opinion, to do so to protect the Owner from loss due to any of the reasons set forth in Sections 9.5.1.1 through 9.5.1.7. § 9.6.2 Payment of Subcontractors § 9.6.2.1 The Contractor shall pay each Subcontractor, no later than seven days after receipt of payment from the Owner, the amount to which the Subcontractor is entitled, reflecting percentages actually retained from payments to the Contractor on account of the Subcontractor’s portion of the Work. The Contractor shall, by appropriate agreement with each Subcontractor, require each Subcontractor to make payments to Sub-subcontractors in a similar manner. § 9.6.2.2 Within seven (7) working days after receipt of amounts paid to the Contractor by the Owner for Work performed under this Agreement, the Contractor shall do one of the following: a. Pay each Subcontractor for the proportional share of the total payment received from the Owner attributable to the Work performed by the respective Subcontractor under This Agreement; or b. Notify the Owner and Architect, and Subcontractor, in writing, of the Contractor's intention to withhold all or part of the Subcontractor's payment with the reason for nonpayment. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 31 § 9.6.2.3 The Contractor shall pay interest to each Subcontractor on all amounts owed by the Contractor that remain unpaid after seven (7) days following receipt by the Contractor of payment from the Owner for Work performed by the affected Subcontractor under this Agreement, except for amounts withheld as allowed in Section 9.6.8.1. Unless otherwise provided under the terms of this Agreement, for purposes solely of these prompt payment provisions, interest shall accrue at the rate of one percent (1%) per month. § 9.6.2.4 In each Subcontract, the Contractor shall include a provision requiring each Subcontractor to include or otherwise be subject to the same payment and interest requirements with respect to each lower-tier Subcontractor (Sub-Subcontractor). § 9.6.2.5 The Contractor’s obligation to pay interest to a Subcontractor pursuant to the prompt payment provisions is not an obligation of the Owner, and no modification shall be made to this Agreement and no cost reimbursements claim shall be made for the purpose of providing reimbursement by Owner for such interest charge. § 9.6.3 The Architect will, on request, furnish to a Subcontractor, if practicable, information regarding percentages of completion or amounts applied for by the Contractor and action taken thereon by the Architect and Owner on account of portions of the Work done by such Subcontractor. § 9.6.4 The Owner has the right to request written evidence from the Contractor that the Contractor has properly paid Subcontractors and suppliers amounts paid by the Owner to the Contractor for subcontracted Work. If the Contractor fails to furnish such evidence within seven days, the Owner shall have the right to contact Subcontractors and suppliers to ascertain whether they have been properly paid. Neither the Owner nor Architect shall have an obligation to pay, or to see to the payment of money to, a Subcontractor or supplier, except as may otherwise be required by law. § 9.6.5 The Contractor’s payments to suppliers shall be treated in a manner similar to that provided in Sections 9.6.2, 9.6.3 and 9.6.4. § 9.6.6 A Certificate for Payment, a progress payment, or partial or entire use or occupancy of the Project by the Owner shall not constitute acceptance of Work not in accordance with the Contract Documents. § 9.6.7 Unless the Contractor provides the Owner with a payment bond in the full penal sum of the Contract Sum, payments received by the Contractor for Work properly performed by Subcontractors or provided by suppliers shall be held by the Contractor for those Subcontractors or suppliers who performed Work or furnished materials, or both, under contract with the Contractor for which payment was made by the Owner. Nothing contained herein shall require money to be placed in a separate account and not commingled with money of the Contractor, create any fiduciary liability or tort liability on the part of the Contractor for breach of trust, or entitle any person or entity to an award of punitive damages against the Contractor for breach of the requirements of this provision. § 9.6.8 Provided the Owner has fulfilled its payment obligations under the Contract Documents, the Contractor shall defend and indemnify the Owner from all loss, liability, damage or expense, including reasonable attorney’s fees and litigation expenses, arising out of any lien claim or other claim for payment by any Subcontractor or supplier of any tier. Upon receipt of notice of a lien claim or other claim for payment, the Owner shall notify the Contractor. If approved by the applicable court, when required, the Contractor may substitute a surety bond for the property against which the lien or other claim for payment has been asserted. § 9.7 Failure of Payment If, unless otherwise agreed upon, the Architect does not issue a Certificate for Payment, through no fault of the Contractor, within seven working days after receipt of the Contractor’s Application for Payment, or if the Owner does not pay the Contractor within seven working days after the date established in the Contract Documents, the amount certified by the Architect or awarded by binding dispute resolution, then the Contractor may, upon seven additional working days’ notice to the Owner and Architect, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Contractor’s reasonable costs of shutdown, delay and start-up, plus interest as provided for in the Contract Documents. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 32 § 9.8 Substantial Completion § 9.8.1 Substantial Completion is the stage when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner fully can occupy or utilize the Work or designated portion thereof, for its intended use with all of the Work’s parts and systems operable as required by the Contract Documents. Only incidental cleaning, if required beyond cleaning needed for the Owner’s full occupancy or utilization, may remain for final completion. § 9.8.2 When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall prepare and submit to the Architect a comprehensive list of items to be completed or corrected. Failure to include an item on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. § 9.8.3 Upon receipt of the Contractor’s list, the Architect will make an inspection to determine whether the Work or designated portion thereof is substantially complete. If the Architect discloses any item, whether or not included on the Contractor’s list, which is not sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work or designated portion thereof for its intended use, the Contractor shall, before issuance of the Certificate of Substantial Completion, complete or correct such item upon notification by the Architect. In such case, the Contractor shall then submit a request for another inspection by the Architect to determine Substantial Completion. § 9.8.3.1 The Architect will provide no more than one (1) PIC/PM to provide up to two (2) inspections to determine whether the Work or a designated portion thereof has attained Substantial Completion in accordance with the Contract Documents. The Owner shall deduct from the Contract Sum amounts paid to the Architect for any additional inspections. § 9.8.4 When the Work or designated portion thereof is substantially complete, the Architect will prepare a Certificate of Substantial Completion that shall establish the date of Substantial Completion; establish responsibilities of the Owner and Contractor for security, maintenance, heat, utilities, damage to the Work and insurance; and fix the time within which the Contractor shall finish all items on the list accompanying the Certificate. Warranties required by the Contract Documents shall commence on the date of Substantial Completion of the Work or designated portion thereof unless otherwise provided in the Certificate of Substantial Completion. § 9.8.5 The Certificate of Substantial Completion shall be submitted to the Owner and Contractor for their written acceptance of responsibilities assigned to them in the Certificate. Upon such acceptance, and consent of surety if any, the Owner shall make payment of retainage applying to the Work or designated portion thereof. Such payment shall be adjusted for Work that is incomplete or not in accordance with the requirements of the Contract Documents. § 9.9 Partial Occupancy or Use § 9.9.1 The Owner may occupy or use any completed or partially completed portion of the Work at any stage when such portion is designated by separate agreement with the Contractor, provided such occupancy or use is consented to by the insurer and authorized by public authorities having jurisdiction over the Project. Such partial occupancy or use may commence whether or not the portion is substantially complete, provided the Owner and Contractor have accepted in writing the responsibilities assigned to each of them for payments, retainage, if any, security, maintenance, heat, utilities, damage to the Work and insurance, and have agreed in writing concerning the period for correction of the Work and commencement of warranties required by the Contract Documents. When the Contractor considers a portion substantially complete, the Contractor shall prepare and submit a list to the Architect as provided under Section 9.8.2. Consent of the Contractor to partial occupancy or use shall not be unreasonably withheld. The stage of the progress of the Work shall be determined by written agreement between the Owner and Contractor or, if no agreement is reached, by decision of the Architect. § 9.9.2 Immediately prior to such partial occupancy or use, the Owner, Contractor, and Architect shall jointly review the area to be occupied or portion of the Work to be used in order to determine and record the condition of the Work. § 9.9.3 Unless otherwise agreed upon, partial occupancy or use of a portion or portions of the Work shall not constitute acceptance of Work not complying with the requirements of the Contract Documents. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 33 § 9.10 Final Completion and Final Payment § 9.10.1 Upon receipt of the Contractor’s notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in general compliance with the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed in Section 9.10.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled. § 9.10.1.1 The Architect will provide no more than one (1) PIC/PM to provide up to two (2) inspections to determine whether the Work or a designated portion thereof has attained final completion in accordance with the Contract Documents. The Owner shall deduct from the Contract Sum amounts paid to the Architect for any additional inspections. § 9.10.2 Neither final payment nor any remaining retained percentage shall become due until the Contractor submits to the Architect for the record (1) an affidavit that payrolls, bills for materials and equipment, and other indebtedness connected with the Work for which the Owner or the Owner’s property might be responsible or encumbered (less amounts withheld by Owner) have been paid or otherwise satisfied, (2) a certificate evidencing that insurance required by the Contract Documents to remain in force after final payment is currently in effect, (3) a written statement that the Contractor knows of no reason that the insurance will not be renewable to cover the period required by the Contract Documents, (4) consent of surety, if any, to final payment, (5) documentation of any special warranties, such as manufacturers’ warranties or specific Subcontractor warranties, and (6) if required by the Owner, other data establishing payment or satisfaction of obligations, such as receipts and releases and waivers of liens, claims, security interests, or encumbrances arising out of the Contract, to the extent and in such form as may be designated by the Owner. If a Subcontractor refuses to furnish a release or waiver required by the Owner, the Contractor may furnish a bond satisfactory to the Owner to indemnify the Owner against such lien, claim, security interest, or encumbrance. If a lien, claim, security interest, or encumbrance remains unsatisfied after payments are made, the Contractor shall refund to the Owner all money that the Owner may be compelled to pay in discharging the lien, claim, security interest, or encumbrance, including all costs and reasonable attorneys’ fees. § 9.10.3 If, after Substantial Completion of the Work, final completion thereof is materially delayed through no fault of the Contractor or by issuance of Change Orders affecting final completion, and the Architect so confirms, the Owner shall, upon application by the Contractor and certification by the Architect, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed, corrected, and accepted. If the remaining balance for Work not fully completed or corrected is less than retainage stipulated in the Contract Documents, and if bonds have been furnished, the written consent of the surety to payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by the Contractor to the Architect prior to certification of such payment. Such payment shall be made under terms and conditions governing final payment, except that it shall not constitute a waiver of Claims. § 9.10.4 The making of final payment shall constitute a waiver of Claims by the Owner except those arising from .1 liens, Claims, security interests, or encumbrances arising out of the Contract and unsettled; .2 failure of the Work to comply with the requirements of the Contract Documents; .3 terms of special warranties required by the Contract Documents; or .4 audits performed by the Owner, if permitted by the Contract Documents, after final payment. § 9.10.5 Acceptance of final payment by the Contractor, a Subcontractor, or a supplier, shall constitute a waiver of claims by that payee except those previously made in writing and identified by that payee as unsettled at the time of final Application for Payment. § 9.11 LIQUIDATED DAMAGES § 9.11.1 The Contractor, and the Contractor’s surety shall be liable for and shall pay the Owner the sums stipulated on the Bid Form, if any, as liquidated damages for each calendar day of delay after the date established for Substantial Completion in the Contract Documents until the Work is substantially complete. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 34 § 9.11.2 The Owner has established this amount as the proper measure of liquidated damages which the Owner will sustain per day by the failure of the Contractor to substantially complete the Work at the stipulated time and it is not to be construed in any sense as a penalty. § 9.11.3 In addition to Liquidated Damages, the Contractor shall pay to the Owner the cost of extended architectural and engineering (including Architect’s on-site representative(s), if any, on-site) services rendered beginning at 31 days from the date of Substantial Completion required by the Contract, as adjusted if applicable, and continuously until final completion is achieved. ARTICLE 10 PROTECTION OF PERSONS AND PROPERTY § 10.1 Safety Precautions and Programs The Contractor shall be responsible for initiating, maintaining, and supervising all safety precautions and programs in connection with the performance of the Contract. § 10.2 Safety of Persons and Property § 10.2.1 The Contractor shall take reasonable precautions for safety of, and shall provide reasonable protection to prevent damage, injury, or loss to .1 employees on the Work and other persons who may be affected thereby; .2 the Work and materials and equipment to be incorporated therein, whether in storage on or off the site, under care, custody, or control of the Contractor, a Subcontractor, or a Sub-subcontractor; and .3 other property at the site or adjacent thereto, such as trees, shrubs, lawns, walks, pavements, roadways, structures, and utilities not designated for removal, relocation, or replacement in the course of construction. § 10.2.2 The Contractor shall comply with, and give notices required by applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities, bearing on safety of persons or property or their protection from damage, injury, or loss. § 10.2.3 The Contractor shall implement, erect, and maintain, as required by existing conditions and performance of the Contract, reasonable safeguards for safety and protection, including posting danger signs and other warnings against hazards; promulgating safety regulations; and notifying the owners and users of adjacent sites and utilities of the safeguards. § 10.2.4 When use or storage of explosives or other hazardous materials or equipment, or unusual methods are necessary for execution of the Work, the Contractor shall exercise utmost care and carry on such activities under supervision of properly qualified personnel. § 10.2.5 The Contractor shall promptly remedy damage and loss (other than damage or loss insured under property insurance required by the Contract Documents) to property referred to in Sections 10.2.1.2 and 10.2.1.3 caused in whole or in part by the Contractor, a Subcontractor, a Sub-subcontractor, or anyone directly or indirectly employed by any of them, or by anyone for whose acts they may be liable and for which the Contractor is responsible under Sections 10.2.1.2 and 10.2.1.3. The Contractor may make a Claim for the cost to remedy the damage or loss to the extent such damage or loss is attributable to acts or omissions of the Owner or Architect or anyone directly or indirectly employed by either of them, or by anyone for whose acts either of them may be liable, and not attributable to the fault or negligence of the Contractor. The foregoing obligations of the Contractor are in addition to the Contractor’s obligations under Section 3.18. § 10.2.6 The Contractor shall designate a responsible member of the Contractor’s organization at the site whose duty shall be the prevention of accidents. This person shall be the Contractor’s superintendent unless otherwise designated by the Contractor in writing to the Owner. § 10.2.7 The Contractor shall not permit any part of the construction or site to be loaded so as to cause damage or create an unsafe condition. § 10.2.8 Injury or Damage to Person or Property If either party suffers injury or damage to person or property because of an act or omission of the other party, or of others for whose acts such party is legally responsible, notice of the injury or damage, whether or not insured, shall AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 35 be given to the other party within a reasonable time not exceeding 21 days after discovery. The notice shall provide sufficient detail to enable the other party to investigate the matter. § 10.3 Hazardous Materials and Substances § 10.3.1 The Contractor is responsible for compliance with any requirements included in the Contract Documents regarding hazardous materials or substances. If the Contractor encounters a hazardous material or substance not addressed in the Contract Documents and if reasonable precautions will be inadequate to prevent foreseeable bodily injury or death to persons resulting from a material or substance, including but not limited to asbestos or polychlorinated biphenyl (PCB), encountered on the site by the Contractor, the Contractor shall, upon recognizing the condition, immediately stop Work in the affected area and notify the Owner and Architect of the condition. § 10.3.2 Upon receipt of the Contractor’s notice, the Owner may obtain the services of a licensed laboratory to verify the presence or absence of the material or substance reported by the Contractor and, in the event such material or substance is found to be present, to cause it to be rendered harmless. Unless otherwise required by the Contract Documents, the Owner shall furnish in writing to the Contractor the names and qualifications of persons or entities who are to perform tests verifying the presence or absence of the material or substance or who are to perform the task of removal or safe containment of the material or substance. The Contractor will promptly reply to the Owner in writing stating whether or not either has reasonable objection to the persons or entities proposed by the Owner. If the Contractor has an objection to a person or entity proposed by the Owner, the Owner shall propose another to whom the Contractor hasno reasonable objection. When the material or substance has been rendered harmless, Work in the affected area shall resume upon written agreement of the Owner and Contractor. By Change Order, the Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Contractor’s reasonable additional costs of shutdown, delay, and start-up. § 10.3.4 The Owner shall not be responsible under this Section 10.3 for hazardous materials or substances the Contractor brings to the site unless such materials or substances are required by the Contract Documents. The Owner shall be responsible for hazardous materials or substances required by the Contract Documents, except to the extent of the Contractor’s fault or negligence in the use and handling of such materials or substances. § 10.3.5 The Contractor shall reimburse the Owner for the cost and expense the Owner incurs (1) for remediation of hazardous materials or substances the Contractor brings to the site and negligently handles, or (2) where the Contractor fails to perform its obligations under Section 10.3.1, except to the extent that the cost and expense are due to the Owner’s fault or negligence. § 10.3.6 If, without negligence on the part of the Contractor, the Contractor is held liable by a government agency for the cost of remediation of a hazardous material or substance solely by reason of performing Work as required by the Contract Documents, the Owner shall reimburse the Contractor for all cost and expense thereby incurred. § 10.4 Emergencies In an emergency affecting safety of persons or property, the Contractor shall act, at the Contractor’s discretion, to prevent threatened damage, injury, or loss. Additional compensation or extension of time claimed by the Contractor on account of an emergency shall be determined as provided in Article 15 and Article 7. ARTICLE 11 INSURANCE AND BONDS § 11.1 Contractor’s Insurance and Bonds § 11.1.1 The Contractor shall purchase and maintain insurance of the types and limits of liability, containing the endorsements, and subject to the terms and conditions, as described in the Agreement or elsewhere in the Contract Documents. The Contractor shall purchase and maintain the required insurance from an insurance company or insurance companies lawfully authorized to issue insurance in the jurisdiction where the Project is located. The Owner, Architect, and Architect’s consultants shall be named as additional insureds under the Contractor’s commercial general liability policy or as otherwise described in the Contract Documents. § 11.1.2 The Contractor shall provide surety bonds of the types, for such penal sums, and subject to such terms and conditions as required by the Contract Documents. The Contractor shall purchase and maintain the required bonds from a company or companies lawfully authorized to issue surety bonds in the jurisdiction where the Project is located. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 36 § 11.1.3 Upon the request of any person or entity appearing to be a potential beneficiary of bonds covering payment of obligations arising under the Contract, the Contractor shall promptly furnish a copy of the bonds or shall authorize a copy to be furnished. § 11.1.4 Notice of Cancellation or Expiration of Contractor’s Required Insurance. Within three (3) working days of the date the Contractor becomes aware of an impending or actual cancellation or expiration of any insurance required by the Contract Documents, the Contractor shall provide notice to the Owner of such impending or actual cancellation or expiration. Upon receipt of notice from the Contractor, the Owner shall, unless the lapse in coverage arises from an act or omission of the Owner, have the right to stop the Work until the lapse in coverage has been cured by the procurement of replacement coverage by the Contractor. The furnishing of notice by the Contractor shall not relieve the Contractor of any contractual obligation to provide any required coverage. § 11.2 Owner’s Insurance § 11.2.1 The Owner shall purchase and maintain insurance of the types and limits of liability, containing the endorsements, and subject to the terms and conditions, as described in the Agreement or elsewhere in the Contract Documents. The Owner shall purchase and maintain the required insurance from an insurance company or insurance companies lawfully authorized to issue insurance in the jurisdiction where the Project is located. § 11.2.2 Property Insurance. The Contractor shall purchase and maintain, in a company or companies lawfully authorized to do business in the jurisdiction in which the Project is located, property insurance written on a builder’s risk “all-risk” or equivalent policy form in the amount of the initial Contract Sum as well as subsequent Contract modifications thereto for the entire Work at the site on a replacement cost basis without optional deductibles. Such property insurance shall be maintained, unless otherwise agreed in writing by all persons and entities who are beneficiaries of such insurance, until final payment has been made as provided in Section 9.10 or until no person or entity other than the Owner has an insurable interest in the property required by this Section 11.3 to be covered, whichever is later. This insurance shall include interests of the Owner, the Contractor, Subcontractors and Sub- subcontractors in the Project. § 11.2.3 Property insurance shall be on an “all-risk” or equivalent policy form and shall insure against the perils of fire and extended coverage and physical loss or damage including, without duplication of coverage, theft, vandalism, malicious mischief, collapse, collapse, earthquake, flood, windstorm, false work, testing and startup, temporary buildings, and debris removal, including demolition occasioned by enforcement of any applicable legal requirements, and shall cover reasonable compensation for Architect's services and expenses required as a result of such insured loss. Coverage for other perils shall not be required unless otherwise provided in the Contract Documents. § 11.2.4 If the property insurance requires minimum deductibles and such deductibles are identified in the Contract Documents, the Contractor shall pay costs not covered because of such deductibles. § 11.2.5 This property insurance shall cover portions of the Work stored off the site, and also portions of the Work in transit. § 11.2.6 Partial occupancy or use in accordance with Section 9.9 shall not commence until the insurance company or companies providing property insurance have consented to such partial occupancy or use by endorsement or otherwise. The Owner and the Contractor shall take reasonable steps to obtain consent of the insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse, or reduction of insurance. § 11.3 Waivers of Subrogation § 11.3.1 The Owner and Contractor waive all rights against (1) each other and any of their subcontractors, sub- subcontractors, agents, and employees, each of the other; (2) the Architect and Architect’s consultants; and (3) Separate Contractors, if any, and any of their subcontractors, sub-subcontractors, agents, and employees, for damages caused by fire, or other causes of loss, to the extent those losses are covered by property insurance required by the Agreement or other property insurance applicable to the Project, except such rights as they have to proceeds AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 37 of such insurance. The Owner or Contractor, as appropriate, shall require similar written waivers in favor of the individuals and entities identified above from the Architect, Architect’s consultants, Separate Contractors, subcontractors, and sub-subcontractors. The policies of insurance purchased and maintained by each person or entity agreeing to waive claims pursuant to this section 11.3.1 shall not prohibit this waiver of subrogation. This waiver of subrogation shall be effective as to a person or entity (1) even though that person or entity would otherwise have a duty of indemnification, contractual or otherwise, (2) even though that person or entity did not pay the insurance premium directly or indirectly, or (3) whether or not the person or entity had an insurable interest in the damaged property. § 11.3.2 If during the Project construction period the Owner insures properties, real or personal or both, at or adjacent to the site by property insurance under policies separate from those insuring the Project, or if after final payment property insurance is to be provided on the completed Project through a policy or policies other than those insuring the Project during the construction period, to the extent permissible by such policies, the Owner waives all rights in accordance with the terms of Section 11.3.1 for damages caused by fire or other causes of loss covered by this separate property insurance. § 11.4 Loss of Use, Business Interruption, and Delay in Completion Insurance The Owner, at the Owner’s option, may purchase and maintain insurance that will protect the Owner against loss of use of the Owner’s property, or the inability to conduct normal operations, due to fire or other causes of loss. The Owner waives all rights of action against the Contractor and Architect for loss of use of the Owner’s property, due to fire or other hazards however caused. §11.5 Adjustment and Settlement of Insured Loss § 11.5.1 A loss insured under the property insurance required by the Agreement shall be adjusted by the Owner as fiduciary and made payable to the Owner as fiduciary for the insureds, as their interests may appear, subject to requirements of any applicable mortgagee clause and of Section 11.5.2. The Owner shall pay the Architect and Contractor their just shares of insurance proceeds received by the Owner, and by appropriate agreements the Architect and Contractor shall make payments to their consultants and Subcontractors in similar manner. § 11.5.2 Prior to settlement of an insured loss, the Owner shall notify the Contractor of the terms of the proposed settlement as well as the proposed allocation of the insurance proceeds. The Contractor shall have 14 days from receipt of notice to object to the proposed settlement or allocation of the proceeds. If the Contractor does not object, the Owner shall settle the loss and the Contractor shall be bound by the settlement and allocation. Upon receipt, the Owner shall deposit the insurance proceeds in a separate account and make the appropriate distributions. Thereafter, if no other agreement is made or the Owner does not terminate the Contract for convenience, the Owner and Contractor shall execute a Change Order for reconstruction of the damaged or destroyed Work in the amount allocated for that purpose. If the Contractor timely objects to either the terms of the proposed settlement or the allocation of the proceeds, the Owner may proceed to settle the insured loss, and any dispute between the Owner and Contractor arising out of the settlement or allocation of the proceeds shall be resolved pursuant to Article 15. Pending resolution of any dispute, the Owner may issue a Construction Change Directive for the reconstruction of the damaged or destroyed Work. ARTICLE 12 UNCOVERING AND CORRECTION OF WORK § 12.1 Uncovering of Work § 12.1.1 If a portion of the Work is covered contrary to the Architect’s request or to requirements specifically expressed in the Contract Documents, it must, if requested in writing by the Architect, be uncovered for the Architect’s review and be replaced at the Contractor’s expense without change in the Contract Time. § 12.1.2 If a portion of the Work has been covered that the Architect has not specifically requested to review prior to its being covered, the Architect may request to see such Work and it shall be uncovered by the Contractor. If such Work is in accordance with the Contract Documents, the Contractor shall be entitled to an equitable adjustment to the Contract Sum and Contract Time as may be appropriate. If such Work is not in accordance with the Contract Documents, the costs of uncovering the Work, and the cost of correction, shall be at the Contractor’s expense without change to the contract time. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 38 § 12.2 Correction of Work § 12.2.1 Before Substantial Completion The Contractor shall promptly correct Work rejected by the Architect or Owner or failing to conform to the requirements of the Contract Documents, discovered before Substantial Completion and whether or not fabricated, installed or completed. Costs of correcting such rejected Work, including additional testing and inspections, the cost of uncovering and replacement, and compensation for the Architect’s services and expenses made necessary thereby, shall be at the Contractor’s expense without change to the contract time. § 12.2.2 After Substantial Completion § 12.2.2.1 In addition to the Contractor’s obligations under Section 3.5, if, within one year after the date of Substantial Completion of the Work or designated portion thereof or after the date for commencement of warranties established under Section 9.9.1, or by terms of any applicable special warranty required by the Contract Documents, any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor shall correct it promptly after receipt of notice from the Owner to do so, unless the Owner has previously given the Contractor a written acceptance of such condition. The Owner shall give such notice promptly after discovery of the condition. During the one-year period for correction of Work, if the Owner fails to notify the Contractor and give the Contractor an opportunity to make the correction, the Owner waives the rights to require correction by the Contractor and to make a claim for breach of warranty. If the Contractor fails to correct nonconforming Work within a reasonable time during that period after receipt of notice from the Owner or Architect, the Owner may correct it in accordance with Section 2.5. § 12.2.2.2 The one-year period for correction of Work shall be extended with respect to portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual completion of that portion of the Work. § 12.2.2.3 The one-year period for correction of Work shall not be extended by corrective Work performed by the Contractor pursuant to this Section 12.2. § 12.2.2.4 If required by the Owner and the Architect and, upon request by the Owner and prior to the expiration of one year from the date of Substantial Completion, the Architect will conduct and the Contractor shall attend a meeting with the Owner to review the facility operations and performance and the Work. § 12.2.3 The Contractor shall remove from the site portions of the Work that are not in accordance with the requirements of the Contract Documents and are neither corrected by the Contractor nor accepted by the Owner. § 12.2.4 The Contractor shall bear the cost of correcting destroyed or damaged construction of the Owner or Separate Contractors, whether completed or partially completed, caused by the Contractor’s correction or removal of Work that is not in accordance with the requirements of the Contract Documents. § 12.2.5 Nothing contained in this Section 12.2 shall be construed to establish a period of limitation with respect to other obligations the Contractor has under the Contract Documents. Establishment of the one-year period for correction of Work as described in Section 12.2.2 relates only to the specific obligation of the Contractor to correct the Work, and has no relationship to the time within which the obligation to comply with the Contract Documents may be sought to be enforced, nor to the time within which proceedings may be commenced to establish the Contractor’s liability with respect to the Contractor’s obligations other than specifically to correct the Work. § 12.3 Acceptance of Nonconforming Work If the Owner prefers to accept Work that is not in accordance with the requirements of the Contract Documents, the Owner may do so instead of requiring its removal and correction, in which case the Contract Sum will be reduced as appropriate and equitable. Such adjustment shall be effected whether or not final payment has been made. ARTICLE 13 MISCELLANEOUS PROVISIONS § 13.1 Governing Law The Contract shall be governed by the law of the place where the Project is located. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 39 § 13.2 Successors and Assigns § 13.2.1 The Owner and Contractor respectively bind themselves, their partners, successors, assigns, and legal representatives to covenants, agreements, and obligations contained in the Contract Documents. Except as provided in Section 13.2.2, neither party to the Contract shall assign the Contract as a whole without written consent of the other. If either party attempts to make an assignment without such consent, that party shall nevertheless remain legally responsible for all obligations under the Contract. § 13.2.2 The Owner may, without consent of the Contractor, assign the Contract to a lender providing construction financing for the Project, if the lender assumes the Owner’s rights and obligations under the Contract Documents. The Contractor shall execute all consents reasonably required to facilitate the assignment. § 13.3 Rights and Remedies § 13.3.1 Duties and obligations imposed by the Contract Documents and rights and remedies available thereunder shall be in addition to and not a limitation of duties, obligations, rights, and remedies otherwise imposed or available by law. § 13.3.2 No action or failure to act by the Owner, Architect, or Contractor shall constitute a waiver of a right or duty afforded them under the Contract, nor shall such action or failure to act constitute approval of or acquiescence in a breach thereunder, except as may be specifically agreed upon in writing. § 13.4 Tests and Inspections § 13.4.1 Tests, inspections, and approvals of portions of the Work shall be made as required by the Contract Documents and by applicable laws, statutes, ordinances, codes, rules, and regulations or lawful orders of public authorities. Unless otherwise provided, the Contractor shall make arrangements for such tests, inspections, and approvals with an independent testing laboratory or entity acceptable to the Owner, or with the appropriate public authority, and shall bear all related costs of tests, inspections, and approvals. The Contractor shall give the Architect timely notice of when and where tests and inspections are to be made so that the Architect may be present for such procedures. The Owner shall bear costs of tests, inspections, or approvals that do not become requirements until after bids are received or negotiations concluded. § 13.4.2 If the Architect, Owner, or public authorities having jurisdiction determine that portions of the Work require additional testing, inspection, or approval not included under Section 13.4.1, the Architect will, upon written authorization from the Owner, instruct the Contractor to make arrangements for such additional testing, inspection, or approval, by an entity acceptable to the Owner, and the Contractor shall give timely notice to the Architect of when and where tests and inspections are to be made so that the Architect may be present for such procedures. Such costs, except as provided in Section 13.4.3, shall be at the Owner’s expense. § 13.4.3 If procedures for testing, inspection, or approval under Sections 13.4.1 and 13.4.2 reveal failure of the portions of the Work to comply with requirements established by the Contract Documents, all costs made necessary by such failure, including those of repeated procedures and compensation for the Architect’s services and expenses, shall be at the Contractor’s expense without change to contract time. § 13.4.4 Required certificates of testing, inspection, or approval shall, unless otherwise required by the Contract Documents, be secured by the Contractor and submitted to the Architect. § 13.4.5 If the Architect is to observe tests, inspections, or approvals required by the Contract Documents, the Architect will do so in a timely manner and, where practicable, at the normal place of testing. § 13.4.6 Tests or inspections conducted pursuant to the Contract Documents shall be made promptly to avoid unreasonable delay in the Work. § 13.5 Interest Payments due and unpaid under the Contract Documents shall bear interest from the date payment is due at the rate the parties agree upon in writing or, in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 40 ARTICLE 14 TERMINATION OR SUSPENSION OF THE CONTRACT § 14.1 Termination by the Contractor § 14.1.1 The Contractor may terminate the Contract if the Work is stopped for a period of 30 consecutive days through no act or fault of the Contractor, a Subcontractor, a Sub-subcontractor, their agents or employees, or any other persons or entities performing portions of the Work, for any of the following reasons: .1 Issuance of an order of a court or other public authority having jurisdiction that requires all Work to be stopped; .2 An act of government, such as a declaration of national emergency, that requires all Work to be stopped; .3 Because the Architect has not issued a Certificate for Payment and has not notified the Contractor of the reason for withholding certification as provided in Section 9.4.1, or because the Owner has not made payment on a Certificate for Payment within the time stated in the Contract Documents; or .4 The Owner has failed to furnish to the Contractor reasonable evidence as required by Section 2.2. § 14.1.2 The Contractor may terminate the Contract if, through no act or fault of the Contractor, a Subcontractor, a Sub-subcontractor, their agents or employees, or any other persons or entities performing portions of the Work, repeated suspensions, delays, or interruptions of the entire Work by the Owner as described in Section 14.3, constitute in the aggregate more than 100 percent of the total number of days scheduled for completion, or 120 days in any 365-day period, whichever is less. § 14.1.3 If one of the reasons described in Section 14.1.1 or 14.1.2 exists, the Contractor may, upon seven working days’ notice to the Owner and Architect, terminate the Contract and recover from the Owner payment for Work executed, as well as reasonable overhead and profit on Work not executed, and costs incurred by reason of such termination. § 14.1.4 If the Work is stopped for a period of 60 consecutive days through no act or fault of the Contractor, a Subcontractor, a Sub-subcontractor, or their agents or employees or any other persons or entities performing portions of the Work because the Owner has repeatedly failed to fulfill the Owner’s obligations under the Contract Documents with respect to matters important to the progress of the Work, the Contractor may, upon seven working additional days’ notice to the Owner and the Architect, terminate the Contract and recover from the Owner as provided in Section 14.1.3. § 14.2 Termination by the Owner for Cause § 14.2.1 The Owner may terminate the Contract if the Contractor .1 repeatedly refuses or fails to supply enough properly skilled workers or proper materials; .2 fails to make payment to Subcontractors or suppliers in accordance with the respective agreements between the Contractor and the Subcontractors or Suppliers; .3 repeatedly disregards applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of a public authority; or .4 otherwise is guilty of substantial breach of a provision of the Contract Documents. § 14.2.2 When any of the reasons described in Section 14.2.1 exist, and upon determination by the Architect that sufficient cause exists to justify such action, the Owner may, without prejudice to any other rights or remedies of the Owner and after giving the Contractor and the Contractor’s surety, if any, seven days’ notice, terminate employment of the Contractor and may, subject to any prior rights of the surety: .1 Exclude the Contractor from the site and take possession of all materials, equipment, tools, and construction equipment and machinery thereon owned by the Contractor; .2 Accept assignment of subcontracts pursuant to Section 5.4; and .3 Finish the Work by whatever reasonable method the Owner may deem expedient. Upon written request of the Contractor, the Owner shall furnish to the Contractor a detailed accounting of the costs incurred by the Owner in finishing the Work. § 14.2.3 When the Owner terminates the Contract for one of the reasons stated in Section 14.2.1, the Contractor shall not be entitled to receive further payment until the Work is finished. § 14.2.4 If the unpaid balance of the Contract Sum exceeds costs of finishing the Work, including compensation for the Architect’s services and expenses made necessary thereby, and other damages incurred by the Owner and not AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 41 expressly waived, such excess shall be paid to the Contractor. If such costs and damages exceed the unpaid balance, the Contractor shall pay the difference to the Owner. The amount to be paid to the Contractor or Owner, as the case may be, shall be determined by the Initial Decision Maker, upon application, and this obligation for payment shall survive termination of the Contract. § 14.3 Suspension by the Owner for Convenience § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, in whole or in part for such period of time as the Owner may determine. § 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay, or interruption under Section 14.3.1. Adjustment of the Contract Sum shall include profit. No adjustment shall be made to the extent .1 that performance is, was, or would have been, so suspended, delayed, or interrupted, by another cause for which the Contractor is responsible; or .2 that an equitable adjustment is made or denied under another provision of the Contract. § 14.4 Termination by the Owner for Convenience § 14.4.1 The Owner may, at any time, terminate the Contract for the Owner’s convenience and without cause. § 14.4.2 Upon receipt of notice from the Owner of such termination for the Owner’s convenience, the Contractor shall .1 cease operations as directed by the Owner in the notice; .2 take actions necessary, or that the Owner may direct, for the protection and preservation of the Work; and .3 except for Work directed to be performed prior to the effective date of termination stated in the notice, terminate all existing subcontracts and purchase orders and enter into no further subcontracts and purchase orders. § 14.4.3 In case of such termination for the Owner’s convenience, the Owner shall pay the Contractor for Work properly executed; costs incurred by reason of the termination, including costs attributable to termination of Subcontracts; and the termination fee, if any, set forth in the Agreement. ARTICLE 15 CLAIMS AND DISPUTES § 15.1 Claims § 15.1.1 Definition A Claim is a demand or assertion by one of the parties seeking, as a matter of right, payment of money, a change in the Contract Time, or other relief with respect to the terms of the Contract. The term “Claim” also includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract. The responsibility to substantiate Claims shall rest with the party making the Claim. This Section 15.1.1 does not require the Owner to file a Claim in order to impose liquidated damages in accordance with the Contract Documents. § 15.1.2 Time Limits on Claims The Owner and Contractor shall commence all Claims and causes of action against the other and arising out of or related to the Contract, whether in contract, tort, breach of warranty or otherwise, in accordance with the requirements of the binding dispute resolution method selected in the Agreement and within the period specified by applicable law, but in any case not more than 10 years after the date of Substantial Completion of the Work. The Owner and Contractor waive all Claims and causes of action not commenced in accordance with this Section 15.1.2. § 15.1.3 Notice of Claims § 15.1.3.1 Claims by either the Owner or Contractor, where the condition giving rise to the Claim is first discovered prior to expiration of the period for correction of the Work set forth in Section 12.2.2, shall be initiated by notice to the other party and to the Initial Decision Maker with a copy sent to the Architect, if the Architect is not serving as the Initial Decision Maker. Claims by either party under this Section 15.1.3.1 shall be initiated within 21 days after occurrence of the event giving rise to such Claim or within 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 42 § 15.1.3.2 Claims by either the Owner or Contractor, where the condition giving rise to the Claim is first discovered after expiration of the period for correction of the Work set forth in Section 12.2.2, shall be initiated by notice to the other party. In such event, no decision by the Initial Decision Maker is required. § 15.1.4 Continuing Contract Performance § 15.1.4.1 Pending final resolution of a Claim, except as otherwise agreed in writing or as provided in Section 9.7 and Article 14, the Contractor shall proceed diligently with performance of the Contract and the Owner shall continue to make payments in accordance with the Contract Documents. § 15.1.4.2 The Contract Sum, Contract Time, or both shall be adjusted in accordance with the Initial Decision Maker’s decision, subject to the right of either party to proceed in accordance with this Article 15. The Architect will issue Certificates for Payment in accordance with the decision of the Initial Decision Maker. § 15.1.5 Claims for Additional Cost If the Contractor wishes to make a Claim for an increase in the Contract Sum notice as provided in Section 15.1.3 shall be given before proceeding to execute the portion of the Work that is the subject of the Claim. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4. § 15.1.6 Claims for Additional Time § 15.1.6.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, notice as provided in Section 15.1.3 shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. § 15.1.6.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated, and had an adverse effect on the scheduled construction. Time extensions from adverse weather conditions shall not entitle the Contractor to “extended overhead” recovery. § 15.1.6.2.1 Weather data utilized to support claims for adverse weather conditions shall be that obtained from the National Oceanic and Atmospheric Administration (NOAA) for the nearest weather station to the Project. Adverse weather conditions are defined as measurable precipitation (MP) of 0.1 " or more, or 1.0" or more of snow or ice pellets, or freezing temperature (FT) for a day (24 hours) when the temperature remains at 32 degrees Fahrenheit or below. Only measurable precipitation (MP) or freezing temperature (FT) shall be permitted to be claimed for any one calendar day. Time extensions for adverse weather conditions shall be cumulative over the duration of the Project time and claims shall not be permitted for days for drying out of rain-soaked soil, snow accumulation, or similar weather-related conditions or resulting Project conditions. .1 The Contractor agrees that it shall not be entitled to a time extension for normal inclement weather (weather conditions other than “adverse weather conditions”) which could have been expected at the Project locale due to precipitation or temperature, based upon actual data from the National Oceanic and Atmospheric Administration (NOAA) for the locality closest to the Project for a five- year period preceding the date of the Contract. The Contractor acknowledges and warrants that in making its proposal or bid and Construction Schedule for the Work, it gave due care and consideration to this expected number of calendar days of inclement weather for the locale of the Project and allowed for the impact of normal inclement weather on subsequent Work. During the time of performance, should the expected number of calendar days of normal inclement weather for the locale of the Project be less than originally anticipated by the Contractor and the Owner, at the time of contracting, those days not so affected by normal inclement weather shall be considered float time in the Construction Schedule. .2 The Contractor agrees that the measure of adverse weather conditions due to MP or FT during the period covered by this Contract shall be the number of days where adverse weather conditions comply with the weather data referenced in subparagraph 15.1.6.2.1. .3 Extensions of time will be made only for days in which abnormal adverse weather criteria cited in subparagraph 15.1.6.2.1 occur. .4 If the total calendar days lost due to adverse weather conditions, from the start of the Work at the Project by the Contractor until the principal portions of the Work are enclosed, exceeds the total number of days to be expected to be lost for the same time period, a time extension, if granted, AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 43 shall only be for the number of calendar days needed to equal the excess number of calendar days lost to such adverse weather conditions. § 15.1.7 Waiver of Claims for Consequential Damages The Contractor and Owner waive Claims against each other for consequential damages arising out of or relating to this Contract. This mutual waiver includes .1 damages incurred by the Owner for rental expenses, for losses of use, income, profit, financing, business and reputation, and for loss of management or employee productivity or of the services of such persons; and .2 damages incurred by the Contractor for principal office expenses including the compensation of personnel stationed there, for losses of financing, business and reputation, and for loss of profit, except anticipated profit arising directly from the Work. This mutual waiver is applicable, without limitation, to all consequential damages due to either party’s termination in accordance with Article 14. Nothing contained in this Section 15.1.7 shall be deemed to preclude assessment of liquidated damages, when applicable, in accordance with the requirements of the Contract Documents. § 15.2 Initial Decision § 15.2.1 Claims, excluding those where the condition giving rise to the Claim is first discovered after expiration of the period for correction of the Work set forth in Section 12.2.2 or arising under Sections 10.3, 10.4, and 11.5, shall be referred to the Initial Decision Maker for initial decision. The Architect will serve as the Initial Decision Maker, unless otherwise indicated in the Agreement. Except for those Claims excluded by this Section 15.2.1, an initial decision shall be required as a condition precedent to mediation of any Claim. If an initial decision has not been rendered within 30 working days after the Claim has been referred to the Initial Decision Maker, subject to Section 15.2.6 the party asserting the Claim may demand mediation without a decision having been rendered. The Initial Decision Maker will not decide disputes between the Contractor and persons or entities other than the Owner. § 15.2.2 The Initial Decision Maker will review Claims and within ten working days of the receipt of a Claim take one or more of the following actions: (1) request additional supporting data from the claimant or a response with supporting data from the other party, (2) reject the Claim in whole or in part, (3) approve the Claim, (4) suggest a compromise, or (5) advise the parties that the Initial Decision Maker is unable to resolve the Claim if the Initial Decision Maker lacks sufficient information to evaluate the merits of the Claim or if the Initial Decision Maker concludes that, in the Initial Decision Maker’s sole discretion, it would be inappropriate for the Initial Decision Maker to resolve the Claim. § 15.2.3 In evaluating Claims, the Initial Decision Maker may, but shall not be obligated to, consult with or seek information from either party or from persons with special knowledge or expertise who may assist the Initial Decision Maker in rendering a decision. The Initial Decision Maker may request the Owner to authorize retention of such persons at the Owner’s expense. § 15.2.4 If the Initial Decision Maker requests a party to provide a response to a Claim or to furnish additional supporting data, such party shall respond, within ten working days after receipt of the request, and shall either (1) provide a response on the requested supporting data, (2) advise the Initial Decision Maker when the response or supporting data will be furnished, or (3) advise the Initial Decision Maker that no supporting data will be furnished. Upon receipt of the response or supporting data, if any, the Initial Decision Maker will either reject or approve the Claim in whole or in part. § 15.2.5 The Initial Decision Maker will render an initial decision approving or rejecting the Claim, or indicating that the Initial Decision Maker is unable to resolve the Claim. This initial decision shall (1) be in writing; (2) state the reasons therefor; and (3) notify the parties and the Architect, if the Architect is not serving as the Initial Decision Maker, of any change in the Contract Sum or Contract Time or both. The initial decision shall be final and binding on the parties but subject to mediation and, if the parties fail to resolve their dispute through mediation, to binding dispute resolution. § 15.2.6 Either party may file for mediation at any time, subject to the terms of Section 15.2.6.1. AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:54:48 ET on 09/18/2026 under Order No.500072155_2 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1732725571) 44 § 15.2.6.1 Either party may, within 30 working days from the date of receipt of an initial decision, or if no decision has been rendered in accordance with Section 15.2.1, demand in writing that the other party file for mediation. If such a demand is made and the party receiving the demand fails to file for mediation within 30 working days after receipt thereof, then both parties waive their rights to mediate or pursue binding dispute resolution proceedings with respect to the initial decision. § 15.2.7 In the event of a Claim against the Contractor, the Owner may, but is not obligated to, notify the surety, if any, of the nature and amount of the Claim. If the Claim relates to a possibility of a Contractor’s default, the Owner may, but is not obligated to, notify the surety and request the surety’s assistance in resolving the controversy. § 15.2.8 If a Claim relates to or is the subject of a mechanic’s lien, the party asserting such Claim may proceed in accordance with applicable law to comply with the lien notice or filing deadlines. § 15.3 Mediation § 15.3.1 Claims, disputes, or other matters in controversy arising out of or related to the Contract, except those waived as provided for in Sections 9.10.4, 9.10.5, and 15.1.7, shall be subject to mediation as a condition precedent to binding dispute resolution. § 15.3.2 The parties shall endeavor to resolve their Claims by mediation which, unless the parties mutually agree otherwise, shall be administered by the American Arbitration Association in accordance with its Construction Industry Mediation Procedures in effect on the date of the Agreement. A request for mediation shall be made in writing, delivered to the other party to the Contract, and filed with the person or entity administering the mediation. The request may be made concurrently with the filing of binding dispute resolution proceedings but, in such event, mediation shall proceed in advance of binding dispute resolution proceedings, which shall be stayed pending mediation for a period of 60 working days from the date of filing, unless stayed for a longer period by agreement of the parties or court order. § 15.3.3 Either party may, within 30 working days from the date that mediation has been concluded without resolution of the dispute or 60 working days after mediation has been demanded without resolution of the dispute, demand in writing that the other party file for binding dispute resolution. If such a demand is made and the party receiving the demand fails to file for binding dispute resolution within 60 working days after written receipt thereof, then both parties waive their rights to binding dispute resolution proceedings with respect to the initial decision. § 15.3.4 The parties shall share the mediator’s fee and any filing fees equally. The mediation shall be held in the place where the Project is located, unless another location is mutually agreed upon. Agreements reached in mediation shall be enforceable as settlement agreements in any court having jurisdiction thereof. Montgomery County Part IV – Contract Forms Fire & EMS Headquarters Page 91 of 286 Part IV – Contract Forms Montgomery County Notice of Award Fire & EMS Headquarters Page 92 of 286 Notice of Award (Sample) To: Contractor TBD Project Description: Montgomery County Fire & EMS Headquarters Christiansburg, Virginia 24073 The OWNER has considered the BID you submitted, for the project described above, in response to its Advertisement for Bids and Instructions to Bidders. You are hereby notified that your BID has been accepted for the work in the amount of $____________________, which includes the base bid and alternate 1, option A, B, or C and alternate 2. You are required by the Instructions to Bidders to execute the Agreement and furnish the required Contractor’s Performance BOND, Payment BOND, and Certificates of Insurance within ten (10) calendar days from the date of this Notice of Award. If you fail to execute the Agreement and to furnish Bonds and Insurance within ten (10) calendar days from the date of this Notice, the Owner will be entitled to consider all your rights arising from the Owner’s acceptance of your BID as abandoned and as a forfeiture of your BID BOND. The Owner will be entitled to such other rights as may be granted by law. You are required to return an acknowledged copy of this NOTICE OF AWARD to the Owner. Dated this _____________ day of _________________, 2026. Montgomery County Virginia Government By:______________________________ Title:_____________________________ ACCEPTANCE OF NOTICE Receipt of the above NOTICE OF AWARD is hereby acknowledged by (Name of Contractor) this the ____________ day of ______________, 2026 By:______________________________ Title:_____________________________ AIA ® Document A101® – 2017 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:34:56 ET on 09/18/2026 under Order No.500072155_1 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1163350597) 1 ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification. The parties should complete A101®–2017, Exhibit A, Insurance and Bonds, contemporaneously with this Agreement. AIA Document A201®–2017, General Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified. ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document. AGREEMENT made as of the « » day of « » in the year « » (In words, indicate day, month and year.) BETWEEN the Owner: (Name, legal status, address and other information) « Montgomery County, Virginia »« » « 755 Roanoke Street » « Suite 2E » « Christiansburg, Virginia 24073 » and the Contractor: (Name, legal status, address and other information) « To Be Determined »« » « » « » « » for the following Project: (Name, location and detailed description) « Montgomery County Fire & EMS Headquarters » « Christiansburg, Virginia » « » The Architect: (Name, legal status, address and other information) « Local Studio Architecture and Design PLLC »« » « 336 North Washington Avenue » « Pulaski, Virginia 24301 » « » The Owner and Contractor agree as follows. AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:34:56 ET on 09/18/2026 under Order No.500072155_1 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1163350597) 2 TABLE OF ARTICLES 1 THE CONTRACT DOCUMENTS 2 THE WORK OF THIS CONTRACT 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION 4 CONTRACT SUM 5 PAYMENTS 6 DISPUTE RESOLUTION 7 TERMINATION OR SUSPENSION 8 MISCELLANEOUS PROVISIONS 9 ENUMERATION OF CONTRACT DOCUMENTS EXHIBIT A INSURANCE AND BONDS ARTICLE 1 THE CONTRACT DOCUMENTS The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary, and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9. ARTICLE 2 THE WORK OF THIS CONTRACT The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others. ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: (Check one of the following boxes.) [ « » ] The date of this Agreement. [ « » ] A date set forth in a notice to proceed issued by the Owner. [ « » ] Established as follows: (Insert a date or a means to determine the date of commencement of the Work.) « » If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this Agreement. § 3.2 The Contract Time shall be measured from the date of commencement of the Work. § 3.3 Substantial Completion § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work: (Check one of the following boxes and complete the necessary information.) AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:34:56 ET on 09/18/2026 under Order No.500072155_1 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1163350597) 3 [ « » ] Not later than « » ( « » ) calendar days from the date of commencement of the Work. [ « » ] By the following date: « » § 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date § 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5. ARTICLE 4 CONTRACT SUM § 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract. The Contract Sum shall be « » ($ « » ), subject to additions and deductions as provided in the Contract Documents. § 4.2 Alternates § 4.2.1 Alternates, if any, included in the Contract Sum: Item Price § 4.2.2 Subject to the conditions noted below, the following alternates may be accepted by the Owner following execution of this Agreement. Upon acceptance, the Owner shall issue a Modification to this Agreement. (Insert below each alternate and the conditions that must be met for the Owner to accept the alternate.) Item Price Conditions for Acceptance § 4.3 Allowances, if any, included in the Contract Sum: (Identify each allowance.) Item Price § 4.4 Unit prices, if any: (Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.) Item Units and Limitations Price per Unit ($0.00) § 4.5 Liquidated damages, if any: (Insert terms and conditions for liquidated damages, if any.) « » § 4.6 Other: (Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum.) « » AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:34:56 ET on 09/18/2026 under Order No.500072155_1 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1163350597) 4 ARTICLE 5 PAYMENTS § 5.1 Progress Payments § 5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents. § 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows: « » § 5.1.3 Provided that an Application for Payment is received by the Architect not later than the « » day of a month, the Owner shall make payment of the amount certified to the Contractor not later than the « » day of the « » month. If an Application for Payment is received by the Architect after the application date fixed above, payment of the amount certified shall be made by the Owner not later than « » ( « » ) days after the Architect receives the Application for Payment. (Federal, state or local laws may require payment within a certain period of time.) § 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of values shall be prepared in such form, and supported by such data to substantiate its accuracy, as the Architect may require. This schedule of values shall be used as a basis for reviewing the Contractor’s Applications for Payment. § 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment. § 5.1.6 In accordance with AIA Document A201™–2017, General Conditions of the Contract for Construction, and subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows: § 5.1.6.1 The amount of each progress payment shall first include: .1 That portion of the Contract Sum properly allocable to completed Work; .2 That portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction, or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing; and .3 That portion of Construction Change Directives that the Architect determines, in the Architect’s professional judgment, to be reasonably justified. § 5.1.6.2 The amount of each progress payment shall then be reduced by: .1 The aggregate of any amounts previously paid by the Owner; .2 The amount, if any, for Work that remains uncorrected and for which the Architect has previously withheld a Certificate for Payment as provided in Article 9 of AIA Document A201–2017; .3 Any amount for which the Contractor does not intend to pay a Subcontractor or material supplier, unless the Work has been performed by others the Contractor intends to pay; .4 For Work performed or defects discovered since the last payment application, any amount for which the Architect may withhold payment, or nullify a Certificate of Payment in whole or in part, as provided in Article 9 of AIA Document A201–2017; and .5 Retainage withheld pursuant to Section 5.1.7. § 5.1.7 Retainage § 5.1.7.1 For each progress payment made prior to Substantial Completion of the Work, the Owner may withhold the following amount, as retainage, from the payment otherwise due: 5% (Insert a percentage or amount to be withheld as retainage from each Application for Payment. The amount of retainage may be limited by governing law.) AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:34:56 ET on 09/18/2026 under Order No.500072155_1 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1163350597) 5 « » § 5.1.7.1.1 The following items are not subject to retainage: (Insert any items not subject to the withholding of retainage, such as general conditions, insurance, etc.) « » § 5.1.7.2 Reduction or limitation of retainage, if any, shall be as follows: (If the retainage established in Section 5.1.7.1 is to be modified prior to Substantial Completion of the entire Work, including modifications for Substantial Completion of portions of the Work as provided in Section 3.3.2, insert provisions for such modifications.) « » § 5.1.7.3 Except as set forth in this Section 5.1.7.3, upon Substantial Completion of the Work, the Contractor may submit an Application for Payment that includes the retainage withheld from prior Applications for Payment pursuant to this Section 5.1.7. The Application for Payment submitted at Substantial Completion shall not include retainage as follows: (Insert any other conditions for release of retainage upon Substantial Completion.) « » § 5.1.8 If final completion of the Work is materially delayed through no fault of the Contractor, the Owner shall pay the Contractor any additional amounts in accordance with Article 9 of AIA Document A201–2017. § 5.1.9 Except with the Owner’s prior approval, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site. § 5.2 Final Payment § 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Contractor when .1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct Work as provided in Article 12 of AIA Document A201–2017, and to satisfy other requirements, if any, which extend beyond final payment; and .2 a final Certificate for Payment has been issued by the Architect. § 5.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 days after the issuance of the Architect’s final Certificate for Payment, or as follows: « » § 5.3 Interest Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located. (Insert rate of interest agreed upon, if any.) « » % « » ARTICLE 6 DISPUTE RESOLUTION § 6.1 Initial Decision Maker The Architect will serve as the Initial Decision Maker pursuant to Article 15 of AIA Document A201–2017, unless the parties appoint below another individual, not a party to this Agreement, to serve as the Initial Decision Maker. (If the parties mutually agree, insert the name, address and other contact information of the Initial Decision Maker, if other than the Architect.) « » AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:34:56 ET on 09/18/2026 under Order No.500072155_1 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1163350597) 6 « » « » « » § 6.2 Binding Dispute Resolution For any Claim subject to, but not resolved by, mediation pursuant to Article 15 of AIA Document A201–2017, the method of binding dispute resolution shall be as follows: (Check the appropriate box.) [ « » ] Arbitration pursuant to Section 15.4 of AIA Document A201–2017 [ « X » ] Litigation in a court of competent jurisdiction [ « » ] Other (Specify) « » If the Owner and Contractor do not select a method of binding dispute resolution, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be resolved by litigation in a court of competent jurisdiction. ARTICLE 7 TERMINATION OR SUSPENSION § 7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201–2017. § 7.1.1 If the Contract is terminated for the Owner’s convenience in accordance with Article 14 of AIA Document A201–2017, then the Owner shall pay the Contractor a termination fee as follows: (Insert the amount of, or method for determining, the fee, if any, payable to the Contractor following a termination for the Owner’s convenience.) « » § 7.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201–2017. ARTICLE 8 MISCELLANEOUS PROVISIONS § 8.1 Where reference is made in this Agreement to a provision of AIA Document A201–2017 or another Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents. § 8.2 The Owner’s representative: (Name, address, email address, and other information) « » « » « » « » « » « » § 8.3 The Contractor’s representative: (Name, address, email address, and other information) « » « » « » « » « » AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:34:56 ET on 09/18/2026 under Order No.500072155_1 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1163350597) 7 « » § 8.4 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days’ prior notice to the other party. § 8.5 Insurance and Bonds § 8.5.1 The Owner and the Contractor shall purchase and maintain insurance as set forth in AIA Document A101™– 2017, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum, Exhibit A, Insurance and Bonds, and elsewhere in the Contract Documents. § 8.5.2 The Contractor shall provide bonds as set forth in AIA Document A101™–2017 Exhibit A, and elsewhere in the Contract Documents. § 8.6 Notice in electronic format, pursuant to Article 1 of AIA Document A201–2017, may be given in accordance with AIA Document E203™-2013, Building Information Modeling and Digital Data Exhibit, if completed, or as otherwise set forth below: (If other than in accordance withAIA Document E203-2013 insert requirements for delivering notice in electronic format such as name, title, and email address of the recipient and whether and how the system will be required to generate a read receipt for the transmission.) « » § 8.7 Other provisions: « » ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS § 9.1 This Agreement is comprised of the following documents: .1 AIA Document A101™–2017, Standard Form of Agreement Between Owner and Contractor .2 AIA Document A101™–2017, Exhibit A, Insurance and Bonds .3 AIA Document A201™–2017, General Conditions of the Contract for Construction .4 AIA Document E203™-2013, Building Information Modeling and Digital Data Exhibit, dated as indicated below: (Insert the date of E203-2013 incorporated into this Agreement.) « » .5 Drawings Number Title Date .6 Specifications Section Title Date Pages .7 Addenda, if any: Number Date Pages Portions of Addenda relating to bidding or proposal requirements are not part of the Contract Documents unless the bidding or proposal requirements are also enumerated in this Article 9. .8 Other Exhibits: AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:34:56 ET on 09/18/2026 under Order No.500072155_1 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (1163350597) 8 (Check all boxes that apply and include appropriate information identifying the exhibit where required.) [ « » ] AIA Document E204™–2017, Sustainable Projects Exhibit, dated as indicated below: (Insert the date of the E204-2017 incorporated into this Agreement.) « » [ « » ] The Sustainability Plan: Title Date Pages [ « » ] Supplementary and other Conditions of the Contract: Document Title Date Pages .9 Other documents, if any, listed below: (List here any additional documents that are intended to form part of the Contract Documents. AIA Document A201™–2017 provides that the advertisement or invitation to bid, Instructions to Bidders, sample forms, the Contractor’s bid or proposal, portions of Addenda relating to bidding or proposal requirements, and other information furnished by the Owner in anticipation of receiving bids or proposals, are not part of the Contract Documents unless enumerated in this Agreement. Any such documents should be listed here only if intended to be part of the Contract Documents.) « Performance and Payment Bonds Contractor’s Bid dated XXXXXX » This Agreement entered into as of the day and year first written above. OWNER (Signature) CONTRACTOR (Signature) « »« » « »« » (Printed name and title) (Printed name and title) Montgomery County Exhibit A – Insurance and Bond Requirements Fire & EMS Headquarters Page 101 of 286 Exhibit A – Insurance and Bond Requirements ARTICLE 1 – CONTRACTOR’S INSURANCE & BONDS 1.01 General A. Contractor shall provide and maintain insurance and bond coverages per the requirements herein, and in accordance with requirements of Article 11 of AIA Document A201. In the event of overlap or conflict, the A201 shall govern. B. The Contractor shall provide a summary of insurance coverages on an ACORD 25 Certificate of Insurance (COI) or other industry standard form of certificate. C. Form of Bond for Payment and Performance Bonds: Document AIA A312; sample form of bond is included in the Bidding and Procurement documents. D. All insurance and bond coverage shall be provided through a company or companies with an “A” or better rating and licensed in the state where the Project is located. E. All General Liability, Automobile, and Umbrella insurance shall designate the Owner, Architect, and Architect’s consultants as additional insureds. F. General Liability shall not exclude explosion (X), collapse (C), or underground (U) coverages. G. Automobile Liability shall include coverage for Owned, Non-Owned, and Hired autos. H. The Contractor shall maintain Complete Operations coverage for two (2) years from the date of Substantial Completion. 1.02 Insurance Coverage Limits A. The Contractor shall provide the following minimum coverages: 1. Comprehensive General Liability: a. $1,000,000 – Each Occurrence b. $500,000 – Damage to Rented Premises c. $10,000 – Medical Expense (Any One Person) d. $1,000,000 – Personal and Advertising Injury e. $2,000,000 – General Aggregate f. $2,000,000 – Products and Completed Operations Aggregate Limit g. $100,000 – Fire Damage 2. Comprehensive Business Automobile Liability a. $1,000,000 – Each Occurrence 3. Worker’s Compensation: Per statutory limits of the state where the project is located 4. Employer Liability for Participants not covered by Worker’s Compensation a. $100,000 – Employer Liability – Each Accident b. $100,000 – Employer Liability – Disease – Each Employee c. $500,000 – Employer Liability – Disease – Policy Limit 5. Umbrella Coverage a. $1,000,000 – Each Occurrence b. $5,000,000 – Aggregate 6. Builder’s Risk: Montgomery County Exhibit A – Insurance and Bond Requirements Fire & EMS Headquarters Page 102 of 286 a. New Construction and Additions: The Contractor shall insure 100% of the original Contract amount. 7. Pollution a. $1,000,000 – Each Occurrence b. $2,000,000 – Aggregate 1.03 Bonds A. The Contractor shall provide the following: 1. Performance Bond: 100 percent of the Contract Sum. 2. Payment Bond: 100 percent of the Contract Sum. END OF EXHIBIT A – INSURANCE AND BOND REQUIREMENTS AIA ® Document A312® – 2010 Performance Bond AIA Document A312 – 2010 Performance Bond. Copyright © 2010. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 16:09:50 ET on 09/28/2026 under Order No.500072155_5 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (3B9ADA71) 1 ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification. Any singular reference to Contractor, Surety, Owner or other party shall be considered plural where applicable. ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document. CONTRACTOR: (Name, legal status and address) SURETY: (Name, legal status and principal place of business) « »« » « » « »« » « » OWNER: (Name, legal status and address) «Montgomery County, Virginia»« » «755 Roanoke Street Suite 2E Christiansburg, Virginia 24073» CONSTRUCTION CONTRACT Date: « » Amount: $ «0.00» Description: (Name and location) «Montgomery County Fire & EMS Headquarters» «Christiansburg, Virginia» BOND Date: (Not earlier than Construction Contract Date) « » Amount: $ « » Modifications to this Bond: « » None « » See Section 16 CONTRACTOR AS PRINCIPAL SURETY Company: (Corporate Seal) Company: (Corporate Seal) Signature: « » Signature: « » Name and Title: « »« » Name and Title: « »« » (Any additional signatures appear on the last page of this Performance Bond.) (FOR INFORMATION ONLY — Name, address and telephone) AGENT or BROKER: OWNER’S REPRESENTATIVE: (Architect, Engineer or other party:) « » « » « » « » « » « » « » « » « » AIA Document A312 – 2010 Performance Bond. Copyright © 2010. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 16:09:50 ET on 09/28/2026 under Order No.500072155_5 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (3B9ADA71) 2 § 1 The Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to the Owner for the performance of the Construction Contract, which is incorporated herein by reference. § 2 If the Contractor performs the Construction Contract, the Surety and the Contractor shall have no obligation under this Bond, except when applicable to participate in a conference as provided in Section 3. § 3 If there is no Owner Default under the Construction Contract, the Surety’s obligation under this Bond shall arise after .1 the Owner first provides notice to the Contractor and the Surety that the Owner is considering declaring a Contractor Default. Such notice shall indicate whether the Owner is requesting a conference among the Owner, Contractor and Surety to discuss the Contractor’s performance. If the Owner does not request a conference, the Surety may, within five (5) business days after receipt of the Owner’s notice, request such a conference. If the Surety timely requests a conference, the Owner shall attend. Unless the Owner agrees otherwise, any conference requested under this Section 3.1 shall be held within ten (10) business days of the Surety’s receipt of the Owner’s notice. If the Owner, the Contractor and the Surety agree, the Contractor shall be allowed a reasonable time to perform the Construction Contract, but such an agreement shall not waive the Owner’s right, if any, subsequently to declare a Contractor Default; .2 the Owner declares a Contractor Default, terminates the Construction Contract and notifies the Surety; and .3 the Owner has agreed to pay the Balance of the Contract Price in accordance with the terms of the Construction Contract to the Surety or to a contractor selected to perform the Construction Contract. § 4 Failure on the part of the Owner to comply with the notice requirement in Section 3.1 shall not constitute a failure to comply with a condition precedent to the Surety’s obligations, or release the Surety from its obligations, except to the extent the Surety demonstrates actual prejudice. § 5 When the Owner has satisfied the conditions of Section 3, the Surety shall promptly and at the Surety’s expense take one of the following actions: § 5.1 Arrange for the Contractor, with the consent of the Owner, to perform and complete the Construction Contract; § 5.2 Undertake to perform and complete the Construction Contract itself, through its agents or independent contractors; § 5.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract, arrange for a contract to be prepared for execution by the Owner and a contractor selected with the Owner’s concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the Construction Contract, and pay to the Owner the amount of damages as described in Section 7 in excess of the Balance of the Contract Price incurred by the Owner as a result of the Contractor Default; or § 5.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances: .1 After investigation, determine the amount for which it may be liable to the Owner and, as soon as practicable after the amount is determined, make payment to the Owner; or .2 Deny liability in whole or in part and notify the Owner, citing the reasons for denial. § 6 If the Surety does not proceed as provided in Section 5 with reasonable promptness, the Surety shall be deemed to be in default on this Bond seven days after receipt of an additional written notice from the Owner to the Surety demanding that the Surety perform its obligations under this Bond, and the Owner shall be entitled to enforce any remedy available to the Owner. If the Surety proceeds as provided in Section 5.4, and the Owner refuses the payment or the Surety has denied liability, in whole or in part, without further notice the Owner shall be entitled to enforce any remedy available to the Owner. § 7 If the Surety elects to act under Section 5.1, 5.2 or 5.3, then the responsibilities of the Surety to the Owner shall not be greater than those of the Contractor under the Construction Contract, and the responsibilities of the Owner to the Surety shall not be greater than those of the Owner under the Construction Contract. Subject to the commitment by the Owner to pay the Balance of the Contract Price, the Surety is obligated, without duplication, for AIA Document A312 – 2010 Performance Bond. Copyright © 2010. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 16:09:50 ET on 09/28/2026 under Order No.500072155_5 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (3B9ADA71) 3 .1 the responsibilities of the Contractor for correction of defective work and completion of the Construction Contract; .2 additional legal, design professional and delay costs resulting from the Contractor’s Default, and resulting from the actions or failure to act of the Surety under Section 5; and .3 liquidated damages, or if no liquidated damages are specified in the Construction Contract, actual damages caused by delayed performance or non-performance of the Contractor. § 8 If the Surety elects to act under Section 5.1, 5.3 or 5.4, the Surety’s liability is limited to the amount of this Bond. § 9 The Surety shall not be liable to the Owner or others for obligations of the Contractor that are unrelated to the Construction Contract, and the Balance of the Contract Price shall not be reduced or set off on account of any such unrelated obligations. No right of action shall accrue on this Bond to any person or entity other than the Owner or its heirs, executors, administrators, successors and assigns. § 10 The Surety hereby waives notice of any change, including changes of time, to the Construction Contract or to related subcontracts, purchase orders and other obligations. § 11 Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located and shall be instituted within two years after a declaration of Contractor Default or within two years after the Contractor ceased working or within two years after the Surety refuses or fails to perform its obligations under this Bond, whichever occurs first. If the provisions of this Paragraph are void or prohibited by law, the minimum period of limitation available to sureties as a defense in the jurisdiction of the suit shall be applicable. § 12 Notice to the Surety, the Owner or the Contractor shall be mailed or delivered to the address shown on the page on which their signature appears. § 13 When this Bond has been furnished to comply with a statutory or other legal requirement in the location where the construction was to be performed, any provision in this Bond conflicting with said statutory or legal requirement shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be deemed incorporated herein. When so furnished, the intent is that this Bond shall be construed as a statutory bond and not as a common law bond. § 14 Definitions § 14.1 Balance of the Contract Price. The total amount payable by the Owner to the Contractor under the Construction Contract after all proper adjustments have been made, including allowance to the Contractor of any amounts received or to be received by the Owner in settlement of insurance or other claims for damages to which the Contractor is entitled, reduced by all valid and proper payments made to or on behalf of the Contractor under the Construction Contract. § 14.2 Construction Contract. The agreement between the Owner and Contractor identified on the cover page, including all Contract Documents and changes made to the agreement and the Contract Documents. § 14.3 Contractor Default. Failure of the Contractor, which has not been remedied or waived, to perform or otherwise to comply with a material term of the Construction Contract. § 14.4 Owner Default. Failure of the Owner, which has not been remedied or waived, to pay the Contractor as required under the Construction Contract or to perform and complete or comply with the other material terms of the Construction Contract. § 14.5 Contract Documents. All the documents that comprise the agreement between the Owner and Contractor. § 15 If this Bond is issued for an agreement between a Contractor and subcontractor, the term Contractor in this Bond shall be deemed to be Subcontractor and the term Owner shall be deemed to be Contractor. § 16 Modifications to this bond are as follows: « » AIA Document A312 – 2010 Performance Bond. Copyright © 2010. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 16:09:50 ET on 09/28/2026 under Order No.500072155_5 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (3B9ADA71) 4 (Space is provided below for additional signatures of added parties, other than those appearing on the cover page.) CONTRACTOR AS PRINCIPAL SURETY Company: (Corporate Seal) Company: (Corporate Seal) Signature: « » Signature: « » Name and Title: « »« » Name and Title: « »« » Address: « » Address: « » AIA ® Document A312® – 2010 Payment Bond AIA Document A312 – 2010 Payment Bond. Copyright © 2010. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 16:08:51 ET on 09/28/2026 under Order No.500072155_4 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (3B9ADA70) 1 ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification. Any singular reference to Contractor, Surety, Owner or other party shall be considered plural where applicable. ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document. CONTRACTOR: (Name, legal status and address) SURETY: (Name, legal status and principal place of business) « »« » « » « »« » « » OWNER: (Name, legal status and address) «Montgomery County, Virginia»« » «755 Roanoke Street Suite 2E Christiansburg, Virginia 24073» CONSTRUCTION CONTRACT Date: « » Amount: $ «0.00» Description: (Name and location) «Montgomery County Fire & EMS Headquarters» «Christiansburg, Virginia» BOND Date: (Not earlier than Construction Contract Date) « » Amount: $ « » Modifications to this Bond: « » None « » See Section 18 CONTRACTOR AS PRINCIPAL SURETY Company: (Corporate Seal) Company: (Corporate Seal) Signature: « » Signature: « » Name and Title: « »« » Name and Title: « »« » (Any additional signatures appear on the last page of this Payment Bond.) (FOR INFORMATION ONLY — Name, address and telephone) AGENT or BROKER: OWNER’S REPRESENTATIVE: (Architect, Engineer or other party:) « » « » « » « » « » « » « » « » « » AIA Document A312 – 2010 Payment Bond. Copyright © 2010. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 16:08:51 ET on 09/28/2026 under Order No.500072155_4 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (3B9ADA70) 2 § 1 The Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to the Owner to pay for labor, materials and equipment furnished for use in the performance of the Construction Contract, which is incorporated herein by reference, subject to the following terms. § 2 If the Contractor promptly makes payment of all sums due to Claimants, and defends, indemnifies and holds harmless the Owner from claims, demands, liens or suits by any person or entity seeking payment for labor, materials or equipment furnished for use in the performance of the Construction Contract, then the Surety and the Contractor shall have no obligation under this Bond. § 3 If there is no Owner Default under the Construction Contract, the Surety’s obligation to the Owner under this Bond shall arise after the Owner has promptly notified the Contractor and the Surety (at the address described in Section 13) of claims, demands, liens or suits against the Owner or the Owner’s property by any person or entity seeking payment for labor, materials or equipment furnished for use in the performance of the Construction Contract and tendered defense of such claims, demands, liens or suits to the Contractor and the Surety. § 4 When the Owner has satisfied the conditions in Section 3, the Surety shall promptly and at the Surety’s expense defend, indemnify and hold harmless the Owner against a duly tendered claim, demand, lien or suit. § 5 The Surety’s obligations to a Claimant under this Bond shall arise after the following: § 5.1 Claimants, who do not have a direct contract with the Contractor, .1 have furnished a written notice of non-payment to the Contractor, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were, or equipment was, furnished or supplied or for whom the labor was done or performed, within ninety (90) days after having last performed labor or last furnished materials or equipment included in the Claim; and .2 have sent a Claim to the Surety (at the address described in Section 13). § 5.2 Claimants, who are employed by or have a direct contract with the Contractor, have sent a Claim to the Surety (at the address described in Section 13). § 6 If a notice of non-payment required by Section 5.1.1 is given by the Owner to the Contractor, that is sufficient to satisfy a Claimant’s obligation to furnish a written notice of non-payment under Section 5.1.1. § 7 When a Claimant has satisfied the conditions of Sections 5.1 or 5.2, whichever is applicable, the Surety shall promptly and at the Surety’s expense take the following actions: § 7.1 Send an answer to the Claimant, with a copy to the Owner, within sixty (60) days after receipt of the Claim, stating the amounts that are undisputed and the basis for challenging any amounts that are disputed; and § 7.2 Pay or arrange for payment of any undisputed amounts. § 7.3 The Surety’s failure to discharge its obligations under Section 7.1 or Section 7.2 shall not be deemed to constitute a waiver of defenses the Surety or Contractor may have or acquire as to a Claim, except as to undisputed amounts for which the Surety and Claimant have reached agreement. If, however, the Surety fails to discharge its obligations under Section 7.1 or Section 7.2, the Surety shall indemnify the Claimant for the reasonable attorney’s fees the Claimant incurs thereafter to recover any sums found to be due and owing to the Claimant. § 8 The Surety’s total obligation shall not exceed the amount of this Bond, plus the amount of reasonable attorney’s fees provided under Section 7.3, and the amount of this Bond shall be credited for any payments made in good faith by the Surety. § 9 Amounts owed by the Owner to the Contractor under the Construction Contract shall be used for the performance of the Construction Contract and to satisfy claims, if any, under any construction performance bond. By the Contractor furnishing and the Owner accepting this Bond, they agree that all funds earned by the Contractor in the performance of the Construction Contract are dedicated to satisfy obligations of the Contractor and Surety under this Bond, subject to the Owner’s priority to use the funds for the completion of the work. AIA Document A312 – 2010 Payment Bond. Copyright © 2010. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 16:08:51 ET on 09/28/2026 under Order No.500072155_4 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (3B9ADA70) 3 § 10 The Surety shall not be liable to the Owner, Claimants or others for obligations of the Contractor that are unrelated to the Construction Contract. The Owner shall not be liable for the payment of any costs or expenses of any Claimant under this Bond, and shall have under this Bond no obligation to make payments to, or give notice on behalf of, Claimants or otherwise have any obligations to Claimants under this Bond. § 11 The Surety hereby waives notice of any change, including changes of time, to the Construction Contract or to related subcontracts, purchase orders and other obligations. § 12 No suit or action shall be commenced by a Claimant under this Bond other than in a court of competent jurisdiction in the state in which the project that is the subject of the Construction Contract is located or after the expiration of one year from the date (1) on which the Claimant sent a Claim to the Surety pursuant to Section 5.1.2 or 5.2, or (2) on which the last labor or service was performed by anyone or the last materials or equipment were furnished by anyone under the Construction Contract, whichever of (1) or (2) first occurs. If the provisions of this Paragraph are void or prohibited by law, the minimum period of limitation available to sureties as a defense in the jurisdiction of the suit shall be applicable. § 13 Notice and Claims to the Surety, the Owner or the Contractor shall be mailed or delivered to the address shown on the page on which their signature appears. Actual receipt of notice or Claims, however accomplished, shall be sufficient compliance as of the date received. § 14 When this Bond has been furnished to comply with a statutory or other legal requirement in the location where the construction was to be performed, any provision in this Bond conflicting with said statutory or legal requirement shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be deemed incorporated herein. When so furnished, the intent is that this Bond shall be construed as a statutory bond and not as a common law bond. § 15 Upon request by any person or entity appearing to be a potential beneficiary of this Bond, the Contractor and Owner shall promptly furnish a copy of this Bond or shall permit a copy to be made. § 16 Definitions § 16.1 Claim. A written statement by the Claimant including at a minimum: .1 the name of the Claimant; .2 the name of the person for whom the labor was done, or materials or equipment furnished; .3 a copy of the agreement or purchase order pursuant to which labor, materials or equipment was furnished for use in the performance of the Construction Contract; .4 a brief description of the labor, materials or equipment furnished; .5 the date on which the Claimant last performed labor or last furnished materials or equipment for use in the performance of the Construction Contract; .6 the total amount earned by the Claimant for labor, materials or equipment furnished as of the date of the Claim; .7 the total amount of previous payments received by the Claimant; and .8 the total amount due and unpaid to the Claimant for labor, materials or equipment furnished as of the date of the Claim. § 16.2 Claimant. An individual or entity having a direct contract with the Contractor or with a subcontractor of the Contractor to furnish labor, materials or equipment for use in the performance of the Construction Contract. The term Claimant also includes any individual or entity that has rightfully asserted a claim under an applicable mechanic’s lien or similar statute against the real property upon which the Project is located. The intent of this Bond shall be to include without limitation in the terms “labor, materials or equipment” that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental equipment used in the Construction Contract, architectural and engineering services required for performance of the work of the Contractor and the Contractor’s subcontractors, and all other items for which a mechanic's lien may be asserted in the jurisdiction where the labor, materials or equipment were furnished. § 16.3 Construction Contract. The agreement between the Owner and Contractor identified on the cover page, including all Contract Documents and all changes made to the agreement and the Contract Documents. AIA Document A312 – 2010 Payment Bond. Copyright © 2010. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 16:08:51 ET on 09/28/2026 under Order No.500072155_4 which expires on 09/17/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (3B9ADA70) 4 § 16.4 Owner Default. Failure of the Owner, which has not been remedied or waived, to pay the Contractor as required under the Construction Contract or to perform and complete or comply with the other material terms of the Construction Contract. § 16.5 Contract Documents. All the documents that comprise the agreement between the Owner and Contractor. § 17 If this Bond is issued for an agreement between a Contractor and subcontractor, the term Contractor in this Bond shall be deemed to be Subcontractor and the term Owner shall be deemed to be Contractor. § 18 Modifications to this bond are as follows: « » (Space is provided below for additional signatures of added parties, other than those appearing on the cover page.) CONTRACTOR AS PRINCIPAL SURETY Company: (Corporate Seal) Company: (Corporate Seal) Signature: « » Signature: « » Name and Title: « »« » Name and Title: « »« » Address: « » Address: « » Montgomery County Worker’s Compensation Certificate of Coverage Fire & EMS Headquarters Page 111 of 286 DGS-30-076 CO-9a (Rev. 05/02) Page 1 of 1 COMMONWEALTH OF VIRGINIA WORKERS' COMPENSATION Certificate of Coverage Section 2.2-4332, Code of Virginia, requires construction contractors and subcontractors to obtain and maintain workers' compensation insurance while performing work on behalf of the Commonwealth of Virginia, its departments, institutions, or agencies. This same requirement applies on behalf of local governments. Evidence of coverage must be provided prior to commencement of Work. This form must be completed and returned to the organization contracting the Work. The undersigned organization stipulates that it: A. has workers' compensation insurance and is in compliance with the Workers' Compensation statutes of the Commonwealth of Virginia. _____ Yes _____ No Insurance Company ____________________________________ Policy expiration date __________________________________ B. is self insured for workers' compensation. _______ Yes _____ No Title of Construction Contract: _____________________________________________________________________ _____________________________________________________________________ Contract Number: _____________________________________________________ Signed by: _____________________________________ Title:_____________________________________ Firm Name: _____________________________________ Address:_____________________________________ _____________________________________ _____________________________________ Montgomery County Notice to Proceed Fire & EMS Headquarters Page 112 of 286 Notice to Proceed To: Contractor TBD Date: Project Description: Montgomery County Fire & EMS Headquarters Christiansburg, Virginia 24073 You are hereby notified to commence WORK in accordance with the Notice of Award dated ____/____, 2026, you are to substantially complete the work no later than ____/____, 2026, and you are required to finally complete the work no later than thirty (30) calendar days after the work is substantially complete. You are required to return an acknowledged copy of this NOTICE TO PROCEED to the Owner. Montgomery County Virginia Government By:______________________________ Title:_____________________________ ACCEPTANCE OF NOTICE Receipt of the above NOTICE TO PROCEED is hereby acknowledged by (Name of Contractor) this the ____________ day of ______________, 2026 By:________________________ Title:_______________________ Montgomery County Application and Certificate for Payment Fire & EMS Headquarters Page 113 of 286 Application and Certificate for Payment AIA G702 - 1992 The Contractor shall be responsible for purchasing, obtaining, and utilizing the official, licensed edition of the AIA G702 Application and Certificate for Payment document for all required project submittals and contractual compliance. It is the sole responsibility of the Contractor to secure this document directly from the American Institute of Architects (AIA) or an authorized distributor. The Contractor shall bear all associated costs for the procurement and licensing of the document and must ensure that its use complies fully with all applicable copyright laws and software licensing agreements. No unauthorized reproductions, altered templates, or unlicensed copies will be accepted by the Owner or Architect. The Contractor may propose to use an alternative format that is acceptable to the Owner. Montgomery County Application and Certificate for Payment Fire & EMS Headquarters Page 114 of 286 Application and Certificate for Payment – Continuation Sheet AIA G703 The Contractor shall be responsible for purchasing, obtaining, and utilizing the official, licensed edition of the AIA G703 Application & Certification for Payment – Continuation Sheet document for all required project submittals and contractual compliance. It is the sole responsibility of the Contractor to secure this document directly from the American Institute of Architects (AIA) or an authorized distributor. The Contractor shall bear all associated costs for the procurement and licensing of the document and must ensure that its use complies fully with all applicable copyright laws and software licensing agreements. No unauthorized reproductions, altered templates, or unlicensed copies will be accepted by the Owner or Architect. The Contractor may propose to use an alternative format that is acceptable to the Owner. GENERAL CONTRACTOR ESTIMATE FOR CHANGE ORDERDGS-30-200GC-1(Rev. 03/16)Project Code: General Contractor: Agency: Change Description: Project: GENERAL CONTRACTOR DIRECT COSTSLabor Units Hourly Wage Total Material Equipment TotalItem Direct Labor (Manhours, Rate, Excl. Labor Qty Cost Qty Cost EquipmentNo. Hours Crew Hours) Taxes & Ins. Cost Quantity Units Per Unit Quantity Units Per Unit CostA C D E F=C x E G H I J = G x I K L M N = K x M1.01$0.00 1.00 $100.00 $100.00 $0.001.02$0.00 $0.00 $0.001.03$0.00 $0.00 $0.001.04$0.00 $0.00 $0.001.05$0.00 $0.00 $0.001.06$0.00 $0.00 $0.001.07$0.00 $0.00 $0.001.08$0.00 $0.00 $0.001.09 Subtotal from Estimate Continuation Sheets$0.00 $0.00 $0.001.97 Subtotal (S/T) Direct Costs: Subtotal Labor $0.00 Subtotal Material $100.00 Subtotal Equipment $0.001.98 Taxes/Insurance:FICA, FUI, SUI, & Workmens' Comp. % of Labor $0.00 Sales Tax 0.0% Sales Tax 1.99 Total Direct Costs Total Labor$0.00 Total Material$100.00 Total Equipment$0.00SUBCONTRACT COSTSItem Subcontractor Name Total ItemNo. (List totals from attached SC-1 forms)Cost No. Description Total CostName:A B C3.01 Total Direct Labor CostItem 1.99H $0.002.01 3.02 Total Direct Material CostItem 1.99J $100.00 Signature:2.02 3.03 Total Equipment CostItem 1.99L $0.002.03 3.04 Subtotal3.01+3.02+3.03 $100.00 Title:2.04 3.05Overhead and Profit* (%)$0.002.05 3.06 Subtotal3.04+3.05 $100.00 Date:2.06 3.07 Subcontractor CostItem 2.99 $0.002.07 3.08GC Markup on Subcontractors** (%)$0.00 I have reviewed the costs proposed and find2.08 3.09 Subtotal3.06+3.07+3.08 $100.00 them to be reasonable (as proposed) (as marked).2.09 3.10 Additional Bond Cost2.99 Total Subcontract Costs$0.003.99 Total Change Order Cost(3.09+3.10) $100.00 A/E Signature:**Limited to a total of 10%, shared (cumulative total) if multiple tier subs, on subcontracted work. See Mark-up limitations for a more detailed description.*Limited to 15% on self-performed work.Note: Mark-up is capped in conformance with the provisions of the General Conditions (CO-7).SUMMARYBDirect EquipmentDirect MaterialTotal Material CostDirect LaborScope DescriptionDescription1 Montgomery County Contract Change Order Fire & EMS Headquarters Page 116 of 286 Change Order AIA G701 – 2017 The Owner shall be responsible for purchasing, obtaining, and utilizing the official, licensed edition of the AIA G701 Change Order document for all required project submittals and contractual compliance. The Owner may choose to use an alternative format that is similar to AIA G701. Montgomery County Certificate of Substantial Completion Fire & EMS Headquarters Page 117 of 286 Certificate of Substantial Completion AIA G704 – 2017 The Owner shall be responsible for purchasing, obtaining, and utilizing the official, licensed edition of the AIA G704 Certificate of Substantial Completion document for all required project submittals and contractual compliance. The Owner may choose to use an alternative format that is similar to AIA G704. Montgomery County Certificate of Completion by Architect / Engineer Fire & EMS Headquarters Page 118 of 286 DGS-30-112 CO-13.1 (Rev. 10/24) Page 1 of 1 CERTIFICATE OF COMPLETION BY ARCHITECT/ENGINEER or PROJECT MANAGER Date: TO: Montgomery County 755 Roanoke Street Christiansburg, VA 24073 PROJECT TITLE: Montgomery County Fire & EMS Headquarters MONTGOMERY COUNTY VA BID REQUEST NO. 27-07 PROJECT ADDRESS: 305 Roanoke Street, Christiansburg, VA 24073 Based upon the knowledge gained in the performance of the services required, the undersigned hereby states that the above named project was fully completed in accordance with the requirements of the Contract Documents on . (date) All applicable tests, certificates and regulatory inspections required by the 2021 edition of the Virginia Uniform Statewide Building Code, which was the basis of the design of the project, have been performed and the Owner has been provided with a copy of each report. A copy of the Final Report of Structural & Special Inspections (Form CO-13.1b) is attached to this certificate. All deficiencies noted during the inspection have been corrected or resolved. The accessibility standards required by Chapter 4 of the applicable A/E Manual, as revised, have been met. The Owner has been provided with a copy of all warranties and guarantees, including the starting date(s) of all warranties and guarantees, written and unwritten, required by the Contract Documents. (Typed Firm Name) By: (Typed Name & Title) Attachments: Final Report of Structural & Special Inspections (Form CO-13.1b) Montgomery County Certificate of Completion by Contractor Fire & EMS Headquarters Page 119 of 286 DGS-30-136 CO-13.2 (Rev. 10/18) Page 1 of 1 CERTIFICATE OF COMPLETION BY CONTRACTOR Date: TO: Montgomery County 755 Roanoke Street Christiansburg, VA 24073 PROJECT TITLE: Montgomery County Fire & EMS Headquarters MONTGOMERY COUNTY VA BID REQUEST NO. 27-07 PROJECT ADDRESS: 305 Roanoke Street, Christiansburg, VA 24073 In accordance with the requirements of the Contract between Owner and Contractor, the undersigned Contractor hereby states that the above-named project has been fully completed in accordance with the requirements of the Contract Documents as modified by approved change orders. All applicable tests, certificates and regulatory inspections required by the Virginia Uniform Statewide Building Code and the Contract Documents have been performed with respect to the completed project and the Owner has been provided with a copy of each report. As-built marked-up prints of the completed project have been provided to the Architect/Engineer as required by the Contract Documents. The Owner has been provided with a copy of all warranties and guarantees, including the starting date(s) of all warranties and guarantees, written and unwritten, required by the Contract Documents. All training, operating instructions and maintenance manuals required by the Contract Documents have been provided to the Owner. __________________________________ (Typed Contractor Name) By: _______________________________ __________________________________ (Typed Name & Title of Person Signing) cc: Agency A/E Montgomery County Contractor’s Affidavit of Release of Liens Fire & EMS Headquarters Page 120 of 286 Contractor’s Affidavit of Payment of Debts and Claims AIA G706 – 1994 The Contractor shall be responsible for purchasing, obtaining, and utilizing the official, licensed edition of the AIA G706 Contractor’s Affidavit of Payment of Debts and Claims document for all required project submittals and contractual compliance. It is the sole responsibility of the Contractor to secure this document directly from the American Institute of Architects (AIA) or an authorized distributor. The Contractor shall bear all associated costs for the procurement and licensing of the document and must ensure that its use complies fully with all applicable copyright laws and software licensing agreements. No unauthorized reproductions, altered templates, or unlicensed copies will be accepted by the Owner or Architect. The Contractor may propose to use an alternative format that is acceptable to the Owner. Montgomery County Contractor’s Affidavit of Release of Liens Fire & EMS Headquarters Page 121 of 286 Contractor’s Affidavit of Release of Liens AIA G706A – 1994 The Contractor shall be responsible for purchasing, obtaining, and utilizing the official, licensed edition of the AIA G706A Contractor’s Affidavit of Release of Liens document for all required project submittals and contractual compliance. It is the sole responsibility of the Contractor to secure this document directly from the American Institute of Architects (AIA) or an authorized distributor. The Contractor shall bear all associated costs for the procurement and licensing of the document and must ensure that its use complies fully with all applicable copyright laws and software licensing agreements. No unauthorized reproductions, altered templates, or unlicensed copies will be accepted by the Owner or Architect. The Contractor may propose to use an alternative format that is acceptable to the Owner. Montgomery County Consent of Surety to Final Payment Fire & EMS Headquarters Page 122 of 286 Consent of Surety to Final Payment AIA G707 The Contractor shall be responsible for purchasing, obtaining, and utilizing the official, licensed edition of the AIA G707 Consent of Surety to Final Payment document for all required project submittals and contractual compliance. It is the sole responsibility of the Contractor to secure this document directly from the American Institute of Architects (AIA) or an authorized distributor. The Contractor shall bear all associated costs for the procurement and licensing of the document and must ensure that its use complies fully with all applicable copyright laws and software licensing agreements. No unauthorized reproductions, altered templates, or unlicensed copies will be accepted by the Owner or Architect. The Contractor may propose to use an alternative format that is acceptable to the Owner. Montgomery County Part V – General Requirements Fire & EMS Headquarters Page 123 of 286 Part V – General Requirements Montgomery County 011000 - Summary Fire & EMS Headquarters Page 1 of 5 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Project information. 2. Work covered by Contract Documents. 3. Work performed by Owner. 4. Work under Owner's separate contracts. 5. Owner-furnished/Contractor-installed (OFCI) products. 6. Contractor's use of site and premises. 7. Work restrictions. 8. Specification and Drawing conventions. 9. Miscellaneous provisions. B. Related Requirements: 1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities. 2. Section 017300 "Execution" for coordination of Owner-installed products. 1.2 PROJECT INFORMATION A. Project Identification: Montgomery County Fire & EMS Headquarters 1. Project Location: 305 Roanoke Street, Christiansburg, VA 24073 B. Owner: Montgomery County C. Architect: Local Studio Architecture and Design PLLC 1. Architect's Representative: Braxton Cox, RA 2. Phone: (540) 250-4139 3. Email: braxtoncox@localstudiova.com 4. Address: 336 N Washington Ave, Pulaski, VA 24301 D. Architect's Consultants: Architect has retained the following design professionals, who have prepared designated portions of the Contract Documents: 1. Civil Engineer: Foresight Design Services a. Civil Engineer Representative: John Neel, PE b. Phone: (540) 381-6011 c. Email: jneel@foresightdesignservices.com d. Address: 1260 Radford Street, Christiansburg, VA 24073 Montgomery County 011000 - Summary Fire & EMS Headquarters Page 2 of 5 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 2. Structural Engineer: Truesdell Engineering, Inc. a. Structural Engineer Representative: Jordan Truesdell, PE b. Phone: (540) 552-7090 c. Email: jordan@truesdellengineering.com d. Address: 613 Country Club Drive SE, Blacksburg, VA 24060 3. Plumbing / Mechanical Engineer: MDR Engineering, LLC a. Plumbing / Mechanical Engineer Representative: Melinda Ruble, PE b. Phone: (540) 915-1576 c. Email: melinda@mdrengineering.com d. Address: PO Box 20812, Roanoke, VA 24018 4. Electrical Engineer: Gibson Engineering a. Electrical Engineer Representative: Daniel Gibson, PE b. Phone: (540) 998-6069 c. Email: daniel@gibsonengineer.com d. Address: 2100 Lubna Dr, Christiansburg, VA 24073 1.3 WORK COVERED BY CONTRACT DOCUMENTS A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following: 1. The Work generally consists of the complete interior renovation of the approximately 8,000 square foot building located at 305 Roanoke Street in Christiansburg, Virginia, as well as some exterior improvements. The proposed use of the space is for an administrative facility for the Montgomery County Department of Fire and EMS to include a lobby, offices, conference room, training room, storage rooms, break room, and toilet rooms. The property will also include space for on-call response personnel in the Fire and EMS departments to include sleep rooms, locker room, shower rooms, day room, apparatus bays, pharmacy, and storage rooms. Support spaces include a utility room and an IT / Electrical room. The County’s Mobile Command Unit vehicle will be housed on the property as well. The renovation Work consists of significant modifications to the existing building structural systems; the removal of the existing plumbing, mechanical, and electrical systems and replacement with new systems throughout; new interior finishes throughout; new exterior windows and doors. and other Work indicated in the Contract Documents. B. Type of Contract: 1. Project will be constructed under a single prime contract. 1.4 WORK UNDER OWNER'S SEPARATE CONTRACTS A. Work with Separate Contractors: Cooperate fully with Owner's separate contractors, so Montgomery County 011000 - Summary Fire & EMS Headquarters Page 3 of 5 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. work on those contracts may be carried out smoothly, without interfering with or delaying Work under this Contract or other contracts. Coordinate the Work of this Contract with work performed under Owner's separate contracts. B. Preceding Work: Owner has awarded separate contract(s) for the following construction operations at Project site. Those operations are scheduled to be substantially complete before Work under this Contract begins. 1. Lead & Asbestos Inspection 2. Lead & Asbestos Abatement C. Subsequent Work: Owner will award separate contract(s) for the following additional work to be performed at site following Substantial Completion. Completion of that work will depend on successful completion of preparatory Work under this Contract. 1. Station Alerting System work to be completed by US Digital Designs; rough-in to be completed by contractor per Contract Documents. D. Future Work Not Part of this Contract: The Contract Documents include requirements that will allow Owner to carry out future work following completion of this Project; provide for the following future work: 1. Installation of furnishings and appliances to be furnished and installed by owner or owner's vendor. 1.5 OWNER-FURNISHED/CONTRACTOR-INSTALLED (OFCI) PRODUCTS A. Owner's Responsibilities: Owner will furnish products indicated and perform the following, as applicable: 1. Provide to Contractor Owner-reviewed Product Data, Shop Drawings, and Samples. 2. Provide for delivery of Owner-furnished products to Project site. 3. Upon delivery, inspect, with Contractor present, delivered items. a. If Owner-furnished products are damaged, defective, or missing, arrange for replacement. 4. Obtain manufacturer's inspections, service, and warranties. 5. Inform Contractor of earliest available delivery date for Owner-furnished products. B. Contractor's Responsibilities: The Work includes the following, as applicable: 1. Designate delivery dates of Owner-furnished products in Contractor's construction schedule, utilizing Owner-furnished earliest available delivery dates. 2. Review Owner-reviewed Product Data, Shop Drawings, and Samples, noting discrepancies and other issues in providing for Owner-furnished products in the Work. 3. Receive, unload, handle, store, protect, and install Owner-furnished products. 4. Make building services connections for Owner-furnished products. Montgomery County 011000 - Summary Fire & EMS Headquarters Page 4 of 5 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 5. Protect Owner-furnished products from damage during storage, handling, and installation and prior to Substantial Completion. 6. Repair or replace Owner-furnished products damaged following receipt. C. Owner-Furnished/Contractor-Installed (OFCI) Products: 1. Toilet Tissue Dispenser: Dispenser Tissue Revolution (3-Roll, Black): SCA565828B. 2. Paper Towel Dispenser: Dispenser Towel Smoke (C-Fold and Multi-Fold): GP56650A 3. Soap Dispenser: Dispenser Foam Bulk Soap White/Gray (1,000 mL): IMP9325 1.6 CONTRACTOR'S USE OF SITE AND PREMISES A. Unrestricted Use of Site: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project. B. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations. C. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations. 1.7 WORK RESTRICTIONS A. Comply with restrictions on construction operations. 1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction. B. On-Site Work Hours: Limit work to between 7:00 a.m. to 7:00 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by Owner and authorities having jurisdiction. C. Smoking and Controlled Substance Restrictions: Use of tobacco products , alcoholic beverages, and other controlled substances within the existing building is not permitted. 1.8 SPECIFICATION AND DRAWING CONVENTIONS A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows: 1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase. Montgomery County 011000 - Summary Fire & EMS Headquarters Page 5 of 5 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics. 3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents. 4. Specification requirements are to be performed by Contractor unless specifically stated otherwise. B. General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications. C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications. D. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products: 1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections. 2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings and published as part of the U.S. National CAD Standard. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 011000 Montgomery County 012100 - Allowances Fire & EMS Headquarters Page 1 of 3 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 012100 - ALLOWANCES PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements governing allowances. B. Types of allowances include the following: 1. Quantity allowances. C. Related Requirements: 1. Section 012200 "Unit Prices" for procedures for using unit prices, including adjustment of quantity allowances when applicable. 2. Section 012600 "Contract Modification Procedures" for procedures for submitting and handling Change Orders. 3. Section 014000 "Quality Requirements" for procedures governing the use of allowances for field testing by an independent testing agency. 1.2 DEFINITIONS A. Allowance: A quantity of work or dollar amount included in the Base Bid Price, established in lieu of additional requirements, used to defer selection of actual materials and equipment to a later date when direction will be provided to Contractor. If necessary, additional requirements will be issued by Change Order. 1.3 SELECTION AND PURCHASE A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection, or purchase and delivery, of each product or system described by an allowance must be completed by the Owner to avoid delaying the Work. B. At Architect's request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work. C. Purchase products and systems selected by Architect from the designated supplier. 1.4 ACTION SUBMITTALS A. Submit proposals for purchase of products or systems included in allowances in the form specified for Change Orders. 1.5 INFORMATIONAL SUBMITTALS A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance. Montgomery County 012100 - Allowances Fire & EMS Headquarters Page 2 of 3 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance. C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work. 1.6 QUANTITY ALLOWANCES A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Architect under allowance and shall include taxes, freight, and delivery to Project site. B. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials ordered by Owner or selected by Architect under allowance shall be included as part of the Contract Sum and not part of the allowance. C. Unused Materials: Return unused materials purchased under an allowance to manufacturer or supplier for credit to Owner, after installation has been completed and accepted. 1. If requested by Architect, retain and prepare unused material for storage by Owner. Deliver unused material to Owner's storage space as directed. 1.7 ADJUSTMENT OF ALLOWANCES A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, required maintenance materials, and similar margins. 1. Include installation costs in purchase amount only where indicated as part of the allowance. 2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other markups. 3. Submit substantiation of a change in scope of Work, if any, claimed in Change Orders related to unit-cost allowances. 4. Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count. B. Submit claims for increased costs due to a change in the scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit. 1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of Work has changed from what could have been foreseen from information in the Contract Documents. 2. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated. Montgomery County 012100 - Allowances Fire & EMS Headquarters Page 3 of 3 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 EXAMINATION A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement. 3.2 PREPARATION A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work. 3.3 SCHEDULE OF ALLOWANCES A. Allowance No. 1: Quantity Allowance: Include 1,000 cu. yd. of unsatisfactory soil excavation and disposal off-site and replacement with satisfactory soil material from off-site. 1. Coordinate quantity allowance adjustment with unit-price requirements in Section 012200 "Unit Prices." B. Allowance No. 2: Quantity Allowance: Include 500 cu. yd. of mass rock removal and replacement with satisfactory soil material. 1. Coordinate quantity allowance adjustment with unit-price requirements in Section 012200 "Unit Prices." C. Allowance No. 3: Quantity Allowance: Include 10 cu. yd. of trench rock removal and replacement with satisfactory soil material. 1. Coordinate quantity allowance adjustment with unit-price requirements in Section 012200 "Unit Prices." D. Allowance No. 4: Quantity Allowance: Include 1,500 sq. ft. of partial repointing of existing brick veneer. 1. Coordinate quantity allowance adjustment with unit-price requirements in Section 012200 "Unit Prices." END OF SECTION 012100 Montgomery County 012200 – Unit Prices Fire & EMS Headquarters Page 1 of 2 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 012200 - UNIT PRICES PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for unit prices. B. Related Requirements: 1. Section 012100 "Allowances" for procedures for using unit prices to adjust quantity allowances. 2. Section 012600 "Contract Modification Procedures" for procedures for submitting and handling Change Orders. 3. Section 014000 "Quality Requirements" for field testing by an independent testing agency. 1.2 DEFINITIONS A. Unit price is an amount incorporated into the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased. 1.3 PROCEDURES A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit. B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections. C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor. D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the Part 3 "Schedule of Unit Prices" Article contain requirements for materials described under each unit price. PART 2 - PRODUCTS (Not Used) Montgomery County 012200 – Unit Prices Fire & EMS Headquarters Page 2 of 2 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. PART 3 - EXECUTION 3.1 SCHEDULE OF UNIT PRICES A. Unit Price No. 1: Removal of unsatisfactory soil and replacement with satisfactory soil material. 1. Description: Unsatisfactory soil excavation and disposal off-site and replacement with satisfactory fill material or engineered fill from off-site. 2. Unit of Measurement: cubic yard of soil excavated, based on in-place surveys of volume before and after removal. 3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in Section 012100 "Allowances." B. Unit Price No. 2: Mass rock excavation and replacement with satisfactory soil material. 1. Description: Classified mass rock excavation and disposal off-site and replacement with satisfactory fill material or engineered fill from off-site. 2. Unit of Measurement: cubic yard of rock excavated, based on in-place surveys of volume before and after removal. 3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in Section 012100 "Allowances." C. Unit Price No. 3: Trench rock excavation and replacement with satisfactory soil material. 1. Description: Classified trench rock excavation and disposal off-site and replacement with satisfactory fill material or engineered fill from off-site. 2. Unit of Measurement: cubic yard of rock excavated, based on survey of in-place surveys volume of before and after removal. 3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in Section 012100 "Allowances." D. Unit Price No. 4: Partial Repointing of Existing Brick Veneer 1. Description: Hand-grinding or mechanical cutting of old mortar to a depth at least two times the joint width; flushing debris and dust with water or air; new pointing mortar matched in color, compressive strength, and binder composition; packing and compacting mortar into joints and striking/tooling to the specified joint profile. All materials and equipment necessary to complete the work, including scaffolding, lifts, or outriggers, are to be included in the square-foot unit price. 2. Unit of Measurement: square feet of face of brick veneer wall to be repointed. 3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in Section 012100 "Allowances." END OF SECTION 012200 Montgomery County 012300 - Alternates Fire & EMS Headquarters Page 1 of 2 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 012300 - ALTERNATES PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for alternates. 1.2 DEFINITIONS A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if the Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. 1. Alternates described in this Section are part of the Work only if enumerated in the Agreement. 2. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternates into the Work. No other adjustments are made to the Contract Sum. 1.3 PROCEDURES A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project. 1. Include, as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation, whether or not indicated as part of alternate. B. Execute accepted alternates under the same conditions as other Work of the Contract. C. Schedule: A Part 3 "Schedule of Alternates" Article is included at the end of this Section. Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate. PART 2 - PRODUCTS (Not Used) Montgomery County 012300 - Alternates Fire & EMS Headquarters Page 2 of 2 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. PART 3 - EXECUTION 3.1 SCHEDULE OF ALTERNATES A. Alternate No. 1: New Roof Structure. 1. Base Bid: Modify existing roof structure as indicated on the base bid drawings. Existing roof, fascia, and soffit finishes to remain. 2. Alternate: Replace the existing roof structure with a new roof structure as indicated on the alternate bid drawings. New roof, fascia, and soffit finishes as indicated on the alternate bid drawings. a. Option A – Standing-Seam Metal Roof Panels System: New roof finish to be a standing-seam metal roof panel system b. Option B – Exposed-Fastener Metal Roof Panels System: New roof finish to be an exposed-fastener metal roof panel system c. Option C – Asphalt Shingle Roofing System: New roof finish to be an asphalt shingle roofing system B. Alternate No. 2: Gas Fired Unit Heaters. 1. Base Bid: Relocate the three existing gas fired unit heaters as indicated on sheets M301 and M302. Existing gas fired unit heaters to be inspected and serviced prior to re-use. 2. Alternate: Remove three existing gas fired unit heaters and install new gas fired unit heaters as indicated on sheets M201, M301, and M302 (Note 3). END OF SECTION 012300 Montgomery County 012500 – Substitution Procedures Fire & EMS Headquarters Page 1 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 012500 - SUBSTITUTION PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. The Work of This Section Includes: Administrative and procedural requirements for substitutions. B. Related Requirements: 1. Section 012100 "Allowances" for products selected under an allowance. 2. Section 012300 "Alternates" for products selected under an alternate. 3. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers. 1.2 DEFINITIONS A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents. 1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms. 2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required to meet other Project requirements but may offer advantage to Contractor or Owner. 1.3 ACTION SUBMITTALS A. Substitution Requests: Submit documentation identifying product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles. 1. Substitution Request Form: Use form acceptable to Architect. 2. Documentation: Show compliance with requirements for substitutions and the following, as applicable: a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable. b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution. c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design Montgomery County 012500 – Substitution Procedures Fire & EMS Headquarters Page 2 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified. d. Product Data, including drawings and descriptions of products and fabrication and installation procedures. e. Samples, where applicable or requested. f. Certificates and qualification data, where applicable or requested. g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners. h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated. i. Research reports evidencing compliance with building code in effect for Project. j. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery. k. Cost information, including a proposal of change, if any, in the Contract Sum. l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated. m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results. 3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Architect will notify Contractor of acceptance or rejection of proposed substitution within 14 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later. a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work. b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated. 1.4 QUALITY ASSURANCE A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers. 1.5 PROCEDURES A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions. Montgomery County 012500 – Substitution Procedures Fire & EMS Headquarters Page 3 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1.6 SUBSTITUTIONS A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals. 1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements: a. Requested substitution is consistent with the Contract Documents and will produce indicated results. b. Substitution request is fully documented and properly submitted. c. Requested substitution will not adversely affect Contractor's construction schedule. d. Requested substitution has received necessary approvals from authorities having jurisdiction. e. Requested substitution is compatible with other portions of the Work. f. Requested substitution has been coordinated with other portions of the Work. g. Requested substitution provides specified warranty. h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved. B. Substitutions for Convenience: 1. Architect will consider requests for substitution if received within 75 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Architect. a. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements: 1) Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations. 2) Requested substitution does not require extensive revisions to the Contract Documents. 3) Requested substitution is consistent with the Contract Documents and will produce indicated results. 4) Substitution request is fully documented and properly submitted. 5) Requested substitution will not adversely affect Contractor's construction schedule. Montgomery County 012500 – Substitution Procedures Fire & EMS Headquarters Page 4 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 6) Requested substitution has received necessary approvals from authorities having jurisdiction. 7) Requested substitution is compatible with other portions of the Work. 8) Requested substitution has been coordinated with other portions of the Work. 9) Requested substitution provides specified warranty. 10) If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 012500 Montgomery County 012600 – Contract Modification Procedures Fire & EMS Headquarters Page 1 of 3 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 012600 - CONTRACT MODIFICATION PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for handling and processing Contract modifications. B. Related Requirements: 1. Section 012500 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award. 2. Section 013100 "Project Management and Coordination" for requirements for forms for contract modifications provided as part of web-based Project management software. 1.2 MINOR CHANGES IN THE WORK A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710. 1.3 PROPOSAL REQUESTS A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications. 1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change. 2. Within time specified in Proposal Request, or 20 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change. a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities. b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. c. Include costs of labor and supervision directly attributable to the change. d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time. Montgomery County 012600 – Contract Modification Procedures Fire & EMS Headquarters Page 2 of 3 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. e. Quotation Form: Use forms acceptable to Architect. B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect. 1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time. 2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities. 3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. 4. Include costs of labor and supervision directly attributable to the change. 5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time. 6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified. 7. Proposal Request Form: Use form acceptable to Architect. 1.4 ADMINISTRATIVE CHANGE ORDERS A. Allowance Adjustment: See Section 012100 "Allowances" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances. B. Unit-Price Adjustment: See Section 012200 "Unit Prices" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect measured scope of unit-price work. 1.5 CHANGE ORDER PROCEDURES A. On Owner's approval of a Work Change Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701. 1.6 CONSTRUCTION CHANGE DIRECTIVE A. Construction Change Directive: Architect may issue a Construction Change Directive on AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. 1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time. Montgomery County 012600 – Contract Modification Procedures Fire & EMS Headquarters Page 3 of 3 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive. 1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 012600 Montgomery County 012900 – Payment Procedures Fire & EMS Headquarters Page 1 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 012900 - PAYMENT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment. B. Related Requirements: 1. Section 012100 "Allowances" for procedural requirements governing the handling and processing of allowances. 2. Section 012200 "Unit Prices" for administrative requirements governing the use of unit prices. 3. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract. 4. Section 013200 "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule. 1.2 DEFINITIONS A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment. 1.3 SCHEDULE OF VALUES A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule. 1. Coordinate line items in the schedule of values with items required to be indicated as separate activities in Contractor's construction schedule. 2. Submit the schedule of values to Architect at earliest possible date, but no later than 14 days before the date scheduled for submittal of initial Applications for Payment. B. Format and Content: Use the Construction Specifications Institute (CSI) numbering system to establish line items for the schedule of values. 1. Identification: Include the following Project identification on the schedule of values: a. Project name and location. b. Owner's name. c. Owner's Bid Request number. d. Name of Architect. Montgomery County 012900 – Payment Procedures Fire & EMS Headquarters Page 2 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. e. Architect's Project number. f. Contractor's name and address. g. Date of submittal. 2. Arrange schedule of values consistent with format of AIA Document G703. 3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum. 4. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed. a. Differentiate between items stored on-site and items stored off-site. 5. Allowances: Provide a separate line item in the schedule of values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities. 6. Overhead Costs, Proportional Distribution: Include total cost and proportionate share of general overhead and profit for each line item. 7. Temporary Facilities: Show cost of temporary facilities and other major cost items that are not direct cost of actual work-in-place as separate line items. 8. Closeout Costs. Include separate line items under Contractor and principal subcontracts for Project closeout requirements. 9. Schedule of Values Revisions: Revise the schedule of values when Change Orders or Construction Change Directives result in a change in the Contract Sum. Include at least one separate line item for each Change Order and Construction Change Directive. 1.4 APPLICATIONS FOR PAYMENT A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments, as certified by Architect and paid for by Owner. B. Payment Application Times: The date for each progress payment is indicated in the Owner/Contractor Agreement. The period of construction work covered by each Application for Payment is the period indicated in the Agreement. C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment. 1. Other Application for Payment forms proposed by the Contractor may be acceptable to Architect and Owner. Submit forms for approval with initial submittal of schedule of values. D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action. 1. Entries shall match data on the schedule of values and Contractor's construction Montgomery County 012900 – Payment Procedures Fire & EMS Headquarters Page 3 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. schedule. Use updated schedules if revisions were made. 2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment. 3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application. 4. Indicate separate amounts for work being carried out under Owner-requested project acceleration. E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site. 1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment for stored materials. 2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials. 3. Provide summary documentation for stored materials indicating the following: a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment. b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment. c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment. F. Transmittal: Submit one signed and notarized digital copy of each Application for Payment to Architect by email. The email shall include waivers of lien and similar attachments if required. 1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application. G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following: 1. List of subcontractors. 2. Schedule of values. 3. Contractor's construction schedule (preliminary if not final). 4. Products list (preliminary if not final). 5. Schedule of unit prices. 6. Submittal schedule (preliminary if not final). 7. List of Contractor's staff assignments. 8. List of Contractor's principal consultants. 9. Copies of building permits. 10. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work. 11. Initial progress report. 12. Report of preconstruction conference. Montgomery County 012900 – Payment Procedures Fire & EMS Headquarters Page 4 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 13. Certificates of insurance and insurance policies. 14. Performance and payment bonds. 15. Data needed to acquire Owner's insurance. H. Application for Payment at Substantial Completion: After Architect issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete. 1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum. a. Complete administrative actions, submittals, and Work preceding this application, as described in Section 017700 "Closeout Procedures." 2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work. I. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following: 1. Evidence of completion of Project closeout requirements. 2. Certification of completion of final punch list items. 3. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid. 4. Updated final statement, accounting for final changes to the Contract Sum. 5. AIA Document G706. 6. AIA Document G706A. 7. AIA Document G707. 8. Evidence that claims have been settled. 9. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work. 10. Final liquidated damages settlement statement. 11. Proof that taxes, fees, and similar obligations are paid. 12. Waivers and releases. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 012900 Montgomery County 013100 – Project Management and Coordination Fire & EMS Headquarters Page 1 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 SUMMARY A. The Work of this Section includes administrative provisions for coordinating construction operations on Project, including, but not limited to, the following: 1. General coordination procedures. 2. Coordination drawings. 3. RFIs. 4. Digital project management procedures. 5. Project meetings. B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor. C. Related Requirements: 1. Section 013200 "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule. 2. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points. 3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract. 4. Section 019113 "General Commissioning Requirements" for coordinating the Work with Owner's Commissioning Authority. 1.2 DEFINITIONS A. BIM: Building Information Modeling. B. RFI: Request for Information. Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents. 1.3 INFORMATIONAL SUBMITTALS A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form: 1. Name, address, telephone number, and email address of entity performing subcontract or supplying products. 2. Number and title of related Specification Section(s) covered by subcontract. 3. Drawing number and detail references, as appropriate, covered by subcontract. B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in Montgomery County 013100 – Project Management and Coordination Fire & EMS Headquarters Page 2 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. attendance at Project site. Identify individuals and their duties and responsibilities; list addresses, cellular telephone numbers, and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project. 1. Post copies of list in Project meeting room, in temporary field office, and in prominent location in built facility. Keep list current at all times. 1.4 GENERAL COORDINATION PROCEDURES A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation. 1. Schedule construction operations in sequence required to obtain the best results, where installation of one part of the Work depends on installation of other components, before or after its own installation. 2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair. 3. Make adequate provisions to accommodate items scheduled for later installation. B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings. 1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required. C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following: 1. Preparation of Contractor's construction schedule. 2. Preparation of the schedule of values. 3. Installation and removal of temporary facilities and controls. 4. Delivery and processing of submittals. 5. Progress meetings. 6. Preinstallation conferences. 7. Project closeout activities. 8. Startup and adjustment of systems. 1.5 COORDINATION DRAWINGS A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and Montgomery County 013100 – Project Management and Coordination Fire & EMS Headquarters Page 3 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. materials fabricated or installed by more than one entity. 1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable: a. Use applicable Drawings as a basis for preparation of coordination drawings. Prepare sections, elevations, and details as needed to describe relationship of various systems and components. b. Coordinate the addition of trade-specific information to coordination drawings in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review. c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems. d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation. e. Show location and size of access doors required for access to concealed dampers, valves, and other controls. f. Indicate required installation sequences. g. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternative sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract. B. Coordination Drawing Organization: Organize coordination drawings as follows: 1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work. 2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within plenums to accommodate layout of light fixtures and other components indicated on Drawings. Indicate areas of conflict between light fixtures and other components. 3. Mechanical Rooms: Provide coordination drawings for mechanical rooms, showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment. 4. Structural Penetrations: Indicate penetrations and openings required for all disciplines. 5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items. 6. Mechanical and Plumbing Work: Show the following: a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems. Montgomery County 013100 – Project Management and Coordination Fire & EMS Headquarters Page 4 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment. c. Fire-rated enclosures around ductwork. 7. Electrical Work: Show the following: a. Runs of vertical and horizontal conduit 1-1/4 inches in diameter and larger. b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations. c. Panel board, switchboard, switchgear, transformer, busway, generator, and motor-control center locations. d. Location of pull boxes and junction boxes, dimensioned from column center lines. 8. Fire-Protection System: Show the following: a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads. 9. Review: Architect will review coordination drawings to confirm that, in general, the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If Architect determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Architect will so inform Contractor, who shall make suitable modifications and resubmit. 10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 013300 "Submittal Procedures." C. Coordination Drawing Process: Prepare coordination drawings in the following manner: 1. Schedule submittal and review of Fire Sprinkler, Plumbing, HVAC, and Electrical Shop Drawings to make required changes prior to preparation of coordination drawings. 2. Commence routing of coordination drawing files with HVAC Installer, who will provide drawing plan files denoting approved ductwork. HVAC Installer will locate ductwork and piping on a single layer, using orange color. Forward drawings to Plumbing Installer. 3. Plumbing Installer will locate plumbing and equipment on a single layer, using blue color. 4. Fire Sprinkler Installer will locate piping and equipment, using red color. Fire Sprinkler Installer shall forward drawing files to Electrical Installer. 5. Electrical Installer will indicate service and feeder conduit runs and equipment in green color. Electrical Installer shall forward drawing files to Communications and Electronic Safety and Security Installer. 6. Communications and Electronic Safety and Security Installer will indicate cable trays and cabling runs and equipment in purple color. Communications and Electronic Safety and Security Installer shall forward completed drawing files to Contractor. 7. Contractor shall perform the final coordination review. As each coordination drawing is completed, Contractor will meet with Architect to review and resolve conflicts on the coordination drawings. Montgomery County 013100 – Project Management and Coordination Fire & EMS Headquarters Page 5 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. D. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements: 1. File Preparation Format: a. Same digital data software program, version, and operating system as original Drawings. b. DWG, operating in Microsoft Windows operating system. 2. File Submittal Format: Submit or post coordination drawing files using same format as file preparation format. 3. Architect will furnish Contractor one set of digital data files of Drawings for use in preparing coordination digital data files. a. Architect makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings. b. Digital Data Software Program: Drawings are available in DWG format, operating in Microsoft Windows operating system. c. Contractor shall execute a data licensing agreement in the form of Agreement form acceptable to Owner and Architect. 1.6 REQUEST FOR INFORMATION (RFI) A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified. 1. Architect will return without response those RFIs submitted to Architect by other entities controlled by Contractor. 2. Coordinate and submit RFIs in a prompt manner to avoid delays in Contractor's work or work of subcontractors. B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following: 1. Project name. 2. Owner name. 3. Owner's bid request number. 4. Name of Architect. 5. Architect's Project number. 6. Date. 7. Name of Contractor. 8. RFI number, numbered sequentially. 9. RFI subject. 10. Specification Section number and title and related paragraphs, as appropriate. 11. Drawing number and detail references, as appropriate. 12. Field dimensions and conditions, as appropriate. 13. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI. 14. Contractor's signature. Montgomery County 013100 – Project Management and Coordination Fire & EMS Headquarters Page 6 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 15. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation. a. Include dimensions, thicknesses, and details of affected materials, assemblies, and attachments on attached sketches. C. RFI Forms: form acceptable to Architect. 1. Attachments shall be electronic files in PDF format. D. Action: Architect will review each RFI, determine action required, and respond. Allow seven days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day. 1. The following Contractor-generated RFIs will be returned without action: a. Requests for approval of submittals. b. Requests for approval of substitutions. c. Requests for approval of Contractor's means and methods. d. Requests for coordination information already indicated in the Contract Documents. e. Requests for adjustments in the Contract Time or the Contract Sum. f. Requests for interpretation of Architect's actions on submittals. g. Incomplete RFIs or inaccurately prepared RFIs. 2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt by Architect of additional information. 3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures." a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect in writing within 5 days of receipt of the RFI response. E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Include the following: 1. Project name. 2. Name and address of Contractor. 3. Name and address of Architect. 4. RFI number, including RFIs that were returned without action or withdrawn. 5. RFI description. 6. Date the RFI was submitted. 7. Date Architect's response was received. 8. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate. 9. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate. Montgomery County 013100 – Project Management and Coordination Fire & EMS Headquarters Page 7 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. F. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within three days if Contractor disagrees with response. 1.7 DIGITAL PROJECT MANAGEMENT PROCEDURES A. Use of Architect's Digital Data Files: Digital data files of Architect's BIM model and/or CAD drawings will be provided by Architect for Contractor's use during construction. 1. Digital data files may be used by Contractor in preparing coordination drawings, Shop Drawings, and Project Record Drawings. 2. Architect makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings. 3. Digital Drawing Software Program: Contract Drawings are available in DWG and RVT, operating in Microsoft Windows operating system 4. Contractor shall execute a data licensing agreement in an Agreement form acceptable to Owner and Architect. a. Subcontractors and other parties granted access by Contractor to Architect's digital data files shall execute a data licensing agreement in the form of an Agreement acceptable to Owner and Architect. B. PDF Document Preparation: Where PDFs are required to be submitted to Architect, prepare as follows: 1. Assemble complete submittal package into a single indexed file, incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item. 2. Name file with submittal number or other unique identifier, including revision identifier. 3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated. 1.8 PROJECT MEETINGS A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated. 1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Architect of scheduled meeting dates and times a minimum of seven days prior to meeting. 2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees. 3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner and Architect, within three days of the meeting. Montgomery County 013100 – Project Management and Coordination Fire & EMS Headquarters Page 8 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Architect, but no later than 15 days after execution of the Agreement. 1. Attendees: Authorized representatives of Owner, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work. 2. Agenda: Discuss items of significance that could affect progress, including the following: a. Responsibilities and personnel assignments. b. Tentative construction schedule. c. Phasing. d. Critical work sequencing and long lead items. e. Designation of key personnel and their duties. f. Lines of communications. g. Use of web-based Project software, if using. h. Procedures for processing field decisions and Change Orders. i. Procedures for RFIs. j. Procedures for testing and inspecting. k. Procedures for processing Applications for Payment. l. Distribution of the Contract Documents. m. Submittal procedures. n. Sustainable design requirements. o. Preparation of Record Documents. p. Use of the premises and existing building. q. Work restrictions. r. Working hours. s. Owner's occupancy requirements. t. Responsibility for temporary facilities and controls. u. Procedures for moisture and mold control. v. Procedures for disruptions and shutdowns. w. Construction waste management and recycling. x. Parking availability. y. Office, work, and storage areas. z. Equipment deliveries and priorities. aa. First aid. bb. Security. cc. Progress cleaning. 3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes. C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity when required by other Sections and when required for coordination with other construction. 1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with Montgomery County 013100 – Project Management and Coordination Fire & EMS Headquarters Page 9 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. other materials and installations that have preceded or will follow, shall attend the meeting. Advise Architect of scheduled meeting dates. 2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following: a. Contract Documents. b. Options. c. Related RFIs. d. Related Change Orders. e. Purchases. f. Deliveries. g. Submittals. h. Review of mockups. i. Possible conflicts. j. Compatibility requirements. k. Time schedules. l. Weather limitations. m. Manufacturer's written instructions. n. Warranty requirements. o. Compatibility of materials. p. Acceptability of substrates. q. Temporary facilities and controls. r. Space and access limitations. s. Regulations of authorities having jurisdiction. t. Testing and inspecting requirements. u. Installation procedures. v. Coordination with other work. w. Required performance results. x. Protection of adjacent work. y. Protection of construction and personnel. 3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions. 4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information. 5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date. D. Progress Meetings: Conduct progress meetings at monthly intervals. 1. Coordinate dates of meetings with preparation of payment requests. 2. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work. 3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project. Montgomery County 013100 – Project Management and Coordination Fire & EMS Headquarters Page 10 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time. 1) Review schedule for next period. b. Review present and future needs of each entity present, including the following: 1) Interface requirements. 2) Sequence of operations. 3) Resolution of BIM component conflicts. 4) Status of submittals. 5) Deliveries. 6) Off-site fabrication. 7) Access. 8) Site use. 9) Temporary facilities and controls. 10) Progress cleaning. 11) Quality and work standards. 12) Status of correction of deficient items. 13) Field observations. 14) Status of RFIs. 15) Status of Proposal Requests. 16) Pending changes. 17) Status of Change Orders. 18) Pending claims and disputes. 19) Documentation of information for payment requests. 4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information. a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting, where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting. E. Project Closeout Conference: Schedule and conduct a project closeout conference, at a time convenient to Owner and Architect, but no later than 30 days prior to the scheduled date of Substantial Completion. 1. Conduct the conference to review requirements and responsibilities related to Project closeout. 2. Attendees: Authorized representatives of Owner, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work. Montgomery County 013100 – Project Management and Coordination Fire & EMS Headquarters Page 11 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following: a. Preparation of Record Documents. b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance. c. Procedures for completing and archiving web-based Project software site data files. d. Submittal of written warranties. e. Requirements for preparing operations and maintenance data. f. Requirements for delivery of material samples, attic stock, and spare parts. g. Requirements for demonstration and training. h. Preparation of Contractor's punch list. i. Procedures for processing Applications for Payment at Substantial Completion and for final payment. j. Submittal procedures. k. Installation of Owner's furniture, fixtures, and equipment. l. Responsibility for removing temporary facilities and controls. 4. Minutes: Entity conducting meeting will record and distribute meeting minutes. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 013100 Montgomery County 013200 – Construction Progress Documentation Fire & EMS Headquarters Page 1 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following: 1. Startup construction schedule. 2. Contractor's Construction Schedule. 3. Construction schedule updating reports. 4. Daily construction reports. 5. Material location reports. 6. Site condition reports. 7. Unusual event reports. B. Related Requirements: 1. Section 012900 "Payment Procedures" for schedule of values and requirements for use of cost-loaded schedule for Applications for Payment. 2. Section 014000 "Quality Requirements" for schedule of tests and inspections. 1.2 DEFINITIONS A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources. 1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times. 2. Predecessor Activity: An activity that precedes another activity in the network. 3. Successor Activity: An activity that follows another activity in the network. B. Cost Loading: The allocation of the schedule of values for completing an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum. C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine the critical path of Project and when activities can be performed. D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float. E. Event: The starting or ending point of an activity. F. Float: The measure of leeway in starting and completing an activity. 1. Float time is not for the exclusive use or benefit of either Owner or Contractor, Montgomery County 013200 – Construction Progress Documentation Fire & EMS Headquarters Page 2 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date. 2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity. 3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date. G. Resource Loading: The allocation of labor and equipment necessary for completing an activity as scheduled. 1.3 INFORMATIONAL SUBMITTALS A. Format for Submittals: Submit required submittals in the following format: 1. PDF file. B. Startup construction schedule. 1. Submittal of cost-loaded startup construction schedule will not constitute approval of schedule of values for cost-loaded activities. C. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period. 1. Submit a working digital copy of schedule, labeled to comply with requirements for submittals. D. Construction Schedule Updating Reports: Submit with Applications for Payment. E. Daily Construction Reports: Submit at weekly intervals. F. Material Location Reports: Submit at monthly intervals. G. Site Condition Reports: Submit at time of discovery of differing conditions. H. Unusual Event Reports: Submit at time of unusual event. I. Qualification Data: For scheduling consultant. 1.4 QUALITY ASSURANCE A. Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting, with capability of producing CPM reports and diagrams within 24 hours of Architect's request. B. Prescheduling Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to the preliminary construction schedule and Contractor's Construction Schedule, including, but not limited to, the following: 1. Review software limitations and content and format for reports. 2. Verify availability of qualified personnel needed to develop and update schedule. 3. Discuss constraints. 4. Review delivery dates for Owner-furnished products. 5. Review submittal requirements and procedures. Montgomery County 013200 – Construction Progress Documentation Fire & EMS Headquarters Page 3 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 6. Review time required for review of submittals and resubmittals. 7. Review requirements for tests and inspections by independent testing and inspecting agencies. 8. Review time required for Project closeout and Owner startup procedures. 9. Review and finalize list of construction activities to be included in schedule. 10. Review procedures for updating schedule. 1.5 COORDINATION A. Coordinate Contractor's Construction Schedule with the schedule of values, submittal schedule, progress reports, payment requests, and other required schedules and reports. 1. Secure time commitments for performing critical elements of the Work from entities involved. 2. Coordinate each construction activity in the network with other activities, and schedule them in proper sequence. 1.6 CONTRACTOR'S CONSTRUCTION SCHEDULE A. Computer Scheduling Software: Prepare schedules using current version of a program that is capable of managing construction schedules. B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion. 1. Contract completion date to not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order. C. Activities: Treat each separate area as a separate numbered activity for each main element of the Work. Comply with the following: 1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Architect. 2. Temporary Facilities: Indicate start and completion dates for the following as applicable: a. Securing of approvals and permits required for performance of the Work. b. Temporary facilities. c. Construction of mock-ups, prototypes and samples. d. Owner interfaces and furnishing of items. e. Regulatory agency approvals. f. Punch list. 3. Procurement Activities: Include procurement process activities for any long lead- time items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery. 4. Submittal Review Time: Include review and resubmittal times indicated in Section 013300 "Submittal Procedures" in schedule. Coordinate submittal review times in Montgomery County 013200 – Construction Progress Documentation Fire & EMS Headquarters Page 4 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. Contractor's Construction Schedule with submittal schedule. 5. Startup and Testing Time: Include no fewer than 15 days for startup and testing. 6. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Architect's administrative procedures necessary for certification of Substantial Completion. 7. Punch List and Final Completion: Include not more than 30 days for completion of punch list items and Final Completion. D. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected. 1. Products Ordered in Advance: Include a separate activity for each product. Include delivery date indicated in Section 011000 "Summary." Delivery dates indicated stipulate the earliest possible delivery date. 2. Owner-Furnished Products: Include a separate activity for each product. Include delivery date indicated in Section 011000 "Summary." Delivery dates indicated stipulate the earliest possible delivery date. 3. Work Stages: Indicate important stages of construction for each major portion of the Work, including, but not limited to, the following: a. Subcontract awards. b. Submittals. c. Purchases. d. Mockups. e. Fabrication. f. Sample testing. g. Deliveries. h. Installation. i. Tests and inspections. j. Adjusting. k. Curing. l. Building flush-out. m. Startup and placement into final use and operation. n. Commissioning. 4. Construction Areas: Identify each major area of construction for each major portion of the Work. Indicate where each construction activity within a major area must be sequenced or integrated with other construction activities to provide for the following: a. Structural completion. b. Temporary enclosure and space conditioning. c. Permanent space enclosure. d. Completion of mechanical installation. e. Completion of electrical installation. f. Substantial Completion. E. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion. Montgomery County 013200 – Construction Progress Documentation Fire & EMS Headquarters Page 5 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. F. Upcoming Work Summary: Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update. Summarize the following issues: 1. Unresolved issues. 2. Unanswered Requests for Information. 3. Rejected or unreturned submittals. 4. Notations on returned submittals. 5. Pending modifications affecting the Work and the Contract Time. G. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting. 1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting. 2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations. 3. As the Work progresses, indicate Final Completion percentage for each activity. H. Recovery Schedule: When periodic update indicates the Work is 14 or more calendar days behind the current approved schedule, submit a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule. Indicate changes to working hours, working days, crew sizes, equipment required to achieve compliance, and date by which recovery will be accomplished. I. Distribution: Distribute copies of approved schedule to Architect, Owner, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility. 1. Post copies in Project meeting rooms and temporary field offices. 2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities. 1.7 STARTUP CONSTRUCTION SCHEDULE A. Gantt-Chart Schedule: Submit startup, horizontal, Gantt-chart-type construction schedule within seven days of date established for the Notice to Proceed. B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line. Outline significant construction activities for first 90 days of construction. Include skeleton diagram for the remainder of the Work and a cash requirement prediction based on indicated activities. 1.8 GANTT-CHART SCHEDULE REQUIREMENTS A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal, Gantt- Montgomery County 013200 – Construction Progress Documentation Fire & EMS Headquarters Page 6 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. chart-type, Contractor's Construction Schedule within 30 days of date established for the Notice to Proceed. 1. Base schedule on the startup construction schedule and additional information received since the start of Project. B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line. 1. For construction activities that require three months or longer to complete, indicate an estimated completion percentage in 10 percent increments within time bar. 1.9 REPORTS A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site: 1. List of subcontractors at Project site. 2. List of separate contractors at Project site. 3. Approximate count of personnel at Project site. 4. Equipment at Project site. 5. Material deliveries. 6. High and low temperatures and general weather conditions, including presence of rain or snow. 7. Testing and inspection. 8. Accidents. 9. Meetings and significant decisions. 10. Unusual events. 11. Stoppages, delays, shortages, and losses. 12. Meter readings and similar recordings. 13. Emergency procedures. 14. Orders and requests of authorities having jurisdiction. 15. Change Orders received and implemented. 16. Construction Change Directives received and implemented. 17. Services connected and disconnected. 18. Equipment or system tests and startups. 19. Partial completions and occupancies. 20. Substantial Completions authorized. B. Material Location Reports: At monthly intervals, prepare and submit a comprehensive list of materials delivered to and stored at Project site. List to be cumulative, showing materials previously reported plus items recently delivered. Include with list a statement of progress on and delivery dates for materials or items of equipment fabricated or stored away from Project site. Indicate the following categories for stored materials: 1. Material stored prior to previous report and remaining in storage. 2. Material stored prior to previous report and since removed from storage and installed. 3. Material stored following previous report and remaining in storage. Montgomery County 013200 – Construction Progress Documentation Fire & EMS Headquarters Page 7 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. C. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents. D. Unusual Event Reports: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, responses by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Owner in advance when these events are known or predictable. 1. Submit unusual event reports directly to Owner within one day of an occurrence. Distribute copies of report to parties affected by the occurrence. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 013200 Montgomery County 013300 – Submittal Procedures Fire & EMS Headquarters Page 1 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Submittal schedule requirements. 2. Administrative and procedural requirements for submittals. B. Related Requirements: 1. Section 012900 "Payment Procedures" for submitting Applications for Payment and the schedule of values. 2. Section 013100 "Project Management and Coordination" for submitting coordination drawings and subcontract list. 3. Section 013200 "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule. 4. Section 014000 "Quality Requirements" for submitting test and inspection reports, and schedule of tests and inspections. 5. Section 017700 "Closeout Procedures" for submitting closeout submittals and maintenance material submittals. 6. Section 017823 "Operation and Maintenance Data" for submitting operation and maintenance manuals. 7. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data. 8. Section 017900 "Demonstration and Training" for submitting video recordings of demonstration of equipment and training of Owner's personnel. 1.2 DEFINITIONS A. Action Submittals: Written and graphic information and physical samples that require Architect's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals." B. Informational Submittals: Written and graphic information and physical samples that do not require Architect's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals." 1.3 SUBMITTAL SCHEDULE A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted Montgomery County 013300 – Submittal Procedures Fire & EMS Headquarters Page 2 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. by Architect and additional time for handling and reviewing submittals required by those corrections. 1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule. 2. Initial Submittal Schedule: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication. 3. Final Submittal Schedule: Submit concurrently with the first complete submittal of Contractor's construction schedule. a. Submit revised submittal schedule as required to reflect changes in current status and timing for submittals. 4. Format: Arrange the following information in a tabular format: a. Scheduled date for first submittal. b. Specification Section number and title. c. Submittal Category: Action; informational. d. Name of subcontractor. e. Description of the Work covered. f. Scheduled date for Architect's final release or approval. g. Scheduled dates for purchasing. h. Scheduled date of fabrication. i. Scheduled dates for installation. j. Activity or event number. 1.4 SUBMITTAL FORMATS A. Submittal Information: Include the following information in each submittal: 1. Project name. 2. Date. 3. Name of Architect. 4. Name of Construction Manager. 5. Name of Contractor. 6. Name of firm or entity that prepared submittal. 7. Names of subcontractor, manufacturer, and supplier. 8. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier and alphanumeric suffix for resubmittals. 9. Category and type of submittal. 10. Submittal purpose and description. 11. Number and title of Specification Section, with paragraph number and generic name for each of multiple items. 12. Drawing number and detail references, as appropriate. 13. Indication of full or partial submittal. 14. Location(s) where product is to be installed, as appropriate. 15. Other necessary identification. Montgomery County 013300 – Submittal Procedures Fire & EMS Headquarters Page 3 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 16. Remarks. 17. Signature of transmitter. B. Options: Identify options requiring selection by Architect. C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Architect on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet. D. Paper Submittals: 1. Place a permanent label or title block on each submittal item for identification; include name of firm or entity that prepared submittal. 2. Provide a space approximately 6 by 8 inches on label or beside title block to record Contractor's review and approval markings and action taken by Architect. 3. Action Submittals: Submit three paper copies of each submittal unless otherwise indicated. Architect will return one copy. 4. Informational Submittals: Submit two paper copies of each submittal unless otherwise indicated. Architect will not return copies. 5. Additional Copies: Unless additional copies are required for final submittal, and unless Architect observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal. 6. Transmittal for Submittals: Assemble each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form acceptable to architect. E. Electronic Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number. F. Submittals Utilizing Web-Based Project Software: Prepare submittals as PDF files or other format indicated by Project management software. 1.5 SUBMITTAL PROCEDURES A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections. 1. Email: Prepare submittals as PDF package and transmit to Architect by sending via email. Include PDF transmittal form. Include information in email subject line as requested by Architect. a. Architect will return annotated file. Annotate and retain one copy of file as a digital Project Record Document file. 2. Web-Based Project Management Software: Prepare submittals in PDF form, and upload to web-based Project management software website. Enter required data in web-based software site to fully identify submittal. 3. Paper: Prepare submittals in paper form and deliver to Architect. B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Montgomery County 013300 – Submittal Procedures Fire & EMS Headquarters Page 4 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity. 2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule. 3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals. 4. Coordinate transmittal of submittals for related parts of the Work specified in different Sections, so processing will not be delayed because of need to review submittals concurrently for coordination. a. Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received. C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Architect's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals. 1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Architect will advise Contractor when a submittal being processed must be delayed for coordination. 2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal. 3. Resubmittal Review: Allow 14 days for review of each resubmittal. 4. Sequential Review: Where sequential review of submittals by Architect's consultants, Owner, or other parties is indicated, allow 21 days for initial review of each submittal. 5. Concurrent Consultant Review: Where the Contract Documents indicate that submittals may be transmitted simultaneously to Architect and to Architect's consultants, allow 14 days for review of each submittal. Submittal will be returned to Architect before being returned to Contractor. a. Submit one copy of submittal to concurrent reviewer in addition to specified number of copies to Architect. D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal. 1. Note date and content of previous submittal. 2. Note date and content of revision in label or title block, and clearly indicate extent of revision. 3. Resubmit submittals until they are marked with approval notation from Architect's action stamp. E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms. F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Architect's action stamp. Montgomery County 013300 – Submittal Procedures Fire & EMS Headquarters Page 5 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1.6 SUBMITTAL REQUIREMENTS A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment. 1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data. 2. Mark each copy of each submittal to show which products and options are applicable. 3. Include the following information, as applicable: a. Manufacturer's catalog cuts. b. Manufacturer's product specifications. c. Standard color charts. d. Statement of compliance with specified referenced standards. e. Testing by recognized testing agency. f. Application of testing agency labels and seals. g. Notation of coordination requirements. h. Availability and delivery time information. 4. For equipment, include the following in addition to the above, as applicable: a. Wiring diagrams that show factory-installed wiring. b. Printed performance curves. c. Operational range diagrams. d. Clearances required to other construction, if not indicated on accompanying Shop Drawings. 5. Submit Product Data before Shop Drawings, and before or concurrently with Samples. B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data. 1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable: a. Identification of products. b. Schedules. c. Compliance with specified standards. d. Notation of coordination requirements. e. Notation of dimensions established by field measurement. f. Relationship and attachment to adjoining construction clearly indicated. g. Seal and signature of professional engineer if specified. 2. Paper Sheet Size: Except for templates, patterns, and similar full-size Drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 30 by 42 inches. Montgomery County 013300 – Submittal Procedures Fire & EMS Headquarters Page 6 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. a. Three opaque (bond) copies of each submittal. Architect will return one copy. b. Three opaque copies of each submittal. Architect will retain two copies; remainder will be returned. C. Samples: Submit Samples for review of type, color, pattern, and texture for a check of these characteristics with other materials. 1. Transmit Samples that contain multiple, related components, such as accessories together in one submittal package. 2. Identification: Permanently attach label on unexposed side of Samples that includes the following: a. Project name and submittal number. b. Generic description of Sample. c. Product name and name of manufacturer. d. Sample source. e. Number and title of applicable Specification Section. f. Specification paragraph number and generic name of each item. 3. Email Transmittal: Provide PDF transmittal. Include digital image file illustrating Sample characteristics and identification information for record. 4. Web-Based Project Management Software: Prepare submittals in PDF form, and upload to web-based Project software website. Enter required data in web-based software site to fully identify submittal. 5. Paper Transmittal: Include paper transmittal, including complete submittal information indicated. 6. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set. a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use. b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor. 7. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units, showing the full range of colors, textures, and patterns available. a. Number of Samples: Submit one full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Architect will return submittal with options selected. 8. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples Montgomery County 013300 – Submittal Procedures Fire & EMS Headquarters Page 7 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection. a. Number of Samples: Submit three sets of Samples. Architect will retain two Sample sets; remainder will be returned. 1) Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated. 2) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations. D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form: 1. Type of product. Include unique identifier for each product indicated in the Contract Documents or assigned by Contractor if none is indicated. 2. Manufacturer and product name, and model number if applicable. 3. Number and name of room or space. 4. Location within room or space. E. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified. F. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal. G. Certificates: 1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide a notarized signature where indicated. 2. Installer Certificates: Submit written statements on manufacturer's letterhead, certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project. 3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead, certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required. 4. Material Certificates: Submit written statements on manufacturer's letterhead, certifying that material complies with requirements in the Contract Documents. 5. Product Certificates: Submit written statements on manufacturer's letterhead, Montgomery County 013300 – Submittal Procedures Fire & EMS Headquarters Page 8 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. certifying that product complies with requirements in the Contract Documents. 6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of AWS B2.1/B2.1M on AWS forms. Include names of firms and personnel certified. H. Test and Research Reports: 1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for substrate preparation and primers required. 2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents. 3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents. 4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents. 5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency. 6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information: a. Name of evaluation organization. b. Date of evaluation. c. Time period when report is in effect. d. Product and manufacturers' names. e. Description of product. f. Test procedures and results. g. Limitations of use. 1.7 DELEGATED DESIGN SERVICES A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated. 1. If criteria indicated are insufficient to perform services or certification required, submit a written request for additional information to Architect. Montgomery County 013300 – Submittal Procedures Fire & EMS Headquarters Page 9 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. B. Delegated Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF file of certificate, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional. 1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services. 1.8 CONTRACTOR'S REVIEW A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Architect. B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents. 1. Architect will not review submittals received from Contractor that do not have Contractor's review and approval. 1.9 ARCHITECT'S REVIEW A. Action Submittals: Architect will review each submittal, indicate corrections or revisions required, and return. 1. PDF Submittals: Architect will indicate, via markup on each submittal, the appropriate action. 2. Paper Submittals: Architect will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action. 3. Submittals by Web-Based Project Management Software: Architect will indicate, on Project management software website, the appropriate action. B. Informational Submittals: Architect will review each submittal and will not return it, or will return it if it does not comply with requirements. Architect will forward each submittal to appropriate party. C. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Architect. D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review. E. Architect will return without review, submittals received from sources other than Contractor. Montgomery County 013300 – Submittal Procedures Fire & EMS Headquarters Page 10 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 013300 Montgomery County 014000 – Quality Requirements Fire & EMS Headquarters Page 1 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for quality assurance and quality control. B. Testing and inspection services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements. 1. Specific quality-assurance and quality-control requirements for individual work results are specified in their respective Specification Sections. Requirements in individual Sections may also cover production of standard products. 2. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and quality-control procedures that facilitate compliance with the Contract Document requirements. 3. Requirements for Contractor to provide quality-assurance and quality-control services required by Architect, Owner, or authorities having jurisdiction are not limited by provisions of this Section. 1.2 DEFINITIONS A. Experienced: When used with an entity or individual, "experienced," unless otherwise further described, means having successfully completed a minimum of five previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction. B. Field Quality-Control Tests and Inspections: Tests and inspections that are performed on-site for installation of the Work and for completed Work. C. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, subcontractor, or sub-subcontractor, to perform a particular construction operation, including installation, erection, application, assembly, and similar operations. 1. Use of trade-specific terminology in referring to a Work result does not require that certain construction activities specified apply exclusively to specific trade(s). D. Mockups: Physical assemblies of portions of the Work constructed to establish the standard by which the Work will be judged. Mockups are not Samples. 1. Mockups are used for one or more of the following: a. Verify selections made under Sample submittals. b. Demonstrate aesthetic effects. c. Demonstrate the qualities of products and workmanship. d. Demonstrate successful installation of interfaces between components and Montgomery County 014000 – Quality Requirements Fire & EMS Headquarters Page 2 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. systems. e. Perform preconstruction testing to determine system performance. 2. Product Mockups: Mockups that may include multiple products, materials, or systems specified in a single Section. 3. In-Place Mockups: Mockups constructed on-site in their actual final location as part of permanent construction. E. Preconstruction Testing: Tests and inspections performed specifically for Project before products and materials are incorporated into the Work, to verify performance or compliance with specified criteria. Unless otherwise indicated, copies of reports of tests or inspections performed for other than the Project do not meet this definition. F. Product Tests: Tests and inspections that are performed by a nationally recognized testing laboratory (NRTL) in accordance with 29 CFR 1910.7, by a testing agency accredited in accordance with NIST's National Voluntary Laboratory Accreditation Program (NVLAP), or by a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with specified requirements. G. Source Quality-Control Tests and Inspections: Tests and inspections that are performed at the source (e.g., plant, mill, factory, or shop). H. Testing Agency: An entity engaged to perform specific tests, inspections, or both. The term "testing laboratory" has the same meaning as the term "testing agency." I. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work, to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements. J. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work, to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Contractor's quality- control services do not include contract administration activities performed by Architect. 1.3 DELEGATED DESIGN SERVICES A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated. 1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Architect. B. Delegated Design Services Statement: Submit a statement signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional, indicating that the products and systems are in compliance with performance and design criteria indicated. Include list of codes, loads, and other factors used in performing these services. Montgomery County 014000 – Quality Requirements Fire & EMS Headquarters Page 3 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1.4 CONFLICTING REQUIREMENTS A. Conflicting Standards and Other Requirements: If compliance with two or more standards or requirements is specified and the standards or requirements establish different or conflicting requirements for minimum quantities or quality levels, inform the Architect regarding the conflict and obtain clarification prior to proceeding with the Work. Refer conflicting requirements that are different, but apparently equal, to Architect for clarification before proceeding. B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified is the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding. 1.5 ACTION SUBMITTALS A. Mockup Shop Drawings: 1. Include plans, sections, elevations, and details, indicating materials and size of mockup construction. 2. Indicate manufacturer and model number of individual components. 3. Provide axonometric drawings for conditions difficult to illustrate in two dimensions. 1.6 INFORMATIONAL SUBMITTALS A. Contractor's Quality-Control Plan: For quality-assurance and quality-control activities and responsibilities. B. Qualification Data: For Contractor's quality-control personnel. C. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority. D. Schedule of Tests and Inspections: Prepare in tabular form and include the following: 1. Specification Section number and title. 2. Entity responsible for performing tests and inspections. 3. Description of test and inspection. 4. Identification of applicable standards. 5. Identification of test and inspection methods. 6. Number of tests and inspections required. 7. Time schedule or time span for tests and inspections. 8. Requirements for obtaining samples. 9. Unique characteristics of each quality-control service. E. Reports: Prepare and submit certified written reports and documents as specified. F. Permits, Licenses, and Certificates: For Owner's record, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, Montgomery County 014000 – Quality Requirements Fire & EMS Headquarters Page 4 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work. 1.7 CONTRACTOR'S QUALITY-CONTROL PLAN A. Quality-Control Plan, General: Submit quality-control plan within 10 days of Notice to Proceed, and not less than five days prior to preconstruction conference. Submit in format acceptable to Architect. Identify personnel, procedures, controls, instructions, tests, records, and forms to be used to carry out Contractor's quality-assurance and quality-control responsibilities and to coordinate Owner's quality-assurance and quality- control activities. Coordinate with Contractor's Construction Schedule. B. Quality-Control Personnel Qualifications: Engage qualified personnel trained and experienced in managing and executing quality-assurance and quality-control procedures similar in nature and extent to those required for Project. 1. Project quality-control manager may also serve as Project superintendent. C. Submittal Procedure: Describe procedures for ensuring compliance with requirements through review and management of submittal process. Indicate qualifications of personnel responsible for submittal review. D. Testing and Inspection: In quality-control plan, include a comprehensive schedule of Work requiring testing or inspection, including the following: 1. Contractor-performed tests and inspections, including subcontractor-performed tests and inspections. Include required tests and inspections and Contractor- elected tests and inspections. Distinguish source quality-control tests and inspections from field quality-control tests and inspections. 2. Special inspections required by authorities having jurisdiction and indicated on the Statement of Special Inspections. 3. Owner-performed tests and inspections indicated in the Contract Documents. E. Continuous Inspection of Workmanship: Describe process for continuous inspection during construction to identify and correct deficiencies in workmanship in addition to testing and inspection specified. Indicate types of corrective actions to be required to bring the Work into compliance with standards of workmanship established by Contract requirements and approved mockups. F. Monitoring and Documentation: Maintain testing and inspection reports, including log of approved and rejected results. Include Work Architect has indicated as nonconforming or defective. Indicate corrective actions taken to bring nonconforming Work into compliance with requirements. Comply with requirements of authorities having jurisdiction. 1.8 REPORTS AND DOCUMENTS A. Test and Inspection Reports: Prepare and submit certified written reports specified in other Sections. Include the following: 1. Date of issue. Montgomery County 014000 – Quality Requirements Fire & EMS Headquarters Page 5 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 2. Project title, owners bid request number, and architects project number. 3. Name, address, telephone number, and email address of testing agency. 4. Dates and locations of samples and tests or inspections. 5. Names of individuals making tests and inspections. 6. Description of the Work and test and inspection method. 7. Identification of product and Specification Section. 8. Complete test or inspection data. 9. Test and inspection results and an interpretation of test results. 10. Record of temperature and weather conditions at time of sample-taking and testing and inspection. 11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements. 12. Name and signature of laboratory inspector. 13. Recommendations on retesting and reinspecting. B. Manufacturer's Technical Representative's Field Reports: Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections. Include the following: 1. Name, address, telephone number, and email address of technical representative making report. 2. Statement on condition of substrates and their acceptability for installation of product. 3. Statement that products at Project site comply with requirements. 4. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken. 5. Results of operational and other tests and a statement of whether observed performance complies with requirements. 6. Statement of whether conditions, products, and installation will affect warranty. 7. Other required items indicated in individual Specification Sections. C. Factory-Authorized Service Representative's Reports: Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections. Include the following: 1. Name, address, telephone number, and email address of factory-authorized service representative making report. 2. Statement that equipment complies with requirements. 3. Results of operational and other tests and a statement of whether observed performance complies with requirements. 4. Statement of whether conditions, products, and installation will affect warranty. 5. Other required items indicated in individual Specification Sections. 1.9 QUALITY ASSURANCE A. Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification Sections specify additional requirements. B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. As Montgomery County 014000 – Quality Requirements Fire & EMS Headquarters Page 6 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. applicable, procure products from manufacturers able to meet qualification requirements, warranty requirements, and technical or factory-authorized service representative requirements. C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. D. Installer Qualifications: A firm or individual experienced in installing, erecting, applying, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance. E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that is similar in material, design, and extent to those indicated for this Project. F. Specialists: Certain Specification Sections require that specific construction activities be performed by entities who are recognized experts in those operations. Specialists will satisfy qualification requirements indicated and engage in the activities indicated. 1. Requirements of authorities having jurisdiction supersede requirements for specialists. G. Testing and Inspecting Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspection indicated, as documented in accordance with ASTM E329, and with additional qualifications specified in individual Sections; and, where required by authorities having jurisdiction, that is acceptable to authorities. H. Manufacturer's Technical Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project. I. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect, demonstrate, repair, and perform service on installations of manufacturer's products that are similar in material, design, and extent to those indicated for this Project. J. Preconstruction Testing: Where testing agency is indicated to perform preconstruction testing for compliance with specified requirements for performance and test methods, comply with the following: 1. Contractor's Responsibilities: a. Provide test specimens representative of proposed products and construction. b. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying the Work. c. Provide sizes and configurations of test assemblies, mockups, and laboratory mockups to adequately demonstrate capability of products to comply with performance requirements. d. Build site-assembled test assemblies and mockups, using installers who will perform same tasks for Project. Montgomery County 014000 – Quality Requirements Fire & EMS Headquarters Page 7 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. e. When testing is complete, remove test specimens, test assemblies, and mockups; do not reuse products on Project. 2. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to Architect, with copy to Contractor. Interpret tests and inspections, and state in each report whether tested and inspected Work complies with or deviates from the Contract Documents. K. Mockups: Before installing portions of the Work requiring mockups, build mockups for each form of construction and finish required to comply with the following requirements, using materials indicated for the completed Work: 1. Build mockups of size indicated. 2. Build mockups in location indicated or, if not indicated, as directed by Architect. 3. Notify Architect seven days in advance of dates and times when mockups will be constructed. 4. Employ supervisory personnel who will oversee mockup construction. Employ workers who will be employed to perform same tasks during the construction at Project. 5. Demonstrate the proposed range of aesthetic effects and workmanship. 6. Obtain Architect's approval of mockups before starting corresponding Work, fabrication, or construction. a. Allow seven days for initial review and each re-review of each mockup. 7. Promptly correct unsatisfactory conditions noted by Architect's preliminary review, to the satisfaction of the Architect, before completion of final mockup. 8. Approval of mockups by the Architect does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing. 9. Maintain mockups during construction in an undisturbed condition as a standard for judging the completed Work. 10. Demolish and remove mockups when directed unless otherwise indicated. 1.10 QUALITY CONTROL A. Owner Responsibilities: Where quality-control services are indicated as Owner's responsibility, Owner will engage a qualified testing agency to perform these services. 1. Owner will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspection they are engaged to perform. 2. Payment for these services will be made by owner. 3. Costs for retesting and reinspecting construction that replaces or is necessitated by Work that failed to comply with the Contract Documents will be charged to Contractor. B. Contractor Responsibilities: Tests and inspections not explicitly assigned to Owner are Contractor's responsibility. Perform additional quality-control activities, whether Montgomery County 014000 – Quality Requirements Fire & EMS Headquarters Page 8 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. specified or not, to verify and document that the Work complies with requirements. 1. Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not. 2. Engage a qualified testing agency to perform quality-control services. a. Contractor will not employ same entity engaged by Owner, unless agreed to in writing by Owner. 3. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspection will be performed. 4. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service. 5. Testing and inspection requested by Contractor and not required by the Contract Documents are Contractor's responsibility. 6. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct. C. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents. D. Testing Agency Responsibilities: Cooperate with Architect and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections. 1. Notify Architect and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services. 2. Determine the locations from which test samples will be taken and in which in- situ tests are conducted. 3. Conduct and interpret tests and inspections, and state in each report whether tested and inspected Work complies with or deviates from requirements. 4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor. 5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work. 6. Do not perform duties of Contractor. E. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Section 013300 "Submittal Procedures." F. Manufacturer's Technical Services: Where indicated, engage a manufacturer's technical representative to observe and inspect the Work. Manufacturer's technical representative's services include participation in preinstallation conferences, examination of substrates and conditions, verification of materials, observation of Installer activities, inspection of completed portions of the Work, and submittal of written reports. G. Contractor's Associated Requirements and Services: Cooperate with agencies and representatives performing required tests, inspections, and similar quality-control Montgomery County 014000 – Quality Requirements Fire & EMS Headquarters Page 9 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following: 1. Access to the Work. 2. Incidental labor and facilities necessary to facilitate tests and inspections. 3. Adequate quantities of representative samples of materials that require testing and inspection. Assist agency in obtaining samples. 4. Facilities for storage and field curing of test samples. 5. Delivery of samples to testing agencies. 6. Preliminary design mix proposed for use for material mixes that require control by testing agency. 7. Security and protection for samples and for testing and inspection equipment at Project site. H. Coordination: Coordinate sequence of activities to accommodate required quality- assurance and quality-control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspection. 1. Schedule times for tests, inspections, obtaining samples, and similar activities. I. Schedule of Tests and Inspections: Prepare a schedule of tests, inspections, and similar quality-control services required by the Contract Documents. Coordinate and submit concurrently with Contractor's Construction Schedule. Update and submit with each Application for Payment. 1. Schedule Contents: Include tests, inspections, and quality-control services, including Contractor- and Owner-retained services, commissioning activities, and other Project-required services paid for by other entities. 2. Distribution: Distribute schedule to Owner, Architect, testing agencies, and each party involved in performance of portions of the Work where tests and inspections are required. 1.11 SPECIAL TESTS AND INSPECTIONS A. Special Tests and Inspections: Owner will engage a qualified special inspector to conduct special tests and inspections required by authorities having jurisdiction as the responsibility of Owner, as indicated in the Statement of Special Inspections in the contract documents, and as follows: 1. Verifying that manufacturer maintains detailed fabrication and quality-control procedures, and reviewing the completeness and adequacy of those procedures to perform the Work. 2. Notifying Architect and Contractor promptly of irregularities and deficiencies observed in the Work during performance of its services. 3. Submitting a certified written report of each test, inspection, and similar quality- control service to Architect with copy to Contractor and to authorities having jurisdiction. 4. Submitting a final report of special tests and inspections at Substantial Completion, which includes a list of unresolved deficiencies. Montgomery County 014000 – Quality Requirements Fire & EMS Headquarters Page 10 of 10 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 5. Interpreting tests and inspections, and stating in each report whether tested and inspected Work complies with or deviates from the Contract Documents. 6. Retesting and reinspecting corrected Work. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 TEST AND INSPECTION LOG A. Test and Inspection Log: Prepare a record of tests and inspections. Include the following: 1. Date test or inspection was conducted. 2. Description of the Work tested or inspected. 3. Date test or inspection results were transmitted to Architect. 4. Identification of testing agency or special inspector conducting test or inspection. B. Maintain log at Project site. Post changes and revisions as they occur. Provide access to test and inspection log for Architect's and authorities' having jurisdiction reference during normal working hours. 1. Submit log at Project closeout as part of Project Record Documents. 3.2 REPAIR AND PROTECTION A. General: On completion of testing, inspection, sample-taking, and similar services, repair damaged construction and restore substrates and finishes. 1. Provide materials and comply with installation requirements specified in other Specification Sections or matching existing substrates and finishes. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible. Comply with the Contract Document requirements for cutting and patching in Section 017300 "Execution." B. Protect construction exposed by or for quality-control service activities. C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services. END OF SECTION 014000 Montgomery County 014200 - References Fire & EMS Headquarters Page 1 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 014200 - REFERENCES PART 1 - GENERAL 1.1 DEFINITIONS A. General: Basic Contract definitions are included in the Conditions of the Contract. B. "Approved": When used to convey Architect's action on Contractor's submittals, applications, and requests, "approved" is limited to Architect's duties and responsibilities as stated in the Conditions of the Contract. C. "Directed": A command or instruction by Architect. Other terms, including "requested," "authorized," "selected," "required," and "permitted," have the same meaning as "directed." D. "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms, including "shown," "noted," "scheduled," and "specified," have the same meaning as "indicated." E. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work. F. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations. G. "Install": Unload, temporarily store, unpack, assemble, erect, place, anchor, apply, work to dimension, finish, cure, protect, clean, and similar operations at Project site. H. "Provide": Furnish and install, complete and ready for the intended use. I. "Project Site": Space available for performing construction activities. The extent of Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built. 1.2 INDUSTRY STANDARDS A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference. B. Publication Dates: Comply with standards in effect as of date of the Contract Documents unless otherwise indicated. 1. For standards referenced by applicable building codes, comply with dates of standards as listed in building codes. C. Copies of Standards: Each entity engaged in construction on Project should be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents. 1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source. Montgomery County 014200 - References Fire & EMS Headquarters Page 2 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1.3 ABBREVIATIONS AND ACRONYMS A. Industry Organizations, List: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they are to mean the recognized name of the entities in the following list. Abbreviations and acronyms not included in this list are to mean the recognized name of the entities indicated in Gale's "Encyclopedia of Associations: National Organizations of the U.S." or in Columbia Books' "National Trade & Professional Associations of the United States." The information in this list is subject to change and is believed to be accurate as of the date of the Contract Documents. 1. AABC - Associated Air Balance Council; www.aabc.com. 2. AAMA - American Architectural Manufacturers Association; (see FGIA). 3. AAPFCO - Association of American Plant Food Control Officials; www.aapfco.org. 4. AASHTO - American Association of State Highway and Transportation Officials; www.transportation.org. 5. AATCC - American Association of Textile Chemists and Colorists; www.aatcc.org. 6. ABMA - American Bearing Manufacturers Association; www.americanbearings.org. 7. ABMA - American Boiler Manufacturers Association; www.abma.com. 8. ACI - American Concrete Institute; www.concrete.org. 9. ACP - American Clean Power; (Formerly: American Wind Energy Association); www.cleanpower.org. 10. ACPA - American Concrete Pipe Association; www.concretepipe.org. 11. AEIC - Association of Edison Illuminating Companies, Inc. (The); www.aeic.org. 12. AF&PA - American Forest & Paper Association; www.afandpa.org. 13. AGA - American Gas Association; www.aga.org. 14. AHAM - Association of Home Appliance Manufacturers; www.aham.org. 15. AHRI - Air-Conditioning, Heating, and Refrigeration Institute (The); www.ahrinet.org. 16. AI - Asphalt Institute; www.asphaltinstitute.org. 17. AIA - American Institute of Architects (The); www.aia.org. 18. AISC - American Institute of Steel Construction; www.aisc.org. 19. AISI - American Iron and Steel Institute; www.steel.org. 20. AITC - American Institute of Timber Construction; (see PLIB). 21. AMCA - Air Movement and Control Association International, Inc.; www.amca.org. 22. AMPP - Association for Materials Protection and Performance; www.ampp.org. 23. ANSI - American National Standards Institute; www.ansi.org. 24. AOSA/SCST - Association of Official Seed Analysts (The)/Society of Commercial Seed Technologists (The); www.analyzeseeds.com. 25. APA - APA - The Engineered Wood Association; www.apawood.org. 26. APA - Architectural Precast Association; www.archprecast.org. 27. API - American Petroleum Institute; www.api.org. 28. ARMA - Asphalt Roofing Manufacturers Association; www.asphaltroofing.org. 29. ASA - Acoustical Society of America; www.acousticalsociety.org. 30. ASCE - American Society of Civil Engineers; www.asce.org. 31. ASCE/SEI - American Society of Civil Engineers/Structural Engineering Institute; (see ASCE). Montgomery County 014200 - References Fire & EMS Headquarters Page 3 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 32. ASHRAE - American Society of Heating, Refrigerating and Air-Conditioning Engineers; www.ashrae.org. 33. ASME - ASME International; American Society of Mechanical Engineers (The); www.asme.org. 34. ASSE - ASSE International; (American Society of Sanitary Engineering); www.asse-plumbing.org. 35. ASSP - American Society of Safety Professionals; www.assp.org. 36. ASTM - ASTM International; www.astm.org. 37. ATIS - Alliance for Telecommunications Industry Solutions; www.atis.org. 38. AVIXA - Audiovisual and Integrated Experience Association; www.avixa.org. 39. AWI - Architectural Woodwork Institute; www.awinet.org. 40. AWMAC - Architectural Woodwork Manufacturers Association of Canada; www.awmac.com. 41. AWPA - American Wood Protection Association; www.awpa.com. 42. AWS - American Welding Society; www.aws.org. 43. AWWA - American Water Works Association; www.awwa.org. 44. BHMA - Builders Hardware Manufacturers Association; www.buildershardware.com. 45. BIA - Brick Industry Association (The); www.gobrick.com. 46. BICSI - BICSI, Inc.; www.bicsi.org. 47. BIFMA - Business and Institutional Furniture Manufacturer's Association; www.bifma.org. 48. BISSC - Baking Industry Sanitation Standards Committee; www.bissc.org. 49. BSI - British Standards Institution; www.bsigroup.com. 50. BWF - Badminton World Federation; www.bwfbadminton.com. 51. CARB - California Air Resources Board; www.arb.ca.gov. 52. CDA - Copper Development Association Inc.; www.copper.org. 53. CE - Conformite Europeenne (European Commission); www.ec.europa.eu/growth/single-market/ce-marking. 54. CEA - Canadian Electricity Association; www.electricity.ca. 55. CFFA - Chemical Fabrics and Film Association, Inc.; www.chemicalfabricsandfilm.com. 56. CFSEI - Cold-Formed Steel Engineers Institute; www.cfsei.org. 57. CGA - Compressed Gas Association; www.cganet.com. 58. CIMA - Cellulose Insulation Manufacturers Association; www.cellulose.org. 59. CISCA - Ceilings & Interior Systems Construction Association; www.cisca.org. 60. CISPI - Cast Iron Soil Pipe Institute; www.cispi.org. 61. CLFMI - Chain Link Fence Manufacturers Institute; www.chainlinkinfo.org. 62. CMHA - Concrete Masonry & Hardscape Association; (Formerly: National Concrete Masonry Association); www.masonryandhardscapes.org. 63. CPA - Composite Panel Association; www.compositepanel.org. 64. CRI - Carpet and Rug Institute (The); www.carpet-rug.org. 65. CRRC - Cool Roof Rating Council; www.coolroofs.org. 66. CRSI - Concrete Reinforcing Steel Institute; www.crsi.org. 67. CSA - CSA Group; www.csagroup.org. 68. CSI - Cast Stone Institute; www.caststone.org. 69. CSI - Construction Specifications Institute (The); www.csiresources.org. 70. CSSB - Cedar Shake & Shingle Bureau; www.cedarbureau.org. 71. CTA - Consumer Technology Association; www.cta.tech. 72. CTI - Cooling Technology Institute; www.coolingtechnology.org. 73. DASMA - Door and Access Systems Manufacturers Association; Montgomery County 014200 - References Fire & EMS Headquarters Page 4 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. www.dasma.com. 74. DHA - Decorative Hardwoods Association; www.decorativehardwoods.org. 75. DHI - Door and Hardware Institute; www.dhi.org. 76. ECIA - Electronic Components Industry Association; www.ecianow.org. 77. EIMA - EIFS Industry Members Association; www.eima.com. 78. EJMA - Expansion Joint Manufacturers Association, Inc.; www.ejma.org. 79. EOS/ESD - EOS/ESD Association, Inc.; Electrostatic Discharge Association; www.esda.org. 80. ESTA - Entertainment Services and Technology Association; www.esta.org. 81. EVO - Efficiency Valuation Organization; www.evo-world.org. 82. FCI - Fluid Controls Institute; www.fluidcontrolsinstitute.org. 83. FGIA - Fenestration and Glazing Industry Alliance; https://fgiaonline.org. 84. FIBA - Federation Internationale de Basketball; (The International Basketball Federation); www.fiba.com. 85. FIVB - Federation Internationale de Volleyball; (The International Volleyball Federation); www.fivb.org. 86. FM Approvals - FM Approvals LLC; www.fmapprovals.com. 87. FM Global - FM Global; www.fmglobal.com. 88. FRSA - Florida Roofing and Sheet Metal Contractors Association, Inc.; www.floridaroof.com. 89. FSA - Fluid Sealing Association; www.fluidsealing.com. 90. FSC - Forest Stewardship Council U.S.; www.fscus.org. 91. GA - Gypsum Association; www.gypsum.org. 92. GS - Green Seal; www.greenseal.org. 93. HI - Hydraulic Institute; www.pumps.org. 94. HMMA - Hollow Metal Manufacturers Association; (see NAAMM). 95. IAPSC - International Association of Professional Security Consultants; www.iapsc.org. 96. IAS - International Accreditation Service; www.iasonline.org. 97. ICC - International Code Council; www.iccsafe.org. 98. ICEA - Insulated Cable Engineers Association, Inc.; www.icea.net. 99. ICPA - International Cast Polymer Association (The); www.theicpa.com. 100. ICRI - International Concrete Repair Institute, Inc.; www.icri.org. 101. IEC - International Electrotechnical Commission; www.iec.ch. 102. IEEE SA - IEEE Standards Association; https://standards.ieee.org. 103. IES - Illuminating Engineering Society; www.ies.org. 104. IEST - Institute of Environmental Sciences and Technology; www.iest.org. 105. IGMA - Insulating Glass Manufacturers Alliance; (see FGIA). 106. IGSHPA - International Ground Source Heat Pump Association; www.igshpa.org. 107. ILI - Indiana Limestone Institute of America, Inc.; www.iliai.com. 108. Intertek - Intertek Group; www.intertek.com. 109. ISA - International Society of Automation (The); www.isa.org. 110. ISFA - International Surface Fabricators Association; www.isfanow.org. 111. ISO - International Organization for Standardization; www.iso.org. 112. ITU - International Telecommunication Union; www.itu.int. 113. KCMA - Kitchen Cabinet Manufacturers Association; www.kcma.org. 114. LPI - Lightning Protection Institute; www.lightning.org. 115. MBMA - Metal Building Manufacturers Association; www.mbma.com. 116. MCA - Metal Construction Association; www.metalconstruction.org. 117. MFMA - Maple Flooring Manufacturers Association, Inc.; www.maplefloor.org. 118. MFMA - Metal Framing Manufacturers Association, Inc.; Montgomery County 014200 - References Fire & EMS Headquarters Page 5 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. www.metalframingmfg.org. 119. MHI - Material Handling Industry; www.mhi.org. 120. MMPA - Moulding & Millwork Producers Association; www.wmmpa.com. 121. MPI - Master Painters Institute; www.paintinfo.com. 122. MSS - Manufacturers Standardization Society of The Valve and Fittings Industry, Inc.; www.msshq.org. 123. NAAMM - National Association of Architectural Metal Manufacturers; www.naamm.org. 124. NACE - NACE International; (National Association of Corrosion Engineers International); (see AMPP). 125. NADCA - National Air Duct Cleaners Association; www.nadca.com. 126. NAIMA - North American Insulation Manufacturers Association; www.insulationinstitute.org. 127. NALP - National Association of Landscape Professionals; www.landscapeprofessionals.org. 128. NBGQA - National Building Granite Quarries Association, Inc.; www.nbgqa.com. 129. NBI - New Buildings Institute; www.newbuildings.org. 130. NCAA - National Collegiate Athletic Association (The); www.ncaa.org. 131. NCMA - National Concrete Masonry Association; (see CMHA). 132. NEBB - National Environmental Balancing Bureau; www.nebb.org. 133. NECA - National Electrical Contractors Association; www.necanet.org. 134. NeLMA - Northeastern Lumber Manufacturers Association; www.nelma.org. 135. NEMA - National Electrical Manufacturers Association; www.nema.org. 136. NETA - InterNational Electrical Testing Association; www.netaworld.org. 137. NFHS - National Federation of State High School Associations; www.nfhs.org. 138. NFPA - National Fire Protection Association; www.nfpa.org. 139. NFPA - NFPA International; (see NFPA). 140. NFRC - National Fenestration Rating Council; www.nfrc.org. 141. NGA - National Glass Association; www.glass.org. 142. NHLA - National Hardwood Lumber Association; www.nhla.com. 143. NLGA - National Lumber Grades Authority; www.nlga.org. 144. NOFMA - National Oak Flooring Manufacturers Association; (see NWFA). 145. NOMMA - National Ornamental & Miscellaneous Metals Association; www.nomma.org. 146. NRCA - National Roofing Contractors Association; www.nrca.net. 147. NRMCA - National Ready Mixed Concrete Association; www.nrmca.org. 148. NSF - NSF International; www.nsf.org. 149. NSI - Natural Stone Institute; www.naturalstoneinstitute.org. 150. NSPE - National Society of Professional Engineers; www.nspe.org. 151. NSSGA - National Stone, Sand & Gravel Association; www.nssga.org. 152. NTMA - National Terrazzo & Mosaic Association, Inc. (The); www.ntma.com. 153. NWFA - National Wood Flooring Association; www.nwfa.org. 154. NWRA - National Waste & Recycling Association; www.wasterecycling.org. 155. PCI - Precast/Prestressed Concrete Institute; www.pci.org. 156. PDI - Plumbing & Drainage Institute; www.pdionline.org. 157. PLASA - PLASA; www.plasa.org. 158. PLIB - Pacific Lumber Inspection Bureau; www.plib.org. 159. PVCPA - Uni-Bell PVC Pipe Association; www.uni-bell.org. 160. RCSC - Research Council on Structural Connections; www.boltcouncil.org. 161. RFCI - Resilient Floor Covering Institute; www.rfci.com. 162. RIS - Redwood Inspection Service; (see WWPA). Montgomery County 014200 - References Fire & EMS Headquarters Page 6 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 163. SAE - SAE International; www.sae.org. 164. SCTE - Society of Cable Telecommunications Engineers; www.scte.org. 165. SDI - Steel Deck Institute; www.sdi.org. 166. SDI - Steel Door Institute; www.steeldoor.org. 167. SEFA - Scientific Equipment and Furniture Association (The); www.sefalabs.com. 168. SEI/ASCE - Structural Engineering Institute/American Society of Civil Engineers; (see ASCE). 169. SIA - Security Industry Association; www.securityindustry.org. 170. SJI - Steel Joist Institute; www.steeljoist.org. 171. SMA - Screen Manufacturers Association; www.smainfo.org. 172. SMACNA - Sheet Metal and Air Conditioning Contractors' National Association; www.smacna.org. 173. SMPTE - Society of Motion Picture and Television Engineers; www.smpte.org. 174. SPFA - Spray Polyurethane Foam Alliance; www.sprayfoam.org. 175. SPIB - Southern Pine Inspection Bureau; www.spib.org. 176. SPRI - Single Ply Roofing Industry; www.spri.org. 177. SRCC - Solar Rating & Certification Corporation; www.solar-rating.org. 178. SSINA - Specialty Steel Industry of North America; www.ssina.com. 179. SSPC - SSPC: The Society for Protective Coatings; (see AMPP). 180. STI/SPFA - Steel Tank Institute/Steel Plate Fabricators Association; www.steeltank.com. 181. SWI - Steel Window Institute; www.steelwindows.com. 182. SWPA - Submersible Wastewater Pump Association; www.swpa.org. 183. TCA - Tilt-Up Concrete Association; www.tilt-up.org. 184. TCNA - Tile Council of North America, Inc.; www.tcnatile.com. 185. TEMA - Tubular Exchanger Manufacturers Association, Inc.; www.kbcdco.tema.org. 186. TIA - Telecommunications Industry Association; www.tiaonline.org. 187. TMS - The Masonry Society; www.masonrysociety.org. 188. TPI - Truss Plate Institute; www.tpinst.org. 189. TPI - Turfgrass Producers International; www.turfgrasssod.org. 190. TRI - Tile Roofing Industry Alliance; www.tileroofing.org. 191. ULSE - UL Standards & Engagement Inc.; www.ulse.org. 192. UL - UL Solutions Inc.; www.ul.com. 193. USAV - USA Volleyball; www.usavolleyball.org. 194. USGBC - U.S. Green Building Council; www.usgbc.org. 195. USITT - United States Institute for Theatre Technology, Inc.; www.usitt.org. 196. WA - Wallcoverings Association; www.wallcoverings.org. 197. WCLIB - West Coast Lumber Inspection Bureau; (see PLIB). 198. WCMA - Window Covering Manufacturers Association; www.wcmanet.org. 199. WDMA - Window & Door Manufacturers Association; www.wdma.com. 200. WI - Woodwork Institute; www.woodworkinstitute.com. 201. WSRCA - Western States Roofing Contractors Association; www.wsrca.com. 202. WWPA - Western Wood Products Association; www.wwpa.org. B. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they are to mean the recognized name of the entities in the following list. This information is believed to be accurate as of the date of the Contract Documents. Montgomery County 014200 - References Fire & EMS Headquarters Page 7 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1. DIN - Deutsches Institut fur Normung e.V.; www.din.de. 2. IAPMO - International Association of Plumbing and Mechanical Officials; www.iapmo.org. 3. ICC - International Code Council; www.iccsafe.org. 4. ICC-ES - ICC Evaluation Service, LLC; www.icc-es.org. C. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they are to mean the recognized name of the entities in the following list. Information is subject to change and is up to date as of the date of the Contract Documents. 1. CPSC - U.S. Consumer Product Safety Commission; www.cpsc.gov. 2. DOC - U.S. Department of Commerce; www.commerce.gov. 3. DOD - U.S. Department of Defense; www.defense.gov. 4. DOE - U.S. Department of Energy; www.energy.gov. 5. DOJ - U.S. Department of Justice; www.ojp.usdoj.gov 6. DOS - U.S. Department of State; www.state.gov. 7. EPA - United States Environmental Protection Agency; www.epa.gov. 8. FAA - Federal Aviation Administration; www.faa.gov. 9. GPO - U.S. Government Publishing Office; www.gpo.gov. 10. GSA - U.S. General Services Administration; www.gsa.gov. 11. HUD - U.S. Department of Housing and Urban Development; www.hud.gov. 12. LBNL - Lawrence Berkeley National Laboratory; Energy Technologies Area; www.lbl.gov/. 13. NIST - National Institute of Standards and Technology; www.nist.gov. 14. OSHA - Occupational Safety & Health Administration; www.osha.gov. 15. TRB - Transportation Research Board; National Cooperative Highway Research Program; The National Academies; www.trb.org. 16. USACE - U.S. Army Corps of Engineers; www.usace.army.mil. 17. USDA - U.S. Department of Agriculture; Agriculture Research Service; U.S. Salinity Laboratory; www.ars.usda.gov. 18. USDA - U.S. Department of Agriculture; Rural Utilities Service; www.usda.gov. 19. USP - U.S. Pharmacopeial Convention; www.usp.org. 20. USPS - United States Postal Service; www.usps.com. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 014200 Montgomery County 015000 – Temporary Facilities and Controls Fire & EMS Headquarters Page 1 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities. 1.2 USE CHARGES A. Installation, removal, and use charges for temporary facilities to be included in the Contract Sum unless otherwise indicated. Allow other entities engaged in the Project to use temporary services and facilities without cost, including, but not limited to, Architect, testing agencies, and authorities having jurisdiction. B. Sewer Service: Pay sewer-service use charges for sewer usage by all entities for construction operations. C. Water Service: Pay water-service use charges for water used by all entities for construction operations. D. Electric Power Service: Pay electric-power-service use charges for electricity used by all entities for construction operations. 1.3 INFORMATIONAL SUBMITTALS A. Site Utilization Plan: Show temporary facilities, temporary utility lines and connections, staging areas, construction site entrances, vehicle circulation, and parking areas for construction personnel. B. Implementation and Termination Schedule: Within 15 days of date established for Notice to Proceed, submit schedule indicating implementation and termination dates of each temporary utility. C. Project Identification and Temporary Signs: Show fabrication and installation details, including plans, elevations, details, layouts, typestyles, graphic elements, and message content. D. Fire-Safety Program: Show compliance with requirements of NFPA 241 and authorities having jurisdiction. Indicate Contractor personnel responsible for management of fire- prevention program. E. Moisture- and Mold-Protection Plan: Describe procedures and controls for protecting materials and construction from water absorption and damage and mold. Describe delivery, handling, storage, installation, and protection provisions for materials subject to water absorption or water damage. 1. Indicate procedures for discarding water-damaged materials, protocols for mitigating water intrusion into completed Work, and requirements for replacing water-damaged Work. 2. Indicate sequencing of work that requires water, such as sprayed fire-resistive materials, plastering, and terrazzo grinding, and describe plans for dealing with Montgomery County 015000 – Temporary Facilities and Controls Fire & EMS Headquarters Page 2 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. water from these operations. Show procedures for verifying that wet construction has dried sufficiently to permit installation of finish materials. 3. Indicate methods to be used to avoid trapping water in finished work. F. Dust- and HVAC-Control Plan: Submit coordination drawing and narrative that indicates the dust- and HVAC-control measures proposed for use, proposed locations, and proposed time frame for their operation. Include the following: 1. Locations of dust-control partitions at each phase of work. 2. HVAC system isolation schematic drawing. 3. Location of proposed air-filtration system discharge. 4. Waste-handling procedures. 5. Other dust-control measures. 1.4 QUALITY ASSURANCE A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70. B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits. 1.5 PROJECT CONDITIONS A. Temporary Use of Permanent Facilities: Engage Installer of each permanent service to assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities. PART 2 - PRODUCTS 2.1 MATERIALS A. Chain-Link Fencing: Minimum 2-inch, 0.148-inch- thick, galvanized-steel, chain-link fabric fencing; minimum 6 feet high with galvanized-steel pipe posts; minimum 2-3/8- inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top rails. B. Portable Chain-Link Fencing: Minimum 2-inch, 0.148-inch- thick, galvanized-steel, chain-link fabric fencing; minimum 6 feet high with galvanized-steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1- 5/8-inch- OD top and bottom rails. Provide galvanized-steel bases for supporting posts. C. Polyethylene Sheet: Reinforced, fire-resistive sheet, 10-mil minimum thickness, with flame-spread rating of 15 or less in accordance with ASTM E84 and passing NFPA 701 Test Method 2. D. Dust-Control Adhesive-Surface Walk-Off Mats: Provide mats, minimum 36 by 60 inches. E. Insulation: Unfaced mineral-fiber blanket, manufactured from glass, slag wool, or rock wool; with maximum flame-spread and smoke-developed indexes of 25 and 50, Montgomery County 015000 – Temporary Facilities and Controls Fire & EMS Headquarters Page 3 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. respectively. 2.2 TEMPORARY FACILITIES A. Field Offices: 1. Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading. B. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations. 1. Store combustible materials apart from building. 2.3 EQUIPMENT A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures. B. HVAC Equipment: Unless Owner authorizes use of permanent HVAC system, provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control. 1. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units is prohibited. 2. Heating, Cooling, and Dehumidifying Units: Listed and labeled for type of fuel being consumed, by a qualified testing agency acceptable to authorities having jurisdiction, and marked for intended location and application. C. Air-Filtration Units: Primary and secondary HEPA-filter-equipped portable units with four-stage filtration. Provide single switch for emergency shutoff. Configure to run continuously. PART 3 - EXECUTION 3.1 INSTALLATION, GENERAL A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work. 1. Locate facilities to limit site disturbance as specified in Section 011000 "Summary." B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities. Montgomery County 015000 – Temporary Facilities and Controls Fire & EMS Headquarters Page 4 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 3.2 TEMPORARY UTILITY INSTALLATION A. General: Install temporary service or connect to existing service. 1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services. B. Sewers and Drainage: Provide temporary utilities to remove effluent lawfully. 1. Connect temporary sewers to municipal system as directed by authorities having jurisdiction. C. Water Service: 1. Install water service and distribution piping in sizes and pressures adequate for construction. 2. Connect to Owner's existing water service facilities. Clean and maintain water service facilities in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use. D. Sanitary Facilities: Provide temporary toilets, wash facilities, safety shower and eyewash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities. 1. Use of Permanent Toilets: Use of Owner's existing or new toilet facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use. E. Temporary Heating and Cooling: Provide temporary heating and cooling required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed. 1. Provide temporary dehumidification systems when required to reduce ambient and substrate moisture levels to level required to allow installation or application of finishes and their proper curing or drying. F. Electric Power Service: 1. Provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations. a. Install electric power service underground unless otherwise indicated. G. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions. Montgomery County 015000 – Temporary Facilities and Controls Fire & EMS Headquarters Page 5 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system. 3.3 SUPPORT FACILITIES INSTALLATION A. Traffic Controls: Comply with requirements of authorities having jurisdiction. 1. Protect existing site improvements to remain, including curbs, pavement, and utilities. 2. Maintain access for fire-fighting equipment and access to fire hydrants. B. Parking: Use designated areas of project site as parking areas for construction personnel. C. Storage and Staging: Use designated areas of Project site for storage and staging needs. D. Dewatering Facilities and Drains: Comply with requirements of authorities having jurisdiction. Maintain Project site, excavations, and construction free of water. 1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties or endanger permanent Work or temporary facilities. 2. Remove snow and ice as required to minimize accumulations. E. Project Signs: Provide Project signs as indicated. Unauthorized signs are not permitted. 1. Identification Signs: Provide Project identification signs as indicated on Drawings. 2. Temporary Signs: Provide other signs as indicated and as required to inform public and individuals seeking entrance to Project. a. Provide temporary, directional signs for construction personnel and visitors. 3. Maintain and touch up signs, so they are legible at all times. F. Waste Disposal Facilities: 1. Comply with requirements specified in Section 017419 "Construction Waste Management and Disposal." 2. Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction. Comply with progress cleaning requirements in Section 017300 "Execution." G. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel. 1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities. 3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, Montgomery County 015000 – Temporary Facilities and Controls Fire & EMS Headquarters Page 6 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities. 1. Where access to adjacent properties is required in order to affect protection of existing facilities, obtain written permission from adjacent property owner to access property for that purpose. B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects. 1. Comply with work restrictions specified in Section 011000 "Summary." C. Stormwater Control: Comply with requirements of authorities having jurisdiction. Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains. D. Tree and Plant Protection: 1. Install temporary fencing located as indicated or outside the drip line of trees to protect vegetation from damage from construction operations. Protect tree root systems from damage, flooding, and erosion. E. Pest Control: Engage pest-control service to recommend practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals, so Project will be free of pests and their residues at Substantial Completion. Perform control operations lawfully, using materials approved by authorities having jurisdiction. F. Site Enclosure Fence: Before construction operations begin, furnish and install site enclosure fence in a manner that will prevent people from easily entering site except by entrance gates. 1. Extent of Fence: As required to enclose entire Project site or portion determined sufficient to accommodate construction operations. 2. Maintain security by limiting number of keys and restricting distribution to authorized personnel. Furnish one set of keys to Owner. G. Security Enclosure and Lockup: Install temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security. Lock entrances at end of each workday. H. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting. I. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior. 1. Where heating or cooling is needed and permanent enclosure is incomplete, insulate temporary enclosures. Montgomery County 015000 – Temporary Facilities and Controls Fire & EMS Headquarters Page 7 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. J. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241; manage fire-prevention program. 1. Prohibit smoking in construction areas. Comply with additional limits on smoking specified in other Sections. 2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition in accordance with requirements of authorities having jurisdiction. 3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information. 3.5 MOISTURE AND MOLD CONTROL A. Moisture and Mold Protection: Protect stored materials and installed Work in accordance with Moisture and Mold Protection Plan. B. Exposed Construction Period: Before installation of weather barriers, when materials are subject to wetting and exposure and to airborne mold spores, protect as follows: 1. Protect porous materials from water damage. 2. Protect stored and installed material from flowing or standing water. 3. Keep porous and organic materials from coming into prolonged contact with concrete. 4. Remove standing water from decks. 5. Keep deck openings covered or dammed. C. Partially Enclosed Construction Period: After installation of weather barriers but before full enclosure and conditioning of building, when installed materials are still subject to infiltration of moisture and ambient mold spores, protect as follows: 1. Do not load or install drywall or other porous materials or components, or items with high organic content, into partially enclosed building. 2. Keep interior spaces reasonably clean and protected from water damage. 3. Periodically collect and remove waste containing cellulose or other organic matter. 4. Discard or replace water-damaged material. 5. Do not install material that is wet. 6. Discard and replace stored or installed material that begins to grow mold. 7. Perform work in a sequence that allows wet materials adequate time to dry before enclosing the material in gypsum board or other interior finishes. D. Controlled Construction Period: After completing and sealing of the building enclosure but prior to the full operation of permanent HVAC systems, maintain as follows: 1. Control moisture and humidity inside building by maintaining effective dry-in conditions. 2. Use temporary or permanent HVAC system to control humidity within ranges specified for installed and stored materials. Montgomery County 015000 – Temporary Facilities and Controls Fire & EMS Headquarters Page 8 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 3. Comply with manufacturer's written instructions for temperature, relative humidity, and exposure to water limits. a. Hygroscopic materials that may support mold growth, including wood and gypsum-based products, that become wet during the course of construction and remain wet for 48 hours are considered defective and require replacing. b. Measure moisture content of materials that have been exposed to moisture during construction operations or after installation. Record readings beginning at time of exposure and continuing daily for 48 hours. Identify materials containing moisture levels higher than allowed. Report findings in writing to Architect. c. Remove and replace materials that cannot be completely restored to their manufactured moisture level within 48 hours. 3.6 OPERATION, TERMINATION, AND REMOVAL A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses. B. Maintenance: Maintain facilities in good operating condition until removal. 1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage. C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion. D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired. 1. Materials and facilities that constitute temporary facilities are property of Contractor. Owner reserves right to take possession of Project identification signs. 2. At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period. Comply with final cleaning requirements specified in Section 017700 "Closeout Procedures." END OF SECTION 015000 Montgomery County 016000 – Product Requirements Fire & EMS Headquarters Page 1 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 016000 - PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. The Work of This Section Includes: Administrative and procedural requirements for selection of products for use in Project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; and comparable products. B. Related Requirements: 1. Section 011000 "Summary" for Contractor requirements related to Owner- furnished products. 2. Section 012100 "Allowances" for products selected under an allowance. 3. Section 012300 "Alternates" for products selected under an alternate. 4. Section 012500 "Substitution Procedures" for requests for substitutions. 5. Section 014200 "References" for applicable industry standards for products specified. 6. Section 017700 "Closeout Procedures" for submitting warranties. 1.2 DEFINITIONS A. Products: Items obtained for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent. 1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents. 2. New Products: Items that have not previously been incorporated into another project or facility. Salvaged items or items reused from other projects are not considered new products. Items that are manufactured or fabricated to include recycled content materials are considered new products unless otherwise indicated. 3. Comparable Product: Product by named manufacturer that is demonstrated and approved through the comparable product submittal process described in "Comparable Products" Article, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product. B. Basis-of-Design Product Specification: A specification in which a single manufacturer's product is named and accompanied by the words "basis-of-design product," including make or model number or other designation. Published attributes and characteristics of basis-of-design product establish salient characteristics of products. 1. Evaluating Comparable Products: In addition to the basis-of-design product Montgomery County 016000 – Product Requirements Fire & EMS Headquarters Page 2 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. description, product attributes and characteristics may be listed to establish the significant qualities related to type, function, in-service performance and physical properties, weight, dimension, durability, visual characteristics, and other special features and requirements for purposes of evaluating comparable products of additional manufacturers named in the specification. Manufacturer's published attributes and characteristics of basis-of-design product also establish salient characteristics of products for purposes of evaluating comparable products. C. Subject to Compliance with Requirements: Where the phrase "Subject to compliance with requirements" introduces a product selection procedure in an individual Specification Section, provide products qualified under the specified product procedure. In the event that a named product or product by a named manufacturer does not meet the other requirements of the specifications, select another named product or product from another named manufacturer that does meet the requirements of the specifications; submit a comparable product request or substitution request, if applicable. D. Comparable Product Request Submittal: An action submittal requesting consideration of a comparable product, including the following information: 1. Identification of basis-of-design product or fabrication or installation method to be replaced, including Specification Section number and title and Drawing numbers and titles. 2. Data indicating compliance with the requirements specified in "Comparable Products" Article. E. Basis-of-Design Product Specification Submittal: An action submittal complying with requirements in Section 013300 "Submittal Procedures." F. Substitution: Refer to Section 012500 "Substitution Procedures" for definition and limitations on substitutions. 1.3 QUALITY ASSURANCE A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, select product compatible with products previously selected, even if previously selected products were also options. 1. Resolution of Compatibility Disputes between Multiple Contractors: a. Contractors are responsible for providing products and construction methods compatible with products and construction methods of other contractors. b. If a dispute arises between the multiple contractors over concurrently selectable but incompatible products, Architect will determine which products will be used. B. Identification of Products: Except for required labels and operating data, do not attach or imprint manufacturer or product names or trademarks on exposed surfaces of products or equipment that will be exposed to view in occupied spaces or on the exterior. Montgomery County 016000 – Product Requirements Fire & EMS Headquarters Page 3 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1. Labels: Locate required product labels and stamps on a concealed surface, or, where required for observation following installation, on a visually accessible surface that is inconspicuous. 2. Equipment Nameplates: Provide a permanent nameplate on each item of service- or power-operated equipment. Locate on a visually accessible but inconspicuous surface. Include information essential for operation, including the following: a. Name of product and manufacturer. b. Model and serial number. c. Capacity. d. Speed. e. Ratings. 3. See individual identification Sections in Divisions 21, 22, 23, and 26 for additional equipment identification requirements. 1.4 COORDINATION A. Modify or adjust affected work as necessary to integrate work of approved comparable products and approved substitutions. 1.5 PRODUCT DELIVERY, STORAGE, AND HANDLING A. Deliver, store, and handle products, using means and methods that will prevent damage, deterioration, and loss, including theft and vandalism. Comply with manufacturer's written instructions. B. Delivery and Handling: 1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces. 2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses. 3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing. 4. Inspect products on delivery to determine compliance with the Contract Documents and that products are undamaged and properly protected. C. Storage: 1. Provide a secure location and enclosure at Project site for storage of materials and equipment. 2. Store products to allow for inspection and measurement of quantity or counting of units. 3. Store materials in a manner that will not endanger Project structure. 4. Store products that are subject to damage by the elements under cover in a weathertight enclosure above ground, with ventilation adequate to prevent Montgomery County 016000 – Product Requirements Fire & EMS Headquarters Page 4 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. condensation and with adequate protection from wind. 5. Protect foam plastic from exposure to sunlight, except to extent necessary for period of installation and concealment. 6. Comply with product manufacturer's written instructions for temperature, humidity, ventilation, and weather-protection requirements for storage. 7. Protect stored products from damage and liquids from freezing. 8. Provide a secure location and enclosure at Project site for storage of materials and equipment by Owner's construction forces. Coordinate location with Owner. 1.6 PRODUCT WARRANTIES A. Warranties specified in other Sections are to be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents. 1. Manufacturer's Warranty: Written standard warranty form furnished by individual manufacturer for a particular product and issued in the name of Owner or endorsed by manufacturer to Owner. 2. Special Warranty: Written warranty required by the Contract Documents to provide specific rights for Owner and issued in the name of Owner or endorsed by manufacturer to Owner. B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution. 1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed. 2. Specified Form: When specified forms are included in the Project Manual, prepare a written document, using indicated form properly executed. 3. See other Sections for specific content requirements and particular requirements for submitting special warranties. C. Submittal Time: Comply with requirements in Section 017700 "Closeout Procedures." PART 2 - PRODUCTS 2.1 PRODUCT SELECTION PROCEDURES A. General Product Requirements: Provide products that comply with the Contract Documents, are undamaged and, unless otherwise indicated, are new at time of installation. 1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect. 2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects. Montgomery County 016000 – Product Requirements Fire & EMS Headquarters Page 5 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 3. Owner reserves the right to limit selection to products with warranties meeting requirements of the Contract Documents. 4. Where products are accompanied by the term "as selected," Architect will make selection. 5. Descriptive, performance, and reference standard requirements in Specifications establish salient characteristics of products. 6. Or Equal: For products specified by name and accompanied by the term "or equal," "or approved equal," or "or approved," comply with requirements in "Comparable Products" Article to obtain approval for use of an unnamed product. a. Submit additional documentation required by Architect in order to establish equivalency of proposed products. Unless otherwise indicated, evaluation of "or equal" product status is by Architect, whose determination is final. B. Product Selection Procedures: 1. Sole Product: Where Specifications name a single manufacturer and product, provide the named product that complies with requirements. Comparable products or substitutions for Contractor's convenience will not be considered. a. Sole product may be indicated by the phrase "Subject to compliance with requirements, provide the following." 2. Sole Manufacturer/Source: Where Specifications name a single manufacturer or source, provide a product by the named manufacturer or source that complies with requirements. Comparable products or substitutions for Contractor's convenience will not be considered. a. Sole manufacturer/source may be indicated by the phrase "Subject to compliance with requirements, provide products by the following." 3. Limited List of Products: Where Specifications include a list of names of both manufacturers and products, provide one of the products listed that complies with requirements. Comparable products or substitutions for Contractor's convenience will be considered unless otherwise indicated. a. Limited list of products may be indicated by the phrase "Subject to compliance with requirements, provide one of the following." 4. Non-Limited List of Products: Where Specifications include a list of names of both available manufacturers and products, provide one of the products listed or an unnamed product that complies with requirements. a. Non-limited list of products is indicated by the phrase "Subject to compliance with requirements, available products that may be incorporated in the Work include, but are not limited to, the following." b. Provision of an unnamed product is not considered a substitution, if the product complies with requirements. 5. Limited List of Manufacturers: Where Specifications include a list of manufacturers' names, provide a product by one of the manufacturers listed that Montgomery County 016000 – Product Requirements Fire & EMS Headquarters Page 6 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. complies with requirements. Comparable products or substitutions for Contractor's convenience will be considered unless otherwise indicated. a. Limited list of manufacturers is indicated by the phrase "Subject to compliance with requirements, provide products by one of the following." 6. Non-Limited List of Manufacturers: Where Specifications include a list of available manufacturers, provide a product by one of the manufacturers listed or a product by an unnamed manufacturer that complies with requirements. a. Non-limited list of manufacturers is indicated by the phrase "Subject to compliance with requirements, available manufacturers whose products may be incorporated in the Work include, but are not limited to, the following." b. Provision of products of an unnamed manufacturer is not considered a substitution, if the product complies with requirements. 7. Basis-of-Design Product: Where Specifications name a product, or refer to a product indicated on Drawings, and include a list of manufacturers, provide the specified or indicated product or a comparable product by one of the other named manufacturers. Drawings and Specifications may additionally indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. Comply with requirements in "Comparable Products" Article for consideration of an unnamed product by one of the other named manufacturers. a. For approval of products by unnamed manufacturers, comply with requirements in Section 012500 "Substitution Procedures" for substitutions for convenience. C. Visual Matching Specification: Where Specifications require the phrase "match Architect's sample," provide a product that complies with requirements and matches Architect's sample. Architect's decision will be final on whether a proposed product matches. 1. If no product available within specified category matches and complies with other specified requirements, comply with requirements in Section 012500 "Substitution Procedures" for proposal of product. D. Visual Selection Specification: Where Specifications include the phrase "as selected by Architect from manufacturer's full range" or a similar phrase, select a product that complies with requirements. Architect will select color, gloss, pattern, density, or texture from manufacturer's product line that includes both standard and premium items. 2.2 COMPARABLE PRODUCTS A. Conditions for Consideration of Comparable Products: Architect will consider Contractor's request for comparable product when the following conditions are satisfied. If the following conditions are not satisfied, Architect may return requests without action, except to record noncompliance with the following requirements: Montgomery County 016000 – Product Requirements Fire & EMS Headquarters Page 7 of 7 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1. Evidence that proposed product does not require revisions to the Contract Documents, is consistent with the Contract Documents, will produce the indicated results, and is compatible with other portions of the Work. 2. Detailed comparison of significant qualities of proposed product with those of the named basis-of-design product. Significant product qualities include attributes such as type, function, in-service performance and physical properties, weight, dimension, durability, visual characteristics, and other specific features and requirements. 3. Evidence that proposed product provides specified warranty. 4. List of similar installations for completed projects, with project names and addresses and names and addresses of architects and owners, if requested. 5. Samples, if requested. B. Architect's Action on Comparable Products Submittal: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for a comparable product. Architect will notify Contractor of approval or rejection of proposed comparable product within 14 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later. 1. Architect's Approval of Submittal: Marked with approval notation from Architect's action stamp. See Section 013300 "Submittal Procedures." 2. Use product specified if Architect does not issue a decision on use of a comparable product request within time allocated. C. Submittal Requirements, Two-Step Process: Approval by Architect of Contractor's request for use of comparable product is not intended to satisfy other submittal requirements. Comply with specified submittal requirements. D. Submittal Requirements, Single-Step Process: When acceptable to Architect, incorporate specified submittal requirements of individual Specification Section in combined submittal for comparable products. Approval by Architect of Contractor's request for use of comparable product and of individual submittal requirements will also satisfy other submittal requirements. PART 3 - EXECUTION (Not Used) END OF SECTION 016000 Montgomery County 017300 - Execution Fire & EMS Headquarters Page 1 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 017300 - EXECUTION PART 1 - GENERAL 1.1 SUMMARY A. Section includes general administrative and procedural requirements governing execution of the Work, including, but not limited to, the following: 1. Construction layout. 2. Field engineering. 3. Installation. 4. Cutting and patching. 5. Progress cleaning. 6. Starting and adjusting. 7. Protection of installed construction. 8. Correction of the Work. B. Related Requirements: 1. Section 011000 "Summary" for coordination of Owner-furnished products and limits on use of Project site. 2. Section 013300 "Submittal Procedures" for submitting surveys. 3. Section 017700 "Closeout Procedures" for submitting final property survey with Project Record Documents, recording of Owner-accepted deviations from indicated lines and levels, replacing defective work, and final cleaning. 1.2 DEFINITIONS A. Cutting: Removal of in-place construction necessary to permit installation or performance of subsequent work. B. Patching: Fitting and repair work required to restore construction to original conditions after installation of subsequent work. 1.3 PREINSTALLATION MEETINGS A. Cutting and Patching Conference: Conduct conference at Project site. 1. Prior to commencing work requiring cutting and patching, review extent of cutting and patching anticipated and examine procedures for ensuring satisfactory result from cutting and patching work. Inform Architect of scheduled meeting. Require representatives of each entity directly concerned with cutting and patching to attend, including the following: a. Contractor's superintendent. b. Trade supervisor responsible for cutting operations. c. Trade supervisor(s) responsible for patching of each type of substrate. Montgomery County 017300 - Execution Fire & EMS Headquarters Page 2 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. d. Mechanical, electrical, and utilities subcontractors' supervisors, to the extent each trade is affected by cutting and patching operations. 2. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding. B. Layout Conference: Conduct conference at Project site. 1. Prior to establishing layout of new and existing perimeter and structural column grid(s), review building location requirements. Review benchmark, control point, and layout and dimension requirements. Inform Architect of scheduled meeting. Require representatives of each entity directly concerned with Project layout to attend, including the following: a. Contractor's superintendent. b. Professional surveyor esponsible for performing Project surveying and layout. c. Professional surveyor responsible for performing site survey serving as basis for Project design. 2. Review meanings and intent of dimensions, notes, terms, graphic symbols, and other layout information indicated on the Drawings. 3. Review requirements for including layouts on Shop Drawings and other submittals. 4. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding. 1.4 INFORMATIONAL SUBMITTALS A. Qualification Data: For land surveyor. B. Certified Surveys: Submit two copies signed by land surveyor. C. Certificates: Submit certificate signed by land surveyor, certifying that location and elevation of improvements comply with requirements. D. Cutting and Patching Plan: Submit plan describing procedures at least 10 days prior to the time cutting and patching will be performed. Include the following information: 1. Extent: Describe reason for and extent of each occurrence of cutting and patching. 2. Changes to In-Place Construction: Describe anticipated results. Include changes to structural elements and operating components as well as changes in building appearance and other significant visual elements. 3. Products: List products to be used for patching and firms or entities that will perform patching work. 4. Dates: Indicate when cutting and patching will be performed. 5. Utilities and Mechanical and Electrical Systems: List services and systems that cutting and patching procedures will disturb or affect. List services and systems that will be relocated and those that will be temporarily out of service. Indicate length of time permanent services and systems will be disrupted. a. Include description of provisions for temporary services and systems during Montgomery County 017300 - Execution Fire & EMS Headquarters Page 3 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. interruption of permanent services and systems. E. Landfill Receipts: Submit copy of receipts issued by a landfill facility, licensed to accept hazardous materials, for hazardous waste disposal. 1.5 CLOSEOUT SUBMITTALS A. Final Property Survey: Submit 2 copies showing the Work performed and record survey data. 1.6 QUALITY ASSURANCE A. Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing land-surveying services of the kind indicated. B. Professional Engineer Qualifications: See Section 014000 "Quality Requirements." C. Cutting and Patching: Comply with requirements for and limitations on cutting and patching of construction elements. 1. Structural Elements: When cutting and patching structural elements, or when encountering the need for cutting and patching of elements whose structural function is not known, notify Architect of locations and details of cutting and await directions from Architect before proceeding. Shore, brace, and support structural elements during cutting and patching. Do not cut and patch structural elements in a manner that could change their load-carrying capacity or increase deflection. 2. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety. Operational elements include the following: a. Primary operational systems and equipment. b. Fire separation assemblies. c. Air or smoke barriers. d. Fire-suppression systems. e. Plumbing piping systems. f. Mechanical systems piping and ducts. g. Control systems. h. Communication systems. i. Fire-detection and -alarm systems. j. Conveying systems. k. Electrical wiring systems. l. Operating systems of special construction. 3. Other Construction Elements: Do not cut and patch other construction elements or components in a manner that could change their load-carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance or decreased operational life or safety. Other construction elements include but are not limited to the following: Montgomery County 017300 - Execution Fire & EMS Headquarters Page 4 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. a. Water, moisture, or vapor barriers. b. Membranes and flashings. c. Equipment supports. d. Piping, ductwork, vessels, and equipment. e. Noise- and vibration-control elements and systems. 4. Visual Elements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch exposed construction in a manner that would, in Architect's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner. D. Manufacturer's Installation Instructions: Obtain and maintain on-site manufacturer's written recommendations and instructions for installation of specified products and equipment. PART 2 - PRODUCTS 2.1 MATERIALS A. Comply with requirements specified in other Sections. 1. For projects requiring compliance with sustainable design and construction practices and procedures, use products for patching that comply with sustainable design requirements. B. In-Place Materials: Use materials for patching identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible. 1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to Architect for the visual and functional performance of in-place materials. Use materials that are not considered hazardous. C. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces. PART 3 - EXECUTION 3.1 EXAMINATION A. Existing Conditions: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities, mechanical and electrical systems, and other construction affecting the Work. Montgomery County 017300 - Execution Fire & EMS Headquarters Page 5 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1. Before construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer, gas service piping, and water-service piping; underground electrical services; and other utilities. 2. Furnish location data for work related to Project that must be performed by public utilities serving Project site. B. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations. 1. Examine roughing-in for mechanical and electrical systems to verify actual locations of connections before equipment and fixture installation. 2. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed. 3. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers. C. Written Report: Where a written report listing conditions detrimental to performance of the Work is required by other Sections, include the following: 1. Description of the Work, including Specification Section number and paragraph, and Drawing sheet number and detail, where applicable. 2. List of detrimental conditions, including substrates. 3. List of unacceptable installation tolerances. 4. Recommended corrections. D. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions. 3.2 PREPARATION A. Existing Utility Information: Furnish information to local utility and Owner that isnecessary to adjust, move, or relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located in or affected by construction. Coordinate with authorities having jurisdiction. B. Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work. C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings. D. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to Architect in accordance with requirements in Section 013100 "Project Management and Coordination." Montgomery County 017300 - Execution Fire & EMS Headquarters Page 6 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 3.3 CONSTRUCTION LAYOUT A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks and existing conditions. If discrepancies are discovered, notify Architect promptly. B. Engage a land surveyor experienced in laying out the Work, using the following accepted surveying practices: 1. Establish benchmarks and control points to set lines for construction and elsewhere as needed to locate each element of Project. 2. Establish limits on use of Project site. 3. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions. 4. Inform installers of lines and levels to which they must comply. 5. Check the location, level and plumb, of every major element as the Work progresses. 6. Notify Architect when deviations from required lines exceed allowable tolerances. 7. Close site surveys with an error of closure equal to or less than the standard established by authorities having jurisdiction. C. Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and rim and invert elevations. D. Building Lines and Levels: Locate and lay out control lines and levels for structures, building foundations, column grids, and floor levels, including those required for mechanical and electrical work. Transfer survey markings and elevations for use with control lines and levels. Level foundations and piers from two or more locations. E. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by Architect. 3.4 FIELD ENGINEERING A. Identification: Owner will identify existing benchmarks, control points, and property corners. B. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations. 1. Do not change or relocate existing benchmarks or control points without prior written approval of Architect. Report lost or destroyed permanent benchmarks or control points promptly. Report the need to relocate permanent benchmarks or control points to Architect before proceeding. 2. Replace lost or destroyed permanent benchmarks and control points promptly. Base replacements on the original survey control points. C. Benchmarks: Establish and maintain a minimum of two permanent benchmarks on Project site, referenced to data established by survey control points. Comply with authorities having jurisdiction for type and size of benchmark. Montgomery County 017300 - Execution Fire & EMS Headquarters Page 7 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1. Record benchmark locations, with horizontal and vertical data, on Project Record Documents. 2. Where the actual location or elevation of layout points cannot be marked, provide temporary reference points sufficient to locate the Work. 3. Remove temporary reference points when no longer needed. Restore marked construction to its original condition. D. Certified Survey: On completion of major site improvements and other work requiring field-engineering services, prepare a certified survey showing dimensions, locations, angles, and elevations of construction and sitework. E. Final Property Survey: Engage a land surveyor to prepare a final property survey showing significant features (real property) for Project. Include on the survey a certification, signed by land surveyor, that principal metes, bounds, lines, and levels of Project are accurately positioned as shown on the survey. 1. Show boundary lines, monuments, streets, site improvements and utilities, existing improvements and significant vegetation, adjoining properties, acreage, grade contours, and the distance and bearing from a site corner to a legal point. 2. Recording: At Substantial Completion, have the final property survey recorded by or with authorities having jurisdiction as the official "property survey." 3.5 INSTALLATION A. Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated. 1. Make vertical work plumb, and make horizontal work level. 2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement. 3. Conceal pipes, ducts, and wiring in finished areas unless otherwise indicated. 4. Maintain minimum headroom clearance of 96 inches in occupied spaces and 90 inches in unoccupied spaces, unless otherwise indicated on Drawings. B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated. C. Install products at the time and under conditions that will ensure satisfactory results as judged by Architect. Maintain conditions required for product performance until Substantial Completion. D. Conduct construction operations, so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy of type expected for Project. E. Sequence the Work and allow adequate clearances to accommodate movement of construction items on-site and placement in permanent locations. F. Tools and Equipment: Select tools or equipment that minimize production of excessive noise levels. G. Templates: Obtain and distribute to the parties involved templates for Work specified to be factory prepared and field installed. Check Shop Drawings of other portions of the Work to confirm that adequate provisions are made for locating and installing products to comply with indicated requirements. H. Attachment: Provide blocking and attachment plates and anchors and fasteners of Montgomery County 017300 - Execution Fire & EMS Headquarters Page 8 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. adequate size and number to securely anchor each component in place, accurately located and aligned with other portions of the Work. Where size and type of attachments are not indicated, verify size and type required for load conditions with manufacturer. 1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Architect. 2. Allow for building movement, including thermal expansion and contraction. 3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation. I. Joints: Make joints of uniform width. Where joint locations in exposed Work are not indicated, arrange joints for the best visual effect, as judged by Architect. Fit exposed connections together to form hairline joints. 3.6 CUTTING AND PATCHING A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay. 1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition. B. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during installation or cutting and patching operations, by methods and with materials so as not to void existing warranties. C. Temporary Support: Provide temporary support of Work to be cut. D. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations. E. Adjacent Occupied Areas: Where interference with use of adjoining areas or interruption of free passage to adjoining areas is unavoidable, coordinate cutting and patching in accordance with requirements in Section 011000 "Summary." F. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations. 1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots neatly to minimum size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use. 2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces. 3. Concrete or Masonry: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill. 4. Excavating and Backfilling: Comply with requirements in applicable Sections Montgomery County 017300 - Execution Fire & EMS Headquarters Page 9 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. where required by cutting and patching operations. 5. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting. 6. Proceed with patching after construction operations requiring cutting are complete. G. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as practicable, as judged by Architect. Provide materials and comply with installation requirements specified in other Sections, where applicable. 1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate physical integrity of installation. 2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing. a. Clean piping, conduit, and similar features before applying paint or other finishing materials. b. Restore damaged pipe covering to its original condition. 3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance. a. Where patching occurs in a painted surface, prepare substrate and apply primer and intermediate paint coats appropriate for substrate over the patch, and apply final paint coat over entire unbroken surface containing the patch, corner to corner of wall and edge to edge of ceiling. Provide additional coats until patch blends with adjacent surfaces. 4. Ceilings: Patch, repair, or rehang in-place ceilings as necessary to provide an even-plane surface of uniform appearance. 5. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition and ensures thermal and moisture integrity of building enclosure. H. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces. 3.7 PROGRESS CLEANING A. Clean Project site and work areas daily, including common areas. Enforce requirements strictly. Dispose of materials lawfully. 1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris. Montgomery County 017300 - Execution Fire & EMS Headquarters Page 10 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 2. Do not hold waste materials more than seven days during normal weather or three days if the temperature is expected to rise above 80 deg F. 3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, in accordance with regulations. a. Use containers intended for holding waste materials of type to be stored. B. Site: Maintain Project site free of waste materials and debris. C. Work Areas: Clean areas where Work is in progress to the level of cleanliness necessary for proper execution of the Work. 1. Remove liquid spills promptly. 2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate. D. Installed Work: Keep installed work clean. Clean installed surfaces in accordance with written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces. E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space. F. Exposed Surfaces: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion. G. Waste Disposal: Do not bury or burn waste materials on-site. Do not wash waste materials down sewers or into waterways. Comply with waste disposal requirements in Section 017419 "Construction Waste Management and Disposal." H. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion. I. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects. J. Limiting Exposures: Supervise construction operations to ensure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period. 3.8 STARTING AND ADJUSTING A. Coordinate startup and adjusting of equipment and operating components with requirements in Section 019113 "General Commissioning Requirements." B. Start equipment and operating components to confirm proper operation. Remove malfunctioning units, replace with new units, and retest. C. Adjust equipment for proper operation. Adjust operating components for proper operation without binding. D. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment. E. Manufacturer's Field Service: Comply with qualification requirements in Section 014000 "Quality Requirements." Montgomery County 017300 - Execution Fire & EMS Headquarters Page 11 of 11 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 3.9 PROTECTION OF INSTALLED CONSTRUCTION A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion. B. Protection of Existing Items: Provide protection and ensure that existing items to remain undisturbed by construction are maintained in condition that existed at commencement of the Work. C. Comply with manufacturer's written instructions for temperature and relative humidity. 3.10 CORRECTION OF THE WORK A. Repair or remove and replace damaged, defective, or nonconforming Work. Restore damaged substrates and finishes. 1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. B. Repair Work previously completed and subsequently damaged during construction period. Repair to like-new condition. C. Restore permanent facilities used during construction to their specified condition. D. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair. E. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired. F. Remove and replace chipped, scratched, and broken glass or reflective surfaces. END OF SECTION 017300 Montgomery County 017419 – Construction Waste Management and Disposal Fire & EMS Headquarters Page 1 of 2 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL 1.1 SUMMARY A. The Work of this Section includes administrative and procedural requirements for the following: 1. Salvaging nonhazardous demolition waste. 2. Disposing of nonhazardous demolition and construction waste. 1.2 DEFINITIONS A. CMU: Concrete masonry units. B. Construction Waste: Building, structure, and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging. C. Demolition Waste: Building, structure, and site improvement materials resulting from demolition operations. D. Disposal: Removal of demolition or construction waste and subsequent salvage, sale, recycling, or deposit in landfill, incinerator acceptable to authorities having jurisdiction, or designated spoil areas on Owner's property. E. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse. F. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility. G. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work. 1.3 MATERIALS OWNERSHIP A. Unless otherwise indicated, demolition and construction waste becomes property of Contractor. B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner. 1. Carefully salvage in a manner to prevent damage and promptly return to Owner. 1.4 INFORMATIONAL SUBMITTALS A. Qualification Statements: For refrigerant recovery technician. B. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician responsible for recovering refrigerant, stating that all refrigerant that was present was Montgomery County 017419 – Construction Waste Management and Disposal Fire & EMS Headquarters Page 2 of 2 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. recovered and that recovery was performed in accordance with EPA regulations. Include name and address of technician and date refrigerant was recovered. 1.5 QUALITY ASSURANCE A. Refrigerant Recovery Technician Qualifications: 1. Universal, certified by EPA-approved certification program. B. Regulatory Requirements: Comply with transportation and disposal regulations of authorities having jurisdiction. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 SALVAGING DEMOLITION WASTE A. Salvaged Items for Reuse in the Work: Handle as follows: 1. Clean salvaged items. 2. Pack or crate items after cleaning. Identify contents of containers with label indicating elements, date of removal, quantity, and location where removed. 3. Store items in a secure area until installation. 4. Protect items from damage during transport and storage. 5. Install salvaged items to comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make items functional for use indicated. 3.2 DISPOSAL OF WASTE A. Except for items or materials to be salvaged, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction. 1. Unless otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site. 2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas. B. Burning: 1. Do not burn waste materials. END OF SECTION 017419 Montgomery County 017700 – Closeout Procedures Fire & EMS Headquarters Page 1 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 017700 - CLOSEOUT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for Contract closeout, including, but not limited to, the following: 1. Substantial Completion procedures. 2. Final Completion procedures. 3. List of incomplete items. 4. Submittal of Project warranties. 5. Final cleaning. B. Related Requirements: 1. Section 012900 "Payment Procedures" for requirements for Applications for Payment for Substantial Completion and Final Completion. 2. Section 017823 "Operation and Maintenance Data" for additional operation and maintenance manual requirements. 3. Section 017839 "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data. 4. Section 017900 "Demonstration and Training" for requirements to train Owner's maintenance personnel to adjust, operate, and maintain products, equipment, and systems. 1.2 DEFINITIONS A. List of Incomplete Items: Contractor-prepared list of items to be completed or corrected, prepared for the Architect's use prior to Architect's inspection, to determine if the Work is substantially complete. 1.3 ACTION SUBMITTALS A. Product Data: For each type of cleaning agent. B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion. C. Certified List of Incomplete Items: Final submittal at Final Completion. 1.4 CLOSEOUT SUBMITTALS A. Certificates of Release: From authorities having jurisdiction. B. Certificate of Insurance: For continuing coverage. C. Field Report: For pest-control inspection. Montgomery County 017700 – Closeout Procedures Fire & EMS Headquarters Page 2 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1.5 MAINTENANCE MATERIAL SUBMITTALS A. Schedule of Maintenance Material Items: For maintenance material submittal items required by other Sections. 1.6 SUBSTANTIAL COMPLETION PROCEDURES A. Contractor's List of Incomplete Items: Prepare and submit a list of items to be completed and corrected (Contractor's "punch list"), indicating the value of each item on the list and reasons why the Work is incomplete. B. Submittals Prior to Substantial Completion: Complete the following a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request. 1. Certificates of Release: Obtain and submit releases from authorities having jurisdiction, permitting Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases. 2. Submit closeout submittals specified in other Division 01 Sections, including Project Record Documents, operation and maintenance manuals, damage or settlement surveys, property surveys, and similar final record information. 3. Submit closeout submittals specified in individual Sections, including specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents. 4. Submit maintenance material submittals specified in individual Sections, including tools, spare parts, extra materials, and similar items, and deliver to location designated by Owner. Label with manufacturer's name and model number. a. Schedule of Maintenance Material Items: Prepare and submit schedule of maintenance material submittal items, including name and quantity of each item and name and number of related Specification Section. Obtain Owner's signature for receipt of submittals. 5. Submit testing, adjusting, and balancing records. 6. Submit changeover information related to Owner's occupancy, use, operation, and maintenance. C. Procedures Prior to Substantial Completion: Complete the following a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request. 1. Advise Owner of pending insurance changeover requirements. 2. Make final changeover of permanent locks and deliver keys to Owner. Advise Owner's personnel of changeover in security provisions. 3. Complete startup and testing of systems and equipment. 4. Perform preventive maintenance on equipment used prior to Substantial Completion. 5. Instruct Owner's personnel in operation, adjustment, and maintenance of products, equipment, and systems. Submit demonstration and training video Montgomery County 017700 – Closeout Procedures Fire & EMS Headquarters Page 3 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. recordings specified in Section 017900 "Demonstration and Training." 6. Advise Owner of changeover in utility services. 7. Participate with Owner in conducting inspection and walkthrough with local emergency responders. 8. Terminate and remove temporary facilities from Project site, along with mockups, construction tools, and similar elements. 9. Complete final cleaning requirements. 10. Touch up paint and otherwise repair and restore marred exposed finishes to eliminate visual defects. D. Inspection: Submit a written request for inspection to determine Substantial Completion a minimum of 10 days prior to date the Work will be completed and ready for final inspection and tests. On receipt of request, Architect will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Architect, that must be completed or corrected before certificate will be issued. 1. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected. 2. Results of completed inspection will form the basis of requirements for Final Completion. 1.7 FINAL COMPLETION PROCEDURES A. Submittals Prior to Final Completion: Before requesting final inspection for determining Final Completion, complete the following: 1. Submit a final Application for Payment in accordance with Section 012900 "Payment Procedures." 2. Certified List of Incomplete Items: Submit certified copy of Architect's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Architect. Certified copy of the list will state that each item has been completed or otherwise resolved for acceptance. 3. Certificate of Insurance: Submit evidence of final, continuing insurance coverage complying with insurance requirements. 4. Submit pest-control final inspection report. B. Inspection: Submit a written request for final inspection to determine acceptance a minimum of 10 days prior to date the Work will be completed and ready for final inspection and tests. On receipt of request, Architect will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued. 1. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected. Montgomery County 017700 – Closeout Procedures Fire & EMS Headquarters Page 4 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1.8 LIST OF INCOMPLETE ITEMS A. Organization of List: Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction. 1. Organize list of spaces in sequential order, listed by room and room number. 2. Organize items applying to each space by major element, including categories for ceilings, individual walls, floors, equipment, and building systems. 3. Include the following information at the top of each page: a. Project name. b. Date. c. Name of Architect. d. Name of Contractor. e. Page number. 4. Submit list of incomplete items in the following format: a. MS Excel Electronic File: Architect will return annotated file, or b. Web-Based Project Software Upload: Utilize software feature for creating and updating list of incomplete items (punch list). 1.9 SUBMITTAL OF PROJECT WARRANTIES A. Time of Submittal: Submit written warranties on request of Architect for designated portions of the Work where warranties are indicated to commence on dates other than date of Substantial Completion, or when delay in submittal of warranties might limit Owner's rights under warranty. B. Organize warranty documents into an orderly sequence based on the table of contents of Project Manual. C. Warranty Electronic File: Provide warranties and bonds in PDF format. Assemble complete warranty and bond submittal package into a single electronic PDF file with bookmarks enabling navigation to each item. Provide bookmarked table of contents at beginning of document. 1. Submit on digital media acceptable to Owner. D. Provide additional copies of each warranty to include in operation and maintenance manuals. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 FINAL CLEANING A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to Montgomery County 017700 – Closeout Procedures Fire & EMS Headquarters Page 5 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. comply with local laws and ordinances and Federal and local environmental and antipollution regulations. B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions. 1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a designated portion of Project: a. Clean Project site of rubbish, waste material, litter, and other foreign substances. b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits. c. Rake grounds that are not planted, mulched, or paved to a smooth, even- textured surface. d. Remove tools, construction equipment, machinery, and surplus material from Project site. e. Remove snow and ice to provide safe access to building. f. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition. g. Remove debris and surface dust from limited-access spaces, including roofs, plenums, shafts, trenches, equipment vaults, manholes, attics, and similar spaces. h. Clean flooring, removing debris, dirt, and staining; clean in accordance with manufacturer's instructions. i. Vacuum and mop concrete. j. Vacuum carpet and similar soft surfaces, removing debris and excess nap; clean in accordance with manufacturer's instructions if visible soil or stains remain. k. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing compounds and other noticeable, vision- obscuring materials. Polish mirrors and glass, taking care not to scratch surfaces. l. Remove labels that are not permanent. m. Wipe surfaces of mechanical and electrical equipment and similar equipment. Remove excess lubrication, paint and mortar droppings, and other foreign substances. n. Clean plumbing fixtures to a sanitary condition, free of stains, including stains resulting from water exposure. o. Replace disposable air filters and clean permanent air filters. Clean exposed surfaces of diffusers, registers, and grills. p. Clean ducts, blowers, and coils if units were operated without filters during construction or that display contamination with particulate matter on inspection. 1) Clean HVAC system in compliance with NADCA ACR. Provide written report on completion of cleaning. Montgomery County 017700 – Closeout Procedures Fire & EMS Headquarters Page 6 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. q. Clean luminaires, lamps, globes, and reflectors to function with full efficiency. r. Clean strainers. s. Leave Project clean and ready for occupancy. C. Pest Control: Comply with pest control requirements in Section 015000 "Temporary Facilities and Controls." Prepare written report. D. Construction Waste Disposal: Comply with waste-disposal requirements in Section 017419 "Construction Waste Management and Disposal." 3.2 CORRECTION OF THE WORK A. Complete repair and restoration operations required by "Correction of the Work" Article in Section 017300 "Execution" before requesting inspection for determination of Substantial Completion. END OF SECTION 017700 Montgomery County 017823 – Operation and Maintenance Data Fire & EMS Headquarters Page 1 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 017823 - OPERATION AND MAINTENANCE DATA PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: Administrative and procedural requirements for preparing operation and maintenance manuals, including the following: 1. Operation and maintenance documentation directory manuals. 2. Emergency manuals. 3. Systems and equipment operation manuals. 4. Systems and equipment maintenance manuals. 5. Product maintenance manuals. B. Related Requirements: 1. Section 013300 "Submittal Procedures" for submitting copies of submittals for operation and maintenance manuals. 1.2 DEFINITIONS A. System: An organized collection of parts, equipment, or subsystems united by regular interaction. B. Subsystem: A portion of a system with characteristics similar to a system. 1.3 CLOSEOUT SUBMITTALS A. Submit operation and maintenance manuals indicated. Provide content for each manual as specified in individual Specification Sections, and as reviewed and approved at the time of Section submittals. Submit reviewed manual content formatted and organized as required by this Section. 1. Owner will comment on whether content of operation and maintenance submittals is acceptable. 2. Where applicable, clarify and update reviewed manual content to correspond to revisions and field conditions. B. Format: Submit operation and maintenance manuals in the following formats: 1. Submit on digital media acceptable to Owner for draft submittals and the Final Manual Submittal. Enable reviewer comments on draft submittals. 2. Submit one paper copy of the final manual submittal. C. Initial Manual Submittal: Submit draft copy of each manual at least 30 days before commencing demonstration and training. Owner will comment on whether general scope and content of manual are acceptable. Montgomery County 017823 – Operation and Maintenance Data Fire & EMS Headquarters Page 2 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. D. Final Manual Submittal: Submit each manual in final form prior to requesting inspection for Substantial Completion and at least 15 days before commencing demonstration and training. Owner will return copy with comments. 1. Correct or revise each manual to comply with Owner's comments. Submit copies of each corrected manual within 15 days of receipt of Owner's comments and prior to commencing demonstration and training. E. Comply with Section 017700 "Closeout Procedures" for schedule for submitting operation and maintenance documentation. 1.4 FORMAT OF OPERATION AND MAINTENANCE MANUALS A. Manuals, Electronic Files: Submit manuals in the form of a multiple file composite electronic PDF file for each manual type required. 1. Electronic Files: Use electronic files prepared by manufacturer where available. Where scanning of paper documents is required, configure scanned file for minimum readable file size. 2. File Names and Bookmarks: Bookmark individual documents based on file names. Name document files to correspond to system, subsystem, and equipment names used in manual directory and table of contents. Group documents for each system and subsystem into individual composite bookmarked files, then create composite manual, so that resulting bookmarks reflect the system, subsystem, and equipment names in a readily navigated file tree. Configure electronic manual to display bookmark panel on opening file. B. Manuals, Paper Copy: Submit manuals in the form of hard-copy, bound and labeled volumes. 1. Binders: Heavy-duty, three-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch paper; with clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets. a. If two or more binders are necessary to accommodate data of a system, organize data in each binder into groupings by subsystem and related components. Cross-reference other binders if necessary to provide essential information for proper operation or maintenance of equipment or system. b. Identify each binder on front and spine, with printed title "OPERATION AND MAINTENANCE MANUAL," Project title or name, subject matter of contents, and indicate Specification Section number on bottom of spine. Indicate volume number for multiple-volume sets. 2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section of the manual. Mark each tab to indicate contents. Include typed list of products and major components of equipment included in the section on each divider, cross- referenced to Specification Section number and title of Project Manual. 3. Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose Montgomery County 017823 – Operation and Maintenance Data Fire & EMS Headquarters Page 3 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. diagnostic software storage media for computerized electronic equipment. Enclose title pages and directories in clear plastic sleeves. 4. Supplementary Text: Prepared on 8-1/2-by-11-inch white bond paper. 5. Drawings: Attach reinforced, punched binder tabs on drawings and bind with text. a. If oversize drawings are necessary, fold drawings to same size as text pages and use as foldouts. b. If drawings are too large to be used as foldouts, fold and place drawings in labeled envelopes and bind envelopes in rear of manual. At appropriate locations in manual, insert typewritten pages indicating drawing titles, descriptions of contents, and drawing locations. 1.5 REQUIREMENTS FOR EMERGENCY, OPERATION, AND MAINTENANCE MANUALS A. Organization of Manuals: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual to contain the following materials, in the order listed: 1. Title page. 2. Table of contents. 3. Manual contents. B. Title Page: Include the following information: 1. Subject matter included in manual. 2. Name and address of Project. 3. Name and address of Owner. 4. Date of submittal. 5. Name and contact information for Contractor. 6. Name and contact information for Architect. 7. Names and contact information for major consultants to the Architect that designed the systems contained in the manuals. 8. Cross-reference to related systems in other operation and maintenance manuals. C. Table of Contents: List each product included in manual, identified by product name, indexed to the content of the volume, and cross-referenced to Specification Section number in Project Manual. 1. If operation or maintenance documentation requires more than one volume to accommodate data, include comprehensive table of contents for all volumes in each volume of the set. D. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder. E. Identification: In the documentation directory and in each operation and maintenance manual, identify each system, subsystem, and piece of equipment with same designation used in the Contract Documents. If no designation exists, assign a Montgomery County 017823 – Operation and Maintenance Data Fire & EMS Headquarters Page 4 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. designation in accordance with ASHRAE Guideline 4, "Preparation of Operating and Maintenance Documentation for Building Systems." 1.6 OPERATION AND MAINTENANCE DOCUMENTATION DIRECTORY MANUAL A. Operation and Maintenance Documentation Directory: Prepare a separate manual that provides an organized reference to emergency, operation, and maintenance manuals. List items and their location to facilitate ready access to desired information. Include the following: 1. List of Contractors and Suppliers: List contractors and suppliers by their associated CSI divisions for work performed or material supplied. List shall include all contractors, subcontractors, suppliers, and vendors associated with the Project. Each listing shall include the business name, physical address, website address, contact name, phone number, and email address. 2. List of Systems and Subsystems: List systems alphabetically. Include references to operation and maintenance manuals that contain information about each system. 3. List of Equipment: List equipment for each system, organized alphabetically by system. For pieces of equipment not part of system, list alphabetically in separate list. 4. Tables of Contents: Include a table of contents for each emergency, operation, and maintenance manual. 1.7 EMERGENCY MANUALS A. Emergency Manual: Assemble a complete set of emergency information indicating procedures for use by emergency personnel and by Owner's operating personnel for types of emergencies indicated. B. Content: Organize manual into a separate section for each of the following: 1. Type of emergency. 2. Emergency instructions. 3. Emergency procedures. C. Type of Emergency: Where applicable for each type of emergency indicated below, include instructions and procedures for each system, subsystem, piece of equipment, and component: 1. Fire. 2. Flood. 3. Gas leak. 4. Water leak. 5. Power failure. 6. Water outage. 7. System, subsystem, or equipment failure. 8. Chemical release or spill. D. Emergency Instructions: Describe and explain warnings, trouble indications, error Montgomery County 017823 – Operation and Maintenance Data Fire & EMS Headquarters Page 5 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. messages, and similar codes and signals. Include responsibilities of Owner's operating personnel for notification of Installer, supplier, and manufacturer to maintain warranties. E. Emergency Procedures: Include the following, as applicable: 1. Instructions on stopping. 2. Shutdown instructions for each type of emergency. 3. Operating instructions for conditions outside normal operating limits. 4. Required sequences for electric or electronic systems. 5. Special operating instructions and procedures. 1.8 SYSTEMS AND EQUIPMENT OPERATION MANUALS A. Systems and Equipment Operation Manual: Assemble a complete set of data indicating operation of each system, subsystem, and piece of equipment not part of a system. Include information required for daily operation and management, operating standards, and routine and special operating procedures. 1. Engage a factory-authorized service representative to assemble and prepare information for each system, subsystem, and piece of equipment not part of a system. 2. Prepare a separate manual for each system and subsystem, in the form of an instructional manual for use by Owner's operating personnel. B. Content: In addition to requirements in this Section, include operation data required in individual Specification Sections and the following information: 1. System, subsystem, and equipment descriptions. Use designations for systems and equipment indicated on Contract Documents. 2. Performance and design criteria if Contractor has delegated design responsibility. 3. Operating standards. 4. Operating procedures. 5. Operating logs. 6. Wiring diagrams. 7. Control diagrams. 8. Piped system diagrams. 9. Precautions against improper use. 10. License requirements including inspection and renewal dates. C. Descriptions: Include the following: 1. Product name and model number. Use designations for products indicated on Contract Documents. 2. Manufacturer's name. 3. Equipment identification with serial number of each component. 4. Equipment function. 5. Operating characteristics. 6. Limiting conditions. 7. Performance curves. 8. Engineering data and tests. Montgomery County 017823 – Operation and Maintenance Data Fire & EMS Headquarters Page 6 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 9. Complete nomenclature and number of replacement parts. D. Operating Procedures: Include the following, as applicable: 1. Startup procedures. 2. Equipment or system break-in procedures. 3. Routine and normal operating instructions. 4. Regulation and control procedures. 5. Instructions on stopping. 6. Normal shutdown instructions. 7. Seasonal and weekend operating instructions. 8. Required sequences for electric or electronic systems. 9. Special operating instructions and procedures. E. Systems and Equipment Controls: Describe the sequence of operation, and diagram controls as installed. F. Piped Systems: Diagram piping as installed, and identify color coding where required for identification. 1.9 SYSTEMS AND EQUIPMENT MAINTENANCE MANUALS A. Systems and Equipment Maintenance Manuals: Assemble a complete set of data indicating maintenance of each system, subsystem, and piece of equipment not part of a system. Include manufacturers' maintenance documentation, preventive maintenance procedures and frequency, repair procedures, wiring and systems diagrams, lists of spare parts, and warranty information. 1. Engage a factory-authorized service representative to assemble and prepare information for each system, subsystem, and piece of equipment not part of a system. 2. Prepare a separate manual for each system and subsystem, in the form of an instructional manual for use by Owner's operating personnel. B. Content: For each system, subsystem, and piece of equipment not part of a system, include source information, manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, spare parts list and source information, maintenance service contracts, and warranties and bonds as described below. C. Source Information: List each system, subsystem, and piece of equipment included in manual, identified by product name and arranged to match manual's table of contents. For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross-reference Specification Section number and title in Project Manual and drawing or schedule designation or identifier where applicable. D. Manufacturers' Maintenance Documentation: Include the following information for each component part or piece of equipment: 1. Standard maintenance instructions and bulletins; include only sheets pertinent to product or component installed. Mark each sheet to identify each product or component incorporated into the Work. If data include more than one item in a tabular format, identify each item using appropriate references from the Contract Montgomery County 017823 – Operation and Maintenance Data Fire & EMS Headquarters Page 7 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. Documents. Identify data applicable to the Work and delete references to information not applicable. a. Prepare supplementary text if manufacturers' standard printed data are not available and where the information is necessary for proper operation and maintenance of equipment or systems. 2. Drawings, diagrams, and instructions required for maintenance, including disassembly and component removal, replacement, and assembly. 3. Identification and nomenclature of parts and components. 4. List of items recommended to be stocked as spare parts. E. Maintenance Procedures: Include the following information and items that detail essential maintenance procedures: 1. Test and inspection instructions. 2. Troubleshooting guide. 3. Precautions against improper maintenance. 4. Disassembly; component removal, repair, and replacement; and reassembly instructions. 5. Aligning, adjusting, and checking instructions. 6. Demonstration and training video recording, if available. F. Maintenance and Service Schedules: Include service and lubrication requirements, list of required lubricants for equipment, and separate schedules for preventive and routine maintenance and service with standard time allotment. 1. Scheduled Maintenance and Service: Tabulate actions for daily, weekly, monthly, quarterly, semiannual, and annual frequencies. 2. Maintenance and Service Record: Include manufacturers' forms for recording maintenance. G. Spare Parts List and Source Information: Include lists of replacement and repair parts, with parts identified and cross-referenced to manufacturers' maintenance documentation and local sources of maintenance materials and related services. H. Maintenance Service Contracts: Include copies of maintenance agreements with name and telephone number of service agent. I. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds. 1. Include procedures to follow and required notifications for warranty claims. J. Drawings: Prepare drawings supplementing manufacturers' printed data to illustrate the relationship of component parts of equipment and systems and to illustrate control sequence and flow diagrams. Coordinate these drawings with information contained in record Drawings to ensure correct illustration of completed installation. 1. Do not use original project record documents as part of maintenance manuals. Montgomery County 017823 – Operation and Maintenance Data Fire & EMS Headquarters Page 8 of 8 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1.10 PRODUCT MAINTENANCE MANUALS A. Product Maintenance Manual: Assemble a complete set of maintenance data indicating care and maintenance of each product, material, and finish incorporated into the Work. B. Content: Organize manual into a separate section for each product, material, and finish. Include source information, product information, maintenance procedures, repair materials and sources, and warranties and bonds, as described below. C. Source Information: List each product included in manual, identified by product name and arranged to match manual's table of contents. For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross-reference Specification Section number and title in Project Manual and drawing or schedule designation or identifier where applicable. D. Product Information: Include the following, as applicable: 1. Product name and model number. 2. Manufacturer's name. 3. Color, pattern, and texture. 4. Material and chemical composition. 5. Reordering information for specially manufactured products. E. Maintenance Procedures: Include manufacturer's written recommendations and the following: 1. Inspection procedures. 2. Types of cleaning agents to be used and methods of cleaning. 3. List of cleaning agents and methods of cleaning detrimental to product. 4. Schedule for routine cleaning and maintenance. 5. Repair instructions. F. Repair Materials and Sources: Include lists of materials and local sources of materials and related services. G. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds. 1. Include procedures to follow and required notifications for warranty claims. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 017823 Montgomery County 017839 – Project Record Documents Fire & EMS Headquarters Page 1 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 017839 - PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for Project Record Documents, including the following: 1. Record Drawings. 2. Record specifications. 3. Record Product Data. 4. Miscellaneous record submittals. B. Related Requirements: 1. Section 017300 "Execution" for final property survey. 2. Section 017700 "Closeout Procedures" for general closeout procedures. 3. Section 017823 "Operation and Maintenance Data" for operation and maintenance manual requirements. 1.2 CLOSEOUT SUBMITTALS A. Record Drawings: Comply with the following: 1. Number of Copies: Submit one PDF set of marked-up record prints. B. Record Specifications: Submit annotated PDF electronic files of Project's Specifications, including addenda and Contract modifications. C. Record Product Data: Submit annotated PDF electronic files and directories of each submittal. 1. Where record Product Data are required as part of operation and maintenance manuals, submit duplicate marked-up Product Data as a component of manual. D. Miscellaneous Record Submittals: See other Specification Sections for miscellaneous record-keeping requirements and submittals in connection with various construction activities. Submit annotated PDF electronic files and directories of each submittal. E. Reports: Submit written report weekly indicating items incorporated into Project Record Documents concurrent with progress of the Work, including revisions, concealed conditions, field changes, product selections, and other notations incorporated. 1.3 RECORD DRAWINGS A. Record Prints: Maintain one set of marked-up paper copies of the Contract Drawings and Shop Drawings, incorporating new and revised drawings as modifications are issued. Montgomery County 017839 – Project Record Documents Fire & EMS Headquarters Page 2 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1. Preparation: Mark record prints to show the actual installation, where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to provide information for preparation of corresponding marked-up record prints. a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later. b. Accurately record information in an acceptable drawing technique. c. Record data as soon as possible after obtaining it. d. Record and check the markup before enclosing concealed installations. e. Cross-reference record prints to corresponding photographic documentation. 2. Content: Types of items requiring marking include, but are not limited to, the following: a. Dimensional changes to Drawings. b. Revisions to details shown on Drawings. c. Depths of foundations. d. Locations and depths of underground utilities. e. Revisions to routing of piping and conduits. f. Revisions to electrical circuitry. g. Actual equipment locations. h. Duct size and routing. i. Locations of concealed internal utilities. j. Changes made by Change Order or Construction Change Directive. k. Changes made following Architect's written orders. l. Details not on the original Contract Drawings. m. Field records for variable and concealed conditions. n. Record information on the Work that is shown only schematically. 3. Mark the Contract Drawings and Shop Drawings completely and accurately. Use personnel proficient at recording graphic information in production of marked-up record prints. 4. Mark record prints with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location. 5. Mark important additional information that was either shown schematically or omitted from original Drawings. 6. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable. B. Record Digital Data Files: Immediately before inspection for Certificate of Substantial Completion, review marked-up record prints with Architect. Architect will prepare a full set of corrected digital data files of the Contract Drawings. 1.4 RECORD SPECIFICATIONS A. Preparation: Mark Specifications to indicate the actual product installation, where installation varies from that indicated in Specifications, addenda, and Contract Montgomery County 017839 – Project Record Documents Fire & EMS Headquarters Page 3 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. modifications. 1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later. 2. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected. 3. Record the name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made. 4. For each principal product, indicate whether Record Product Data has been submitted in operation and maintenance manuals instead of submitted as Record Product Data. 5. Note related Change Orders, Record Product Data, and Record Drawings where applicable. B. Format: Submit record specifications as annotated PDF electronic file. 1.5 RECORD PRODUCT DATA A. Recording: Maintain one copy of each submittal during the construction period for Project Record Document purposes. Post changes and revisions to Project Record Documents as they occur; do not wait until end of Project. B. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal. 1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later. 2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation. 3. Note related Change Orders, Record Specifications, and Record Drawings where applicable. C. Format: Submit Record Product Data as annotated PDF electronic file. 1. Include Record Product Data directory organized by Specification Section number and title, electronically linked to each item of Record Product Data. 1.6 MISCELLANEOUS RECORD SUBMITTALS A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference. B. Format: Submit miscellaneous record submittals as PDF electronic file. 1. Include miscellaneous record submittals directory organized by Specification Section number and title, electronically linked to each item of miscellaneous record submittals. Montgomery County 017839 – Project Record Documents Fire & EMS Headquarters Page 4 of 4 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1.7 MAINTENANCE OF RECORD DOCUMENTS A. Maintenance of Record Documents: Store Record Documents in the field office apart from the Contract Documents used for construction. Do not use Project Record Documents for construction purposes. Maintain Record Documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Provide access to Project Record Documents for Architect's reference during normal working hours. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 017839 Montgomery County 017900 – Demonstration and Training Fire & EMS Headquarters Page 1 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. SECTION 017900 - DEMONSTRATION AND TRAINING PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for instructing Owner's personnel, including the following: 1. Instruction in operation and maintenance of systems, subsystems, and equipment. 2. Demonstration and training video recordings. 1.2 INFORMATIONAL SUBMITTALS A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module. 1. Indicate proposed training modules using manufacturer-produced demonstration and training video recordings for systems, equipment, and products in lieu of video recording of live instructional module. B. Attendance Record: For each training module, submit list of participants and length of instruction time. 1.3 CLOSEOUT SUBMITTALS A. Demonstration and Training Video Recordings: Submit two copies within seven days of end of each training module. 1. Identification: On each copy, provide an applied label with the following information: a. Name of Project. b. Name and address of videographer. c. Name of Architect. d. Name of Construction Manager. e. Name of Contractor. f. Date of video recording. 2. Transcript: a. Prepared in PDF electronic format. Include a cover sheet with same label information as the corresponding video recording and a table of contents with links to corresponding training components. Include name of Project Montgomery County 017900 – Demonstration and Training Fire & EMS Headquarters Page 2 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. and date of video recording on each page. 3. At completion of training, submit complete training manual(s) for Owner's use prepared in same PDF file format required for operation and maintenance manuals specified in Section 017823 "Operation and Maintenance Data." 1.4 QUALITY ASSURANCE A. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance. B. Instructor Qualifications: A factory-authorized service representative, complying with requirements in Section 014000 "Quality Requirements," experienced in operation and maintenance procedures and training. C. Videographer Qualifications: A professional videographer who is experienced photographing demonstration and training events similar to those required. D. Preinstruction Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to demonstration and training including, but not limited to, the following: 1. Inspect and discuss locations and other facilities required for instruction. 2. Review and finalize instruction schedule and verify availability of educational materials, instructors' personnel, audiovisual equipment, and facilities needed to avoid delays. 3. Review required content of instruction. 4. For instruction that must occur outside, review weather and forecasted weather conditions and procedures to follow if conditions are unfavorable. 1.5 COORDINATION A. Coordinate instruction schedule with Owner's operations. Adjust schedule as required to minimize disrupting Owner's operations and to ensure availability of Owner's personnel. B. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content. C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data have been reviewed and approved by Architect. 1.6 INSTRUCTION PROGRAM A. Program Structure: Develop an instruction program that includes individual training modules for each system and for equipment not part of a system, as required by individual Specification Sections. B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to Montgomery County 017900 – Demonstration and Training Fire & EMS Headquarters Page 3 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. master. For each module, include instruction for the following as applicable to the system, equipment, or component: 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: a. System, subsystem, and equipment descriptions. b. Performance and design criteria if Contractor is delegated design responsibility. c. Operating standards. d. Regulatory requirements. e. Equipment function. f. Operating characteristics. g. Limiting conditions. h. Performance curves. 2. Documentation: Review the following items in detail: a. Emergency manuals. b. Systems and equipment operation manuals. c. Systems and equipment maintenance manuals. d. Product maintenance manuals. e. Project Record Documents. f. Identification systems. g. Warranties and bonds. h. Maintenance service agreements and similar continuing commitments. 3. Emergencies: Include the following, as applicable: a. Instructions on meaning of warnings, trouble indications, and error messages. b. Instructions on stopping. c. Shutdown instructions for each type of emergency. d. Operating instructions for conditions outside of normal operating limits. e. Sequences for electric or electronic systems. f. Special operating instructions and procedures. 4. Operations: Include the following, as applicable: a. Startup procedures. b. Equipment or system break-in procedures. c. Routine and normal operating instructions. d. Regulation and control procedures. e. Control sequences. f. Safety procedures. g. Instructions on stopping. h. Normal shutdown instructions. i. Operating procedures for emergencies. j. Operating procedures for system, subsystem, or equipment failure. k. Seasonal and weekend operating instructions. l. Required sequences for electric or electronic systems. Montgomery County 017900 – Demonstration and Training Fire & EMS Headquarters Page 4 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. m. Special operating instructions and procedures. 5. Adjustments: Include the following: a. Alignments. b. Checking adjustments. c. Noise and vibration adjustments. d. Economy and efficiency adjustments. 6. Troubleshooting: Include the following: a. Diagnostic instructions. b. Test and inspection procedures. 7. Maintenance: Include the following: a. Inspection procedures. b. Types of cleaning agents to be used and methods of cleaning. c. List of cleaning agents and methods of cleaning detrimental to product. d. Procedures for routine cleaning. e. Procedures for preventive maintenance. f. Procedures for routine maintenance. g. Instruction on use of special tools. 8. Repairs: Include the following: a. Diagnosis instructions. b. Repair instructions. c. Disassembly; component removal, repair, and replacement; and reassembly instructions. d. Instructions for identifying parts and components. e. Review of spare parts needed for operation and maintenance. 1.7 PREPARATION A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 017823 "Operation and Maintenance Data." B. Set up instructional equipment at instruction location. 1.8 INSTRUCTION A. Facilitator: Engage a qualified facilitator to prepare instruction program and training modules, to coordinate instructors, and to coordinate between Contractor and Owner for number of participants, instruction times, and location. B. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. 1. Architect will furnish an instructor to describe basis of system design, operational Montgomery County 017900 – Demonstration and Training Fire & EMS Headquarters Page 5 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. requirements, criteria, and regulatory requirements. 2. Owner will furnish an instructor to describe Owner's operational philosophy. 3. Owner will furnish Contractor with names and positions of participants. C. Scheduling: Provide instruction at mutually agreed-on times. For equipment that requires seasonal operation, provide similar instruction at start of each season. 1. Schedule training with Owner with at least seven days' advance notice. D. Training Location and Reference Material: Conduct training on-site in the completed and fully operational facility using the actual equipment in-place. Conduct training using final operation and maintenance data submittals. E. Cleanup: Collect used and leftover educational materials and give to Owner. Remove instructional equipment. Restore systems and equipment to condition existing before initial training use. 1.9 DEMONSTRATION AND TRAINING VIDEO RECORDINGS A. General: Engage a qualified commercial videographer to record demonstration and training video recordings. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice. 1. At beginning of each training module, record each chart containing learning objective and lesson outline. B. Digital Video Recordings: Provide high-resolution, digital video in MPEG format, produced by a digital camera with minimum sensor resolution of 12 megapixels and capable of recording in full HD mode with vibration reduction technology. 1. Submit video recordings on CD-ROM or thumb drive. 2. File Hierarchy: Organize folder structure and file locations in accordance with Project Manual table of contents. Provide complete screen-based menu. 3. File Names: Utilize file names based on name of equipment generally described in video segment, as identified in Project specifications. 4. Contractor and Installer Contact File: Using appropriate software, create a file for inclusion on the equipment demonstration and training recording that describes the following for each Contractor involved on the Project, arranged in accordance with Project Manual table of contents: a. Name of Contractor/Installer. b. Business address. c. Business phone number. d. Point of contact. e. Email address. C. Recording: Mount camera on tripod before starting recording, unless otherwise necessary to adequately cover area of demonstration and training. Display continuous running time. Montgomery County 017900 – Demonstration and Training Fire & EMS Headquarters Page 6 of 6 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document. 1. Film training session(s) in segments not to exceed 15 minutes. a. Produce segments to present a single significant piece of equipment per segment. b. Organize segments with multiple pieces of equipment to follow order of Project Manual table of contents. c. Where a training session on a particular piece of equipment exceeds 15 minutes, stop filming and pause training session. Begin training session again upon commencement of new filming segment. D. Light Levels: Verify light levels are adequate to properly light equipment. Verify equipment markings are clearly visible prior to recording. 1. Furnish additional portable lighting as required. E. Narration: Describe scenes on video recording by audio narration by microphone while video recording is recorded. Include description of items being viewed. F. Transcript: Provide a transcript of the narration. Display images and running time captured from videotape opposite the corresponding narration segment. G. Preproduced Video Recordings: Provide video recordings used as a component of training modules in same format as recordings of live training. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 017900 Montgomery County Part VI – Reference Documents Fire & EMS Headquarters Page 244 of 286 Part VI – Reference Documents Building Permit #:__________________________________VUSBC Edition: ________________________ Project Name: __________________________________Group: ____ Construction type: _____________ Project Address: _______________________________________________________________________ Building Owner’s Name: (Print) _________________________ (Sign) ____________________________ Owner’s Address: ______________________________________________________________________ This Statement of Special Inspections is submitted as a condition for permit issuance in accordance with the VUSBC. The Special Inspections Schedule is an integral part of the Statement of Special Inspections. The Special Inspections Engineer of Record (SIER) shall keep records of special inspections and shall furnish copies of inspections and testing reports to the Town of Christiansburg Building Department and to the Registered Design Professional in Responsible Charge (RDPRC). Discrepancies from the approved plans and specifications and code violations observed during conduct of special inspections services shall be brought to the immediate attention of the contractor for correction, to the attention of the Town of Christiansburg Building Department, and to the RDPRC. A Final Report of Special Inspections, documenting completion of specified special inspections and correction of any discrepancies and observed code violations shall be submitted to and approved by the Town of Christiansburg Building Department prior to the concealment inspection by the Town of Christiansburg Building Department. Note 1: For retaining walls use pages 1 and 8 only Note 2: For smoke control systems, a separate Statement of Special Inspections is required in addition to that submitted for the rest of the project. The Mechanical Engineer of Record will sign off as RDPRC for the smoke control system. The SIER for the smoke control system shall have expertise in fire protection, mechanical engineering and certification as an air balancer. TOWN OF CHRISTIANSBURG STATEMENT OF SPECIAL INSPECTIONS Please provide the Name, License and Company information of the following: Permit Applicant (If not Owner): Signature / Date: _____________________________ Printed Name: ______________________________________ Owner’s Authorization (If other than Applicant): Signature / Date: _____________________________________ Printed Name: _______________________________________ Primary Registered Design Professional in charge of the project: (Review and Acceptance of Schedule) Signature / Date: ______________________________________ Printed Name: ________________________________________ Architect of Record: Signature / Date: _______________________________________ Printed Name: _________________________________________ Geotechnical Engineer of Record: Signature / Date: _______________________________________ Printed Name: _________________________________________ Sc hedule of Special Inspections Prepared By: Special Inspector/ Engineer of Record: Signature / Date: ________________________________________ Printed Name: __________________________________________ Building Official’s Acceptance: Signature / Date: ________________________________________ Printed Name: __________________________________________ Registered Design Professionals Seal 9/30/2026 10/8/2026 9/30/2026 2Scope of Service for Verification and Inspection Continuous Periodic Ref. Std. IBC Party Start/Completion Date Activity, verification, and inspection Steel Construction 1704.3 1. High strength bolts, nuts and washers Applicable ASTM material specifications; AISC 360 Sec. A3.3 a. Identification markings conform to ASTM specified in the approved construction documents X b. Manufacture certificate of compliance X 2. High strength bolting 1708.4 a. Bearing type connection X AISC 360, M2.5 b. slip critical connections X X 3.Structural steel a. Identification markings conform to ASTM specified in the approved construction documents ASTM 6 or ASTM A 568 b. manufacturer’s certified mill test reports 4. Weld filler AISC, Sec. A3.5 a. Identification markings conform to ASTM specified in the approved construction documents b. Manufacturer’s certificate of compliance required 5. Welding AWS D1.1 1704.3.1 a. Structural steel 1. Complete partial penetration groove welds X 2. Multi-pass fillet welds X 3. Single-pass fillet welds >5/16” X 4. Single pass fillet welds < or = 5/16” X 5. Floor and roof deck welding X AWS D1.3 b. Reinforcing steel AWS D1.4, ACI 318:3.5.2 1. Verification of weld-ability of reinforcing steel other than ASTM 706 2. Reinforcing steel- resisting flexural and axial forces intermediate and special moment frames, and boundary elements of special reinforcing concrete shear walls and shear reinforcement X 3. Shear reinforcement X 4. Other reinforcement 6. Steel joint details X 1704.3.2 a. Details such as bracing and stiffening b. Member locations c. Application of joint details at each connection 7. Steel Fabrication 1704.2 a. Fabricator is AISC certified b. Verify that fabricator maintains detailed fabrication and quality control procedures 8. Others 3Special Inspections Schedule Building Permit #_______________________________ Scope of Service for Verification and inspection Activity, verification and Inspection Continuous Periodic Ref. Std. IBC Party Start/comp. date Concrete construction 1704.4 SIER 1. Reinforcing steel including pre-stressing tendons and placement X ACI 318: 3.5, 7.2-7.7 1913.4 2. Reinforcing steel welding AWS D1.4, ACI 318:3.5.2 3. Bolts installed in concrete X 1911.5 4. Verify use of design mix X ACI:Ch.4, 5.2-5.4 1904.2.2, 1913.2, 1913.3 5. At the time fresh concrete is sampled to fabricate specimens for strength tests, perform slump and air content tests, and determine the temperature of the concrete X ASTM C 172, ASTM C 31, ACI 318: 5.6, 5.8 1913.10 6. Inspection of concrete and shotcrete placement for proper application techniques X ACI 318:5.9-5.10 1913.6-8 7. Inspection and maintenance of curing temperature and techniques X ACI 318: 5.11-5.13 1913.9 8. Inspections of pre-stressed concrete: a: Application of pre-stressed forces b. grouting of bonded pre-stressing tendons in the seismic force resisting system X ACI 318: 18.20, 18.18.4 9. Manufacture of precast/ tilt-up concrete panels 1704.2 10. Erection of precast/ tilt-up panels concrete members ACI 318: Ch. 16 11. Verification of in-situ concrete strength , prior to stressing of tendons in post tensioned concrete and prior to removal of shores and forms from beams and structural slabs X ACI 318: 6.2 12. Inspect form work for shape, location and dimensions of the concrete member being formed X ACI 318: 6.1.1 13. Other X 4Special Inspections Schedule Building Permit #:______________________________________________ Scope of Service for Verification and Inspection Activity, Verification and Inspection Continuous Periodic Reference Standard Reference Standard IBC Party Start/compl. date Masonry construction ACI 530/ASCE 5/TMS 602 ACI530.1/ASCE6/ TMS 602 1704.5 Masonry Level 1 Inspections 1. As masonry construction begins, ensure compliance: SIER a. Proportions of site prepared mortar X Art 2.6A b. Construction of mortar joints X Art 3.3B c. Location of reinforcement and connectors X Art 3.4,3.6 d. Pre-stressing technique X Art 3.6B e. Grade and size of pre-stressing tendons and anchorage X Art 2.4B, 2.4H 2. Inspection shall verify: SIER a. Size and location of structural elements X Art 3.3G b. Type, size and location of anchors, including other details of anchorage of masonry to structural members, frames, or other construction X Sec 1.2.2(e), 2.1.4, 3.1.6 c. Specified size, grade, and type reinforcement X Sec 1.13 Art 2.4,3.4 d. Welding of reinforcing bars X Sec 2.1.10.7.2,3.3.3.4(b) e. Protection masonry during cold weather (<40 F) or (>90 F) X Art 1.8C, 1.8D 2104.3-4 f. Application and measurement of pre-stressing force X Art 3.6B 3. Prior to grouting verify the following to insure compliance: SIER a. Grout space is clean X Art 3.2 b. Placement of reinforcement, connectors, pre-stressing tendons and anchors X Sec 1.13 Art 3.4 c. Proportions of site prepares grout and pre-stressing grout for bonded tendons X Art 2.6B d. Construction of mortar joints X Art 3.3B 4. Grout placement verified to assure compliance with code and construction documents: X Art 3.5 SIER a. Grouting of pre-stressed bonded tendons X Art 3.6C 5. Preparation of any grout or mortar specimens and/or prisms shall be observed. X Art 1.4 2105.2.2, 2105.3 SIER 6. Compliance with required inspection provisions of the construction documents and the approved submittals shall be verified X Art 1.5 SIER 7. Other 5 Scope of Service for Verification and Inspection Activity, Verification and Inspection Continu-ous Period-ic Reference Reference IBC Party Start/compl. Date Masonry Level 2 Special Inspections ACI 530/ ASCE 5/ TMS 602 ACI 530.1/ASCE 6/ TMS 602 1. From the beginning of masonry construction the following shall be verified: SIER a. Proportions of site prepared mortar, grout, pre-stressing grout for bonded tendons X Art. 2.6A b. Placement of masonry units and construction of mortar joints X Art 3.3B c. Placement of reinforcement, connector, pre-stressing tendons and anchorage X Sec 1.13 Art 3.4, 3.6A d. Grout space clean prior to grout placement X Art 3.2D e. Placement of grout X Art 3.5 f. Placement of pre-stressing grout X Art 3.6C 2. The inspection shall verify: SIER a. Size and location of structural steel X Art 3.3G b. Type, size and location of anchors including other details of anchorage of masonry to structural members, frames or other construction X Sec 1.2.2e, 2.1.4, 3.1.6 c. Specified size, grade and type of reinforcement X Sec 1.13 Art 2.4, 3.4 d. Welding of reinforcing bars X Sec 2.1.10.7.2, 3.3.3.4b e. Protection from weather <40 F/ >90 F X Art 1.8C-D 2104.3, 2104.4 f. Application and measurement of pre-stressing force X Art 3.6B 3. Preparation of any required grout or mortar specimens, and/or prisms shall be observed X Art 1.4 2105.2.2, 2105.3 4. Compliance with required inspection provisions of the construction documents and the approved submittals shall be verified SIER 5. Other Wood Construction 1704.3 SIER 1. Verify fabrication of wood structural element sand assembly a. Verify fabrication of wood structural member (specify element) X b. Verify assembly of structural elements X 2. High load diaphragms in accordance table 2306.3.2 1704.6.1 SIER a. Verify grade and thickness of structural panel sheathing as shown on the approved construction documents X b. Verify nominal size of framing members at adjoining panel edges, nail spacing and length, the number of fastener lines and spacing between fasteners in each line and edge margins per approved construction documents X 6Special Inspections Schedule Building Permit# _____________________________ Scope of Service for Verification and Inspection Activity, Verification And Inspection Continuous Periodic Reference: IBC Party Start/ Compl. Date Soils 1704.7 SIER 1. Controlled fill placed under site pad 2. Controlled fill placed under this permit 3. Verify materials below footing are adequate to achieve the design bearing capacity X 4. Verify excavations are extended to proper depth and have reached proper material X 5. Perform classification and testing of controlled fill materials X 6. Verify use of proper materials, densities and lift thicknesses during placement and compaction of controlled fill. X 7. Prior to placement of controlled fill, observe sub grade verify that site has been properly prepared X Footing and Foundation 1. Verify sub grade bearing, footing depth, footing dimension X 2. Verify installation of tile drain X Pile Foundations 1704.8 SIER 1. Verify pile material, sizes, and lengths comply with requirements X 2. Determine capacities of test piles and conduct additional load tests as required X 3. Observe driving operations and maintain complete and accurate records of each pile X 4. Verify placement, location, confirm type and size of hammer, record number of blows per foot of penetration, determine required penetrations to achieve design capacity, record tip and butt elevations and document any pile damage X 5. For steel piles perform additional inspections per1704.3 6. For concrete piles perform additional inspections per 1704.4 7. For specialty piles perform additional inspections per RDPRC 8. For augered uncased and caissons piles addition inspections per 1704.9 Pier Foundations 17004.9 SEIR 1. Observe drilling operations and maintain accurate and complete records of each pier X 2. Verify placement locations, plumb, confirm pier diameters, bell diameters, lengths, embedment into bedrock, and adequate end bearing strata capacity X 3. For concrete piers perform additional inspections per 1704.4 4. For masonry piers perform additional inspections per 1704.5 7Special Inspections Schedule Building Permit# __________________________ Scope of Service for Verification and Inspection Activity, Verification and Inspection Continuous Periodic Reference Standard IBC Party Start/Comp. date Spray applied fire resistant materials 1704.10 SIER 1. Verify structural member surface conditions X 2. Verify application of materials per manufacturer’s instructions X X 3. Verify thickness of applied materials X 4. Verify bond strength/ adhesion of applied materials X Mastic and Intumescent Fire Resistant Coatings AWCI 12-B 1704.11 SIER 1. Verify structural member/deck surface conditions X 2. Verify application of materials per manufacturer’s instructions X X 3. Verify application thickness of materials X 4. Verify bond strength/ adhesion of materials X Exterior Insulation and Finish System 1704.12 SIER 1. Installed per approved construction documents 2. EIFS Contractor card, prepared and signed by EIFS installer after installation of the EIFS, attach to final Report of Special Inspections Smoke Control Systems 1704.14 SIER 1. Verify Compliance with required inspection provisions of approved construction documents and approved submittals 2. Submit detailed report of scope of services including protocol of inspections per 1704.14 Other At the time of these inspections, all items inspected were in compliance with approved construction documents and VUSBC building permits were posted on site, E and S was found to be controlled and properly installed Approved lot grading plan approved lot grading plan and sound engineering practice Sound engineering practice (only retaining wall that did not require an approved grading plan) Sound engineering practice (only for additions, alterations or repairs) Name, company and address of Special Inspections Engineer of Record: Name, company and address of Inspection and Testing Agency: 8Special Inspections Schedule Building Permit# ______________________ Special Inspection Schedule for Earth Retaining Structures Type of Retaining Wall: Earth wall Reinforced Earth w/geogrid Masonry Sheet Pile Cast in place concrete Timber pile H pile Other _________________________________________ Activity Scope of Service for Verification and Inspection Responsible Party Start/ Compl. date Footing, Foundation Compacted earth Gravel: 21A 57 Concrete reinforcement Concrete Pile or Caissons Other_________________________________________ Backfill Information Drains per plan Compacted fill: Onsite material or Offsite material Wall Geometry Batter per plan Height per plan Surcharge per plan Slope of fill per plan Compaction Testing Per approved drawings Per geotechnical engineer’s recommendation Compaction test not needed Layout Information Per approved plan Per approved revised plan At the time of these inspections, all items inspected were in compliance with approved construction documents and VUSBC building permits were posted on site, E and S was found to be controlled and properly installed: Approved lot grading plan approved lot grading plan and sound engineering practice Sound engineering practice (only retaining wall that did not require an approved grading plan) Sound engineering practice (only for additions, alterations or repairs) Name, company and address of Special Inspections Engineer of Record: Name, company and address of Inspection and Testing Agency: Building Department: Backwater Valve Certification This form is applicable to all new residential and commercial projects. In addition, all existing buildings and additions that install new plumbing fixtures. Permit Number: Location of Construction: Builder/Contractor: Email: Phone Number: I/We certify that the elevation of the flood level rim of the lowest fixture or floor drain has been compared to the elevation of the next upstream manhole and is compliance with the backwater valve requirements of the current edition of the Virginia Uniform Statewide Building Code/Virginia Plumbing Code, Section 715, and the Virginia Residential Code, Section P3008. To show compliance with this requirement, I have done the following: (Check the applicable method and show data when appropriate). The lowest fixture is above the upstream manhole. A backwater valve is not required. The lowest fixture is below the upstream manhole. A backwater valve is required to be installed. I verified the elevations with an instrument and the lowest fixture is above the upstream manhole. A backwater valve is not required. The fixture is feet above the manhole. I verified the elevations with an instrument and the lowest fixture is below the upstream manhole. A backwater valve is required to be installed. The fixture is feet below the manhole. I had a licensed professional verify the elevation with an instrument and the lowest fixture is above the upstream manhole. A backwater valve is not required to be installed. (Attach report or letter sealed and signed). I had a licensed professional verify the elevation with an instrument and the lowest fixture is below the upstream manhole. AS backwater valve is required to be installed. (Attach report and letter sealed and signed). Signature of Builder/Contractor/Designer: Date: Printed Name: USDD.VA_MONT.EMSHQ.FSA.DWGdesign byA B C D 4 3 2 1 4 2 1 A B C D 3 projectbuildingfilenamedateT H I S D O C U M E N T C O N T A I N S CONFIDENTIAL AND PROPRIETARY I N F O R M A T I O N W H I C H I S T H E E X C L U S I V E P R O P E R T Y O F U S D I G I T A L D E S I G N S , I N C . R EPR O D UC T ION , DI STR IBU T ION OR USE BY OTHERS, IN WHOLE OR I N P A R T , I S N O T P E R M I T T E D W I T H O U T T H E W R I T T E N AUTHORIZATION FROM US DIGITAL D E S I G N S , I N C . PoE = G2 ATX Power-over-Ethernet (PoE) ports 1...8 and G2 Expansion Module ports 1...12 A.n = G2 ATX Amplifier 1...4 EA.n = G2 External Amplifier 1...n CH.n = G2 Message Remote 2 Channel 1 or 2 5/21/2026 - 1:29PMSYMBOL DESCRIPTION EXTERNAL AMPLIFIER ATX UPS AMP EXP addressATX LT G2 I/O REMOTE PUSH BUTTON - RED G2 STROBE LIGHT SPEAKER, WEATHER-PROOF SPEAKER, FLUSH MOUNT SPEAKER, METAL BOX G2 LED SPEAKER, FLUSH MOUNT G2 LED SPEAKER, METAL BOX OEM TRANSFORMER G2 HDTV REMOTE G2 COLOR INDICATOR REMOTE OEM FLAT PANEL MONITOR, XX", WITH MOUNT G2 MESSAGE SIGN (STANDARD 24") VOLUME CONTROL (CUSTOMER SUPPLIED) G2 ROOM REMOTE 2 ARTICULATING ARM MOUNT - LONG ADAPTER PLATE DOUBLE PUSH BUTTON - BLACK G2 OMNIALERT STROBE SPEAKER G2 MESSAGE SIGN (MINI 12") G2 MESSAGE SIGN (EXTENDED 36") ADAPTER PLATE SINGLE G2 MESSAGE REMOTE 2 TVR PB BLACK PB RED CIR STR I/O T MR2 RR2 S S S ADS MSE MSML MSS MSM VC S S ADP MSML S G2 COLOR INDICATOR REMOTE BACK BOX FPD MOUNT FPM - XX" G2 VIDEO DOOR STATION VDS G2 LCD MESSAGE SIGNMS-LCD UPS-WMB AMP-S SHELF/BRACKET, WALL-MOUNT FOR UPS SHELF, UNDER TABLE OR WALL MOUNT LAR SM-RR2-BB G2 LOCAL ALERTING REMOTE MODULE G2 REMOTE USER INTERFACE MODULERUI SM-CIR-BBSM-CIR-BB SM-RR2-BB G2 ROOM REMOTE SURFACE MOUNT BOX RACK MOUNT EARS FOR G2 ATX OR G2 EXP G2 ATX STATION CONTROLLER G2 EXPANSION MODULE G2 ATX LITE STATION CONTROLLER G2 UNINTERUPTIBLE POWER SUPPLY MONTGOMERY COUNTY DEPARTMENT OF FIRE & EMS, VAFIRE STATION - EMS HQ305 ROANOKE ST, CHRISTIANSBURG, VA, 24073DWKINSTALLER NOTES: 1. INSTALLER TO VERIFY WALL AND CEILING TYPE TO DETERMINE EQUIPMENT MOUNTING TYPE (FLUSH OR SURFACE). 2. INSTALLER TO COORDINATE CONNECTION BETWEEN ATX STATION CONTROLLER’S LINE-LEVEL AUDIO OUTPUT AND (EXISTING) OWNER-FURNISHED HOUSE AUDIO SYSTEM (AMP). (IF APPLICABLE) 3. INSTALLER TO PROVIDE CAT6 & 16/4 CABLES FROM ATX CONTROLLER TO CUSTOMER'S STATION RADIO FOR BACKUP. 4. INSTALLER TO COORDINATE CONNECTION BETWEEN EXISTING STATION LIGHTING CONTROL SYSTEM AND RELAY OUTPUT FROM ATX STATION CONTROLLER OR I/O REMOTE WITH OWNER. (IF APPLICABLE) 5. VOLUME CONTROL PROVIDED BY OWNER OR INSTALLER IF SHOWN ON DRAWING. 6. INSTALLER TO VERIFY AND CONSIDER LOCATION(S) OF NETWORK AND RADIO CONNECTIONS. 7. INSTALLER MUST RUN A GROUNDING WIRE (PER CODE) FROM ATX TO STATION GROUND. NOTES: 1. SEE ARCHITECTURAL SPECIFICATIONS FOR ALL ROUGH-IN AND INSTALLATION DETAILS. 2. US DIGITAL DESIGNS DOES NOT SUPPLY CABLE,WIRE, BACK BOXES, CONDUITS, OR MOUNTING FASTENERS. 3. PHOENIX G2 SYSTEM IS ABLE TO SIGNAL OWNER-FURNISHED SYSTEMS, (EXHAUST, LIGHT, GAS SHUT OFF, ETC.). USDD DOES NOT SUPPLY THESE SYSTEMS AND CANNOT WARRANT OR SUPPORT ANY OF THEIR PERFORMANCE BEYOND THE TRANSMISSION OF RELAY SIGNAL TO THEM. 4. US DIGITAL DESIGNS FIRE STATION ALERTING PLANS ARE DIAGRAMMATIC AND FOR QUOTING PURPOSES ONLY. DRAWING IS NOT TO SCALE. PB BLACK PB RED DOORBELL EMERGENCY ALERT S EA.1 S S PB BLACK PB RED DOORBELL EMERGENCY ALERT ADS MSML MSE PoE ADS MSML MSE PoE VC TVRTO ATX SWITCH ONLY MS-LCDPoE MS-LCDPoE RR2 PoE RR2 PoE RR2 RR2 PoE A.1 A.1 A.3 A.2 A.4 S S S S S S S S SSS SSSS S S S S S S S S VC PB BLACK DOORBELL UPS UPS-WMB ATX AMP AMP-S I/O PoE US DIGITAL DESIGNS Count Name 1 G2 ATX STATION CONTROLLER (ATX) 1 G2 ATX-EXP RACK EARS (ATX-E) 1 UPS (UPS-STD) 1 UPS SHELF-BRACKET WALL-MOUNT (UPS-WMB) 1 EXTERNAL AMPLIFIER (AMP-70V) 1 AMP SHELF-WALL MOUNT (AMP-S) 1 G2 HDTV REMOTE (TV-R) 1 G2 IO REMOTE (IOR) 3 PUSH BUTTON (PB-B) 2 PUSH BUTTON (PB-R) 2 G2 MESSAGE SIGN LCD (USDD-LCD-SIGN) 2 G2 MESSAGE SIGN EXTENDED (MS-G-E) 2 G2 MS ADAPTOR PLATE SINGLE (MS-AP-S) 2 MS MOUNT ARTICULATING (MS-MNT) 4 G2 ROOM REMOTE 2 (RR-2) 12 G2 LED SPEAKER (SPK-LED-FM) 16 G2 SPEAKER - STANDARD (SPK-STD-FM) 3 SPEAKER WEATHER-PROOF (SPK-W-SM) 2 VOLUME CONTROL (CUSTOMER SUPPLIED) S S S S S US DIGITAL DESIGNS Count Name 8 G2 PoE PORT REQUIRED PROPRIETARY and CONFIDENTIAL DEVICE NAME PLAN DESIGNATOR USDD DESIGN SYMBOL PICTURE MOUNTING OPTIONS PRODUCT DIMENSIONS MOUNTING HEIGHT CONDUIT NEEDS BOX NEEDS ATX Station Controller ATX Rack-Mounted or Wall Mounted 17.25" x 17.50" x 6.06"Determined by Installer / Customer 2" Sleeve piped to above mounting location N/A ATX Expansion Module ATX-EXP Rack-Mounted or Wall Mounted 17.25" x 17.50" x 6.06"Determined by Installer / Customer 2" Sleeve piped to above mounting location N/A CyberPower UPS Battery Backup UPS Rack-Mounted or Wall Mounted 3.90" x 11.00" x 14.00"Determined by Installer / Customer N/A N/A Extron Amplifier AMP Rack-Mounted or Wall Mounted 8.70" x 1.70" x 9.50"Determined by Installer / Customer **Utilizes 2" ATX sleeve N/A G2 I/O Remote I/0 Rack-Mounted or Wall Mounted 6.75" x 2.00" x 9.75"Determined by Installer / Customer **Utilizes 2" ATX or EXP sleeve N/A G2 Message Remote 2 MR2 Rack-Mounted or Wall Mounted 6.50" x 2.00" x 6.00"Determined by Installer / Customer **Utilizes 2" ATX or EXP sleeve N/A G2 Message Sign GSS Apparatus Bay 24.80" x 3.70" x 1.60"9.00' AFF 3/4" EMT Single gang box, vertical G2 Message Sign GSS Interior Wall 24.80" x 3.70" x 1.60"6.00" from top of door frame or 12.00" from finished ceiling when not above door 3/4" EMT stub to accessible ceiling Single gang box, horizontal G2 Strobe Light STR Interior Wall 8.00" x 6.00" x 2.40"12.00" from finished ceiling 3/4" EMT stub to accessible ceiling Single gang box, vertical Push Button (Red)PB-R ANY Button is mounted direct to a single gang face plate Switch height 3/4" EMT stub to accessible ceiling Single gang box, vertical Push Button (Black)PB-B Same as above Only in Red ANY Button is mounted direct to a single gang face plate Switch height 3/4" EMT stub to accessible ceiling Single gang box, vertical G2 Room Remote 2 RR2 ALL 11.20" x 8.20" x 1.90"52" AFF; Rough-In Box 4-6" away from any light switch 3/4" EMT stub to accessible ceiling 4-Gang Box (RACO #943 - 2.5"D) w/ mud ring G2 HDTV Remote TVR Wall 3.60" x 1.20" x 2.90" First Option: Flush to wall behind television Second option: Mount near an existing or new outlet on wall or above ceiling 3/4" EMT stub to accessible ceiling N/A G2 Color Indicator Remote CIR Apparatus Bay (wall oR column)9.50" x 4.75" x 1.10"16.00' AFF 3/4" EMT 4-Gang Box (RACO #943 - 2.5"D) w/ mud ring G2 Color Indicator Remote CIR Interior Wall 9.50" x 4.75" x 1.10"12.00" from finished ceiling 3/4" EMT stub to accessible ceiling 4-Gang Box (RACO #943 - 2.5"D) w/ mud ring Bogan Weatherproof Speaker S Apparatus Bay 9.00" x 8.00"12.00' AFF 3/4" EMT Single gang box, vertical G2 LED Flush Mount Speaker S Drop Ceiling 12 5/8" Diameter Determined by Installer / Customer N/A **For installation in hard ceiling only, requires backbox (Bogen #RE84 & TB8) Flush Mount Speaker S Drop Ceiling 12 5/8" Diameter Determined by Installer / Customer N/A **For installation in hard ceiling only, requires backbox (Bogen #RE84 & TB8) G2 LED Metal Box Speaker S Same as below with LED ring Interior Wall or Hard Ceiling 12.00" x 12.00"Determined by Installer / Customer 3/4" EMT stub to accessible ceiling N/A Metal Box Speaker S Interior Wall or Hard Ceiling 12.00" x 12.00"Determined by Installer / Customer 3/4" EMT stub to accessible ceiling N/A G2 Omni Alert Strobe Speaker S Apparatus Bay 13-inches high x 15-inches diameter Determined by Installer / Customer 3/4" EMT N/A